Sub topic 8
Dependency Types and Leads
Compression works on how activities are linked, not only on how long they take. This chapter covers the four dependency types, how leads and lags change them, and which dependencies you can change safely. It prepares you for fast-tracking in the next chapters.
This chapter assumes you can read an activity network or Gantt chart, and that you can find a critical path and float from the earlier chapters. It also assumes basic arithmetic on durations.
What a dependency says
A dependency is a rule about when one activity may start or finish, relative to another. Each dependency links a predecessor to a successor. The successor's timing is constrained by the predecessor's start or finish.
The project management standard names four logical relationships. Each one pairs a point on the predecessor with a point on the successor.
| Type | Rule | Typical example |
|---|---|---|
| Finish-to-start (FS) | Successor cannot start until predecessor finishes | Pour the foundation, then erect walls |
| Start-to-start (SS) | Successor cannot start until predecessor starts | Begin writing test scripts once coding begins |
| Finish-to-finish (FF) | Successor cannot finish until predecessor finishes | Documentation finishes only after the feature is finished |
| Start-to-finish (SF) | Successor cannot finish until predecessor starts | The old system's support ends only after the new shift or system starts |
FS is the default in most scheduling tools and in most plans. It is also the most restrictive for the schedule, because it forces strict sequence. SS and FF let two activities run side by side. SF is rare. If you think you need it, check first whether FS with the roles reversed says the same thing more clearly.
Leads and lags
A lag delays the successor relative to the relationship. A lead moves the successor earlier. A lead is a negative lag, so both are one number added to the relationship.
- Lag example: concrete needs 2 days to cure after the pour. FS with a 2-day lag.
- Lead example: build starts 3 days before design finishes. FS with a 3-day lead, written as lag -3.
A lag represents real waiting time that needs no resources, such as curing, shipping, or an approval window. A lead represents deliberate overlap. The two have opposite effects on duration, but they work the same way in the calculation.
The successor's earliest start or finish is set from the predecessor like this:
- FS: successor start = predecessor finish + lag
- SS: successor start = predecessor start + lag
- FF: successor finish = predecessor finish + lag
- SF: successor finish = predecessor start + lag
For FF and SF, you get the successor's start by subtracting its duration from the finish.
Computing the four types in code
This script computes the successor's window for each relationship type. Design starts on day 0 and finishes on day 6. Build takes 8 days.
def successor_window(kind, pred_start, pred_finish, lag, duration):
"""Return the earliest (start, finish) of the successor."""
if kind == "FS":
start = pred_finish + lag
elif kind == "SS":
start = pred_start + lag
elif kind == "FF":
start = pred_finish + lag - duration
elif kind == "SF":
start = pred_start + lag - duration
else:
raise ValueError(f"unknown dependency type: {kind}")
return start, start + duration
design_start, design_finish = 0, 6
build_duration = 8
cases = [
("FS", 0), # plain sequence
("FS", 2), # 2-day lag (waiting time)
("FS", -3), # 3-day lead (overlap)
("SS", 3), # build starts 3 days after design starts
("FF", 4), # build finishes 4 days after design finishes
("SF", 12), # build finishes 12 days after design starts
]
for kind, lag in cases:
start, finish = successor_window(
kind, design_start, design_finish, lag, build_duration
)
print(f"{kind} lag {lag:+d}: start {start}, finish {finish}")The output is:
FS lag +0: start 6, finish 14
FS lag +2: start 8, finish 16
FS lag -3: start 3, finish 11
SS lag +3: start 3, finish 11
FF lag +4: start 2, finish 10
SF lag +12: start 4, finish 12Two results are worth noting. FS with a 3-day lead and SS with a 3-day lag give the same dates here (start 3, finish 11). They are not the same rule, though. If design later slips or grows longer, FS-with-lead moves build later with it, because build stays tied to design's finish. SS-with-lag moves build only if design's start moves. The two links respond differently to change.
The second point is the lag of +2 in the second line. Waiting time lengthens the schedule. Lags are not compression tools, and every lag on the critical path adds to the project duration.
Which dependencies can you change?
