Sub topic 10
The Risks of Fast-Tracking: Rework and Coordination
This chapter assumes you can read a schedule network and find the critical path. It also assumes you know what a finish-to-start dependency is and have seen the basic idea of fast-tracking, which is overlapping activities that were planned in sequence. Here the focus is on what fast-tracking costs, and on how to judge whether those costs are smaller than the time you save.
Why fast-tracking is not free
Crashing spends money to shorten activities. Fast-tracking spends certainty. A finish-to-start link exists for a reason: the successor needs something the predecessor produces. When you start the successor early, you let it begin on incomplete information.
The schedule gain is easy to see. In the earlier example, design takes 6 days and build takes 8. Run in sequence, the project takes 14 days. If build starts 3 days before design finishes, the finish moves to day 11. That 3-day gain is the best case. It assumes that nothing built during the overlap has to be redone.
The risk comes in two parts:
- Rework. Work done on preliminary information may have to be thrown away or changed.
- Coordination. Two teams working on linked pieces at once need more communication, and that communication takes time and attention.
Where rework comes from
Rework happens when the upstream activity changes something after the downstream activity has already relied on it. Two properties of the dependency decide how much rework to expect.
Evolution: how fast the upstream information settles
Evolution describes how quickly the upstream output becomes stable. A design's overall layout may be fixed after two days, while its detailed dimensions keep changing until the last day. Starting build when the layout is fixed is much safer than starting when the dimensions are still moving.
Sensitivity: how much the downstream work depends on it
Sensitivity describes how much downstream work is invalidated by a change upstream. If a changed wall position forces every pipe, cable and fixture to be moved, sensitivity is high. If a changed paint color touches one task, sensitivity is low.
The worst case for fast-tracking is late-changing, highly sensitive information. The best case is early-settling, low-sensitivity information.
| Upstream information | Downstream sensitivity | Fast-tracking risk | Typical response |
|---|---|---|---|
| Settles early | Low | Low | Overlap freely |
| Settles early | High | Moderate | Overlap after the settling point |
| Settles late | Low | Moderate | Overlap, keep changes cheap |
| Settles late | High | High | Do not overlap, or overlap only a small part |
How rework shows up in the schedule
Rework lands on whichever activity has to redo work. If that activity is on the critical path, every day of rework adds a day to the project. In a fast-tracked pair, the downstream activity is usually critical, because overlapping is only worth doing on the critical path in the first place.
This produces a result that surprises many beginners: a fast-tracked schedule can finish later than the original sequential schedule. In the design and build example, the sequential finish is day 14. If the overlap saves 3 days but a design change forces 4 days of rework in build, the finish is day 15. The team paid for coordination, took on risk, and ended up one day behind.
The sequence below shows how this happens.
A second schedule effect is easy to miss. Overlapping shortens the critical path, which can bring other paths close to critical. After fast-tracking, check float on the other paths. A rework delay on a path that used to have comfortable float may now delay the whole project. This is the near-critical path problem from earlier in the tutorial, now made worse by compression.
Coordination costs
Even when no rework happens, overlap has a cost. Teams that used to hand work over once now exchange information continuously.
- More communication paths. With n people who all need to talk to each other, the number of pairwise channels is n(n-1)/2. Two teams of 3 working in sequence need few channels at a time. The same 6 people working at once have 15 possible channels.
- Interface management. Someone has to track which version of the upstream work the downstream team is using, and tell them when it changes.
- Review and approval overhead. Work that normally gets one formal approval at handover may now need partial reviews, so the downstream team has something stable to build on.
- Resource peaks. Activities that were sequential now need people at the same time. If the same specialists are needed in both, you have created a resource conflict, and the overlap may not be possible at all.
- Quality and compliance exposure. Starting work before a required approval, test result or permit can create legal or safety problems that no amount of schedule gain justifies.
These costs are real but hard to put in a schedule. A common mistake is to count only the days saved and forget the management time consumed.
Putting a number on the risk
You can estimate whether an overlap pays off with a simple expected-value comparison. For one overlap:
- Let g be the days gained by overlapping.
- Let p be the probability that rework is needed.
- Let r be the days of rework if it is needed.
The expected net gain is g − p × r. Overlap is worthwhile in expectation when p × r is less than g. Expected value alone is not enough, though. If the worst case (g − r) pushes you past a hard deadline, the average does not matter. You also need to look at the worst case.
