Schedule, Milestones and Dependencies
Assume you understand the basic relationship between a master service agreement (MSA) and a statement of work (SOW). This chapter focuses on turning project timing into terms that the client and vendor can use to manage performance and payment.
Build a schedule that assigns responsibility
A SOW schedule should do more than list target dates. It should connect each milestone to:
- A specific deliverable or activity
- The party responsible for completing it
- Any required client dependency
- A review or acceptance period
- The consequence of a missed date
A milestone is a meaningful checkpoint in a project. A deliverable is the work product produced for the client. A milestone may mark delivery, approval, testing, or another event that affects the next stage.
| Schedule item | Example | Why it matters |
|---|---|---|
| Milestone | User acceptance testing starts on June 10 | Shows a measurable project checkpoint |
| Dependency | Client provides test data by May 20 | Identifies an event outside the vendor’s control |
| Deliverable | Version 1.0 configuration package | Defines what must be produced |
| Review period | Client has five business days to review | Prevents open-ended approval |
Use calendar dates when the parties know them. If dates depend on an earlier event, define the trigger precisely. “Within 15 business days after the vendor receives complete source data” is clearer than “shortly after data delivery.”
Identify dependencies and schedule relief
A dependency is an event or input that must occur before another task can begin. Common dependencies include client access, decisions, approvals, data, personnel, or third-party services.
The SOW should state who controls each dependency and what happens if it is late. A useful provision might say that a vendor deadline moves by the number of days caused by a client delay, provided that the vendor promptly gives notice and takes reasonable steps to reduce the effect.
This mechanism should not excuse every delay. Define conditions such as:
- The dependency was listed in the SOW or was reasonably necessary for the work.
- The vendor requested the item with enough lead time.
- The vendor notified the client of the delay and its likely impact.
- The vendor continued unaffected work.
Use milestones to manage payment and risk
A milestone can trigger an invoice, acceptance review, or release of a project phase. Link payment to an objective event, such as delivery of a specified package, rather than to an undefined statement that work is “substantially complete.”
Do not make every date a hard deadline unless the parties intend that result. Classify dates as firm commitments, target dates, or estimates. The contract should state whether missing a firm milestone creates a breach, a service credit, a right to terminate, or only a duty to provide a recovery plan.
Map the schedule
A schedule should also include a recovery process. Require the delayed party to notify the other party, explain the cause, provide a revised forecast, and identify corrective actions. A change order may be appropriate when the delay changes scope, fees, or the agreed completion date.
Exercise
The client must provide data by May 1, but provides it on May 11. The vendor notified the client on May 2 that the delay would affect testing. What should the SOW address?
Show answer
It should state whether the vendor's affected deadlines move by the ten-day delay, subject to notice, mitigation, and any limits in the SOW. It should also require a revised schedule if the delay affects fees, milestones, or the final delivery date.