Sub topic 6
Acceptance Criteria and the Review Process
This chapter assumes you understand basic contract terms and the roles of a client, vendor, project manager, and legal counsel. It focuses on how a statement of work (SOW) defines when a deliverable is complete and how the client reviews it.
What acceptance criteria do
Acceptance criteria are objective conditions that a deliverable must satisfy before the client accepts it. Acceptance matters because it can affect payment, warranty periods, project completion, and the vendor's duty to correct defects.
A weak requirement says:
- “The vendor will deliver a user-friendly dashboard.”
A stronger requirement says:
- “The dashboard must display the 12 metrics listed in Appendix A.”
- “A user can filter results by date range and department.”
- “The dashboard must load within three seconds for a dataset of up to 100,000 records.”
- “The client will test the dashboard using the test cases in Appendix B.”
The stronger version gives the reviewer a repeatable test. It also reduces arguments about personal preferences.
Acceptance criteria should identify:
- The deliverable being tested.
- The required function, quality, format, or performance.
- The test method or evidence.
- The person or role authorized to review it.
- The review period.
- The result of acceptance, rejection, or silence.
- The process for correcting rejected work.
Linking acceptance to payment
The SOW should state whether payment depends on acceptance. A milestone payment might become due when the vendor submits a deliverable, when the client accepts it, or when the review period expires without a valid rejection. These choices create different risks.
For example, a client-friendly clause might provide that the client pays after acceptance. A vendor-friendly clause might require payment on submission and treat rejection as a separate correction obligation. The parties can also split a milestone payment, paying part on submission and the balance on acceptance.
The SOW should avoid making payment depend on an undefined concept such as “client satisfaction.” If subjective judgment is unavoidable, define who exercises it, what factors they consider, and how the parties address a good-faith disagreement.
A practical review workflow
A useful process separates delivery, review, rejection, correction, and final acceptance.
A rejection should identify each failed criterion and provide enough information to reproduce the problem. A client should not use rejection to demand work that the SOW excludes. Likewise, a vendor should not call work complete while known failures remain.
The SOW should state whether the client gets one review cycle or several, whether the vendor bears correction costs, and what happens if the client misses the review deadline.
| Issue | Clear provision | Common error |
|---|---|---|
| Review period | Client has 10 business days after delivery to review | No deadline |
| Rejection | Rejection must list specific failed criteria | “Not acceptable” |
| Correction | Vendor corrects confirmed defects within 5 business days | Unlimited redesign |
| Deemed acceptance | Silence counts as acceptance only if expressly agreed | Assuming silence has a legal effect |
Common errors
The most frequent errors are criteria that cannot be tested, requirements hidden in informal emails, and a review process that conflicts with the MSA. Check whether the SOW overrides any general acceptance, invoicing, or dispute provision. Make sure defined terms such as “defect,” “material breach,” and “business day” have consistent meanings.
Also distinguish a defect from a change request. If the deliverable fails an agreed criterion, correction is usually part of the original work. If the client wants a new feature or different result, the request should enter the change control process.
Exercise
A client rejects a report because it wants two additional charts that the SOW never listed. Is this automatically a failed acceptance test?
Show answer
No. The client should identify the applicable acceptance criterion that failed. If the report meets the agreed criteria, the additional charts are likely a change request rather than a defect.