The usual relationship is that more overlap raises both p and r. The longer the successor runs on unstable information, the more likely a change arrives, and the more work it affects. This is why returns diminish. The code below models that with a simple assumption: the probability of change grows by 0.15 per day of overlap, and rework is 1.5 days per day of overlap. These numbers are illustrative. In a real project you would take them from past projects or expert judgment.
design, build = 6, 8
sequential = design + build # finish-to-start: 14 days
print("overlap finish p(rework) rework expected finish")
for overlap in range(0, 7):
build_start = design - overlap
finish = max(design, build_start + build)
p = 0.15 * overlap
rework = 1.5 * overlap
expected = finish + p * rework
print(f"{overlap:7d} {finish:6d} {p:9.2f} {rework:6.1f} {expected:15.3f}")
print("sequential finish:", sequential)The output shows expected finish days of 14.000, 13.225, 12.900, 13.025, 13.600, 14.625 and 16.100 for overlaps of 0 to 6 days. The best overlap under this model is 2 days, which saves about 1.1 days in expectation. The nominal gain from a 3-day overlap is 3 days, but its expected gain is under 1 day. At 5 days of overlap the expected finish is worse than not overlapping at all.
Two points follow from this:
- The first days of overlap are the cheapest, because they happen when the upstream information is most stable. The last days of overlap are the most expensive.
- The nominal schedule gain from fast-tracking overstates the real gain, and the gap grows with the amount of overlap.
Reducing the risk
You cannot remove the risk, but you can reduce either its probability or its cost.
- Overlap at the right point. Start the successor when the upstream information is stable enough, not as early as the logic allows. Ask the upstream team which decisions are already frozen.
- Split activities. Instead of overlapping whole activities, overlap only the parts with low sensitivity. For example, start site preparation while detailed interior design continues.
- Freeze interfaces early. Agree on the points where the two pieces connect, such as dimensions, data formats or API contracts, before downstream work begins. Changes inside each piece then stay inside it.
- Release in stages. Have the upstream team deliver partial outputs with clear status, such as "draft" and "approved", so the downstream team knows what is safe to rely on.
- Add review gates inside the overlap. A short check at the midpoint catches a divergence while it is still cheap to fix.
- Reserve contingency. Add schedule and cost reserve for the expected rework, and record the overlap as a risk with an owner and a trigger in the risk register.
- Prefer reversible work first. Begin with downstream tasks that can be reused if the upstream design changes, such as procurement lead times, environment setup or tooling.
When to decide against fast-tracking
Use these checks before you commit to an overlap:
- The upstream information changes often, and the downstream work is highly sensitive to it.
- The worst case (g − r) is later than a hard deadline, and the deadline cannot move.
- The overlapping activities need the same scarce people.
- The dependency is mandatory because of approvals, safety or law.
- The team has no capacity to manage the added coordination.
If several of these apply, crashing, which adds resources without changing the logic, may be the safer choice. The next chapter compares the two techniques directly.
Summary
Fast-tracking converts a sequence into a partial parallel run, and the saving depends on the upstream information staying stable. Rework is the main risk, and it scales with how late the information changes and how sensitive the downstream work is. Coordination adds overhead even in the good case. Model both, check the worst case against your deadline, and limit overlap to the early, stable part of the upstream work.
Exercise
Design takes 6 days and build takes 8 days. Build starts 4 days before design finishes. There is a 50% chance of a design change that causes 5 days of rework in build. What are the sequential finish, the best-case overlapped finish, the worst-case overlapped finish, and the expected overlapped finish? Is the overlap worthwhile in expectation, and does it beat the sequential plan in the worst case?
Show answer
Sequential finish is 6 + 8 = 14 days. Build starts on day 2, so the best-case finish is 2 + 8 = 10 days. The worst case adds 5 days of rework: 15 days. The expected finish is 10 + 0.5 × 5 = 12.5 days. In expectation the overlap saves 1.5 days, so it is worthwhile on average. In the worst case it finishes at day 15, one day later than the sequential plan, so it does not beat the sequential plan in the worst case. If the deadline is day 14, the 50% chance of missing it needs a mitigation or a smaller overlap.
Exercise
Which of these two overlaps is riskier, and why? (a) Starting procurement of standard fittings while the detailed layout is being finalized. (b) Starting wall construction while the floor plan is still being revised.
Show answer
Overlap (b) is riskier. The floor plan is information that changes late and the wall construction is highly sensitive to it, because a change moves the walls and forces demolition and rebuilding. In (a), standard fittings are unlikely to change with the layout, so sensitivity is low and a change causes little rework.
Exercise
Two teams of 4 people each must work at the same time on an overlapped pair of activities, and each person might need to talk with every other person. How many pairwise communication channels is that, and why does this matter for fast-tracking?
Show answer
There are 8 people, so 8 × 7 / 2 = 28 channels. In sequence, the teams would mostly work separately, and only a handover would connect them. Overlapping makes continuous communication necessary, which adds coordination time that does not appear as an activity in the schedule. This is a hidden cost that reduces the real gain of fast-tracking.