Managing Change with Change Orders
Assume you understand basic contract terms, the relationship between a master service agreement (MSA) and a statement of work (SOW), and the difference between a deliverable and a milestone. This chapter focuses on what happens when the agreed project must change.
Why change control matters
A SOW defines the work the vendor must perform, the client must provide, the dates that matter, and the price. A requested change can affect all four. For example, adding a reporting feature may require more development time, move testing dates, increase fees, and change the acceptance criteria.
A change order is a written amendment that records an approved change to a SOW. It should identify what changes and what does not. The MSA or SOW should state that neither party must perform a material change until both parties approve it under the agreed process.
Without this process, a casual email or meeting comment can create disagreement about whether work is included, authorized, or billable.
A practical change control process
A useful process has these steps:
- Submit the request. Identify the requester, date, affected SOW section, and reason for the change.
- Analyze the impact. Review deliverables, acceptance criteria, dependencies, schedule, fees, staffing, security, and legal risk.
- Prepare the change order. State the new, deleted, or modified requirements. Include revised dates, prices, and responsibilities.
- Obtain approval. Require signatures or another clearly authorized approval method from both parties.
- Update the project records. Link the change order to the SOW and update the schedule, budget, requirements, and acceptance plan.
- Track completion. Test and accept the changed work using the revised criteria.
The change order should say whether all other SOW terms remain unchanged. It should also state when the change becomes effective. Avoid allowing project staff to approve commercial changes unless the contract gives them that authority.
Worked example
A SOW requires a vendor to deliver a customer portal by June 30 for $40,000. The client later requests two-factor authentication. The vendor estimates $6,000 in additional work and a two-week delay.
A complete change order would identify the new authentication requirement, revise the delivery date to July 14, increase the fee to $46,000, update the security acceptance test, and state whether future maintenance fees change. It would also record that all unaffected deliverables remain subject to the original SOW.
A vague approval such as “Please add two-factor authentication” does not resolve whether the vendor must absorb the cost or meet the original deadline.
Common errors
- Treating a change request as automatically approved.
- Using “reasonable,” “minor,” or “as needed” without defining the boundary.
- Failing to document rejected requests.
- Changing the scope but not the acceptance criteria.
- Allowing work to begin before commercial approval.
- Creating a change order that conflicts with the MSA without expressly identifying the override.
Exercise
A client requests a new dashboard. The vendor agrees to build it but does not discuss price or schedule. What should happen before work begins?
Show answer
The parties should assess the dashboard's effects, document the revised scope, acceptance criteria, fees, and schedule in a change order, and obtain approval from authorized representatives.