Compression by overlap depends on which dependencies can be relaxed. Dependencies fall into categories that tell you how much freedom you have.
| Category | Meaning | Can you overlap it? |
|---|---|---|
| Mandatory (hard logic) | Required by the nature of the work, such as a physical or legal constraint | Generally no |
| Discretionary (soft logic) | Chosen by the team as best practice or preference | Yes, with a risk assessment |
| External | Depends on something outside the project, such as a supplier delivery | Only by negotiating with the outside party |
| Internal | Depends on another project activity under the team's control | Yes, if the work allows it |
You cannot pour the roof before the walls exist. That is a mandatory dependency, so a lead there would be wrong. Starting detailed build work before every design review is complete is discretionary. The team chose that order to reduce risk.
Discretionary, internal dependencies are the candidates for fast-tracking. When you review a network for compression, mark each FS link with its category. Only the discretionary, internal ones go on the shortlist.
How a lead interacts with the critical path
A lead shortens the project only when the relationship it modifies sits on the critical path. This follows from the critical path rule you already know: shortening a non-critical link uses up float without changing the end date.
Take a network with two paths. Path 1 is Design (6) to Build (8), 14 days in total. Path 2 is Procurement (10) to Install (3), 13 days in total. Path 1 is critical, with 1 day of float on Path 2.
- Add a 3-day lead between Design and Build. Path 1 drops to 11 days. Path 2, at 13 days, becomes the critical path. The project finishes in 13 days, not 11.
- The gain is 1 day, not 3, because the other path now limits the schedule.
After any lead, recompute the critical path. A lead can move the critical path onto another route, and the saving is capped by the near-critical path. This is why the earlier chapter on float and near-critical paths matters here.
Limits of a lead
A lead has hard boundaries. These are the main mistakes to avoid.
- A lead longer than the predecessor. With an FS lead of 8 on a 6-day design, the successor would start 2 days before design begins. The link then says nothing sensible. Keep the lead less than the predecessor's duration. Check that the predecessor has produced the output the successor needs by the lead's start point.
- A lead that ignores the shape of the work. A 3-day lead assumes the last 3 days of design are not needed to begin build. If those days contain a key decision, the build team will work on assumptions and may redo work.
- Mixing SS and FF to fake a lead. A common pattern is SS with a lag and FF with a lag on the same pair, so both ends are constrained. This is valid and often more realistic. Without the FF link, the successor could finish before the predecessor's final output exists. If you use only SS, the finish can end up unconstrained.
- Using lags as padding. A 5-day lag labeled "buffer" hides time inside the logic. It does not appear as float, and compression analysis will treat it as fixed waiting time. Put contingency in a visible reserve instead.
- Calendar mismatch. A lag in calendar days (curing, shipping) differs from a lag in working days. If the tool counts working days, a 2-day cure over a weekend gives the wrong date. Check which calendar the lag uses.
What this means for compression
Crashing leaves the logic alone and shortens activity durations. Fast-tracking leaves durations alone and changes the logic. A lead is the most common way to record that change. It is a schedule edit, not a work edit, so it costs nothing to enter and can cost a great deal to deliver.
The steps to apply it are:
- Find the critical path.
- List the FS links on it.
- Classify each as mandatory or discretionary, and internal or external.
- For each discretionary, internal link, decide how much of the predecessor must finish before the successor can usefully start. That sets the maximum lead.
- Apply the lead, then recompute the critical path and the new project duration.
The next chapters cover how to choose the amount of overlap and what rework it can cause.
Exercise
Design runs days 0 to 6 and Build takes 8 days. Use the rules in this chapter to give Build's start and finish for (a) FS with a 2-day lag, and (b) FF with a 4-day lag.
Show answer
(a) Start = 6 + 2 = 8, finish = 8 + 8 = 16. (b) Finish = 6 + 4 = 10, so start = 10 - 8 = 2.
Exercise
Path 1 is Design (6 days) then Build (8 days). Path 2 is Procurement (10 days) then Install (3 days). You add a 3-day lead between Design and Build. What is the new project duration, and why is it not 11 days?
Show answer
The project is 13 days. Path 1 drops from 14 to 11 days. Path 2 takes 13 days, so it becomes the critical path and sets the finish. The lead saved only 1 day because the near-critical path limits the gain.
Exercise
A team wants to put a 5-day lead between "Pour roof slab" and "Install roof waterproofing" to save time. What kind of dependency is this, and should they do it?
Show answer
It is a mandatory dependency, because waterproofing needs the slab to exist and cure. A lead would not be valid, so they should look for discretionary links to overlap instead.