Sub topic 16
A Checklist for Drafting and Reviewing an MSA and SOW
Prerequisites and the review model
Assume you understand what a contract is and know the roles of a client, vendor, project manager, and legal counsel. An MSA is the reusable agreement that sets general legal and commercial rules. A statement of work, or SOW, applies those rules to one project.
Review the documents as one system:
- Confirm that the MSA and SOW identify the same parties.
- Check that the SOW clearly incorporates the correct MSA, including its date and amendments.
- Find conflicts between the documents before signing.
- Test whether the project terms are specific enough to administer.
- Confirm that payment, risk, and remedies match the actual work.
Core drafting checklist
| Review area | Questions to ask | Common gap |
|---|---|---|
| Parties and authority | Are the legal names, addresses, and signatories correct? | A business unit signs without authority |
| Scope | What is included, and what is excluded? | Broad promises such as “support as needed” |
| Deliverables | What must the vendor provide, and in what format? | No objective completion standard |
| Acceptance | How and when does the client accept or reject work? | Silence has no defined effect |
| Schedule | Are milestones, dependencies, and delay effects stated? | Client delays are ignored |
| Fees | What triggers invoices, and what expenses are allowed? | Payment is not tied to measurable events |
| Change control | How must additions or alterations be approved? | Informal requests change the project |
| Risk | Do warranties, indemnities, and liability limits fit the work? | Liability cap has unclear exceptions |
| Exit | What happens to work, data, and fees after termination? | No transition or handover process |
Scope, deliverables, and acceptance
Use nouns and measurable actions. “Prepare a monthly security report containing the listed tests and findings” is easier to administer than “provide security services.”
For each deliverable, specify:
- its name and required format;
- the person responsible for providing inputs;
- the due date or milestone;
- objective acceptance criteria;
- the review period;
- the correction process after rejection.
Acceptance criteria should describe observable results. For example, a report may be accepted when it contains all required sections, covers the agreed systems, and has no missing test results. Link payment to acceptance only when the parties intend acceptance to control invoicing. Otherwise, state whether payment is based on delivery, time worked, or another event.
Consistency and document priority
An order-of-precedence clause states which document controls when terms conflict. The clause should identify whether a later change order, the SOW, the MSA, or an attachment wins. An SOW should expressly identify any MSA provision it overrides. A general statement that the SOW “controls” can create unintended changes to confidentiality, liability, or intellectual-property terms.
Common errors and final checks
Watch for undefined terms, inconsistent dates, missing dependencies, and references to attachments that are not included. Check that service levels use a stated measurement method and that remedies such as service credits are calculated clearly. Confirm that the MSA covers confidentiality, data protection, intellectual property, termination, dispute resolution, governing law, and notices.
This checklist supports review but does not replace legal advice. Enforceability and required clauses vary by jurisdiction and transaction.
Exercise
The SOW says the vendor will deliver a working dashboard, but it gives no test, review period, or rejection process. What should the reviewer request?
Show answer
Request measurable acceptance criteria, a review deadline, the permitted reasons for rejection, a correction process, and the effect of acceptance or rejection on payment.