Common Pitfalls and How to Avoid Them
Assume you know the basic roles of a client and vendor, and understand how an MSA, SOW, deliverable, acceptance criterion, milestone, and change order work. This chapter focuses on gaps that cause disagreements after signing.
Vague scope and hidden assumptions
A SOW fails when it describes an outcome without defining the work needed to reach it. “Build a user-friendly reporting system” leaves room for different interpretations. A stronger scope identifies the users, functions, integrations, supported environments, and excluded work.
State assumptions and client dependencies separately. For example, the vendor might assume that the client will provide test data by a particular date. If that dependency is late, the schedule should move under an agreed rule.
Explicit exclusions are equally important. If post-launch support, data cleansing, or translation is not included, say so. Silence often becomes an argument about whether the work was part of the fixed fee.
Scope creep without a decision record
Scope creep is work added informally after the parties agree to the SOW. It often begins with a reasonable request in an email or meeting. The risk grows when the team performs the work before anyone records its effect on fees and schedule.
Use a change control process:
- Describe the requested change.
- Identify affected deliverables, dependencies, risks, dates, and fees.
- Have authorized representatives approve or reject it.
- Update the SOW, schedule, or change log.
A change order should state that all other terms remain unchanged. This prevents a narrow change from accidentally reopening the whole agreement.
Conflicting or incomplete documents
An MSA usually contains reusable legal terms. A SOW contains project-specific terms. Problems arise when the SOW silently contradicts the MSA, or when an attachment uses different definitions, dates, or payment rules.
Include an order-of-precedence clause. It should identify which document controls and when a SOW may override the MSA. Requiring an express reference to the overridden section is safer than allowing a general statement that the SOW “supersedes” the MSA.
| Risk | Preventive drafting step |
|---|---|
| SOW conflicts with the MSA | State a clear order of precedence and require express overrides |
| Acceptance is subjective | Use measurable criteria and a review deadline |
| Client delay is ignored | List dependencies and schedule consequences |
Payment, acceptance, and measurement gaps
Link invoices to clear events, such as delivery, acceptance, or a milestone date. Define what happens if the client does not respond within the review period. Without a deemed-acceptance rule or another response mechanism, an invoice may remain disputed indefinitely.
Service levels create a similar measurement problem. Define the data source, measurement period, exclusions, calculation method, and remedy. A target such as “high availability” is not measurable. A percentage target with a stated service credit formula is more useful.
A practical review path
Review the documents in this order:
- Compare the parties, effective dates, definitions, and referenced attachments.
- Trace each deliverable to acceptance criteria, an owner, a date, and a payment event.
- Check every assumption for a corresponding dependency or consequence.
- Test a likely change request and confirm that the approval process works.
- Confirm that liability, intellectual property, confidentiality, termination, and dispute terms are not accidentally altered by the SOW.
Exercise
The SOW says the vendor will deliver a “complete training program,” but gives no audience, materials, session count, or acceptance test. What is the main defect, and how should it be corrected?
Show answer
The scope is vague and acceptance is subjective. Define the audience, materials, number and format of sessions, delivery dates, and measurable acceptance criteria. State what training work is excluded.