Sub topic 12
Limits, Diminishing Returns and Combining Techniques
This chapter assumes you can find a critical path and calculate float. It also assumes you know the crash cost slope (extra cost per day saved) and how a start-to-start dependency with a lead lets two activities overlap. Here we ask how far compression can go, why each extra day costs more than the last, and how to combine crashing and fast-tracking without losing the gains.
Why compression has a ceiling
Compression keeps scope fixed and shortens the schedule. Each technique has its own limit.
- Crashing stops when every activity on the critical path is at its crash limit. That is the shortest duration the activity can have, even with extra resources.
- Fast-tracking stops when no remaining dependency can safely be overlapped. A mandatory dependency, such as pouring concrete before the concrete cures, cannot be overlapped at all.
The shortest possible project duration is the length of the longest path when every activity is at its crash limit. No amount of money gets below it. Before you promise a date, calculate this floor. If the target is below it, the options are to cut scope or move the date.
The four-activity network from the earlier chapters is a small example.
| Activity | Normal days | Crash limit | Slope per day | Predecessors |
|---|---|---|---|---|
| A | 3 | 2 | 500 | none |
| B | 5 | 3 | 400 | A |
| C | 4 | 3 | 300 | A |
| D | 3 | 2 | 600 | B, C |
At normal durations the path A-B-D takes 11 days and A-C-D takes 10. At the crash limits both paths take 2 + 3 + 2 = 7 days. So 7 days is the floor, and asking for 6 is not a compression problem.
Diminishing returns: each day costs more
The cheapest day to save is always taken first. The second day must come from something more expensive, and so on. The cost curve is therefore convex: it rises faster the further you compress.
Three things cause this:
- Cheap slopes get used up. An activity reaches its crash limit and drops out of the choice.
- Parallel paths multiply the cost. Once two paths are both critical, one crash on one path saves nothing. You must shorten every critical path by one day, so the day costs the sum of the slopes.
- Short activities have no room left. The activities with the largest slopes are usually the ones that were already tight.
You can see this by enumerating every combination of durations, instead of crashing greedily. The program below keeps the cheapest cost found for each project duration. For a network this small, that exhaustive search is quick.
from itertools import product
activities = {
# name: normal duration, minimum (crash) duration, crash cost per day, predecessors
"A": {"dur": 3, "min": 2, "slope": 500, "preds": []},
"B": {"dur": 5, "min": 3, "slope": 400, "preds": ["A"]},
"C": {"dur": 4, "min": 3, "slope": 300, "preds": ["A"]},
"D": {"dur": 3, "min": 2, "slope": 600, "preds": ["B", "C"]},
}
def project_duration(durs):
finish = {}
for name, a in activities.items(): # listed in dependency order
start = max((finish[p] for p in a["preds"]), default=0)
finish[name] = start + durs[name]
return max(finish.values())
names = list(activities)
ranges = [range(a["min"], a["dur"] + 1) for a in activities.values()]
best = {} # project duration -> cheapest total crash cost
for combo in product(*ranges):
durs = dict(zip(names, combo))
cost = sum(a["slope"] * (a["dur"] - durs[n]) for n, a in activities.items())
d = project_duration(durs)
if d not in best or cost < best[d]:
best[d] = cost
previous = 0
for d in sorted(best, reverse=True):
print(f"{d} days: total {best[d]}, this step {best[d] - previous}")
previous = best[d]The output is:
11 days: total 0, this step 0
10 days: total 400, this step 400
9 days: total 900, this step 500
8 days: total 1500, this step 600
7 days: total 2200, this step 700The step cost rises by 100 each time. The first day costs 400 (crash B). The second costs 500 (crash A, which shortens both paths). The third costs 600 (crash D). The fourth costs 700, because B and C must both be crashed at once (400 + 300).
Deciding where to stop
The curve above gives the cost of time. To know whether to buy a day, you need the value of time: a daily delay penalty, an early-completion bonus, the cost of running the site or team, or revenue from an earlier launch. Compare the two numbers one day at a time.
- If the next day's step cost is below the value of a day, compress it.
- If it is above, stop.
Suppose each day is worth 550. Then you compress to 9 days (the 500 step passes) and stop, because the 600 step to 8 days does not. If a day is worth only 350, you stop at 10 days.
Cost is not the only reason to stop. Other limits can bind before the money does.
| Limit | What it means in practice |
|---|---|
| Crash limit | The activity cannot get shorter, however many people are added. |
| Resource availability | There are no more qualified people, machines or work areas to add. |
| Added effort per person | New people need onboarding and coordination, so the saving per person falls. |
| Mandatory dependency | The order is physical or contractual and cannot be overlapped. |
| Risk tolerance | Each overlap raises the chance of rework. At some point the sponsor will not accept more. |
| Budget ceiling | The funding cap is reached before the value of time is. |
Fast-tracking has limits too
Fast-tracking has no price per day, but it still has a cost: rework and coordination. The overlap example from the spine shows the gain before that cost.
design, build = 6, 8
sequential = design + build # finish-to-start: 14 days
build_start = 3 # build starts 3 days before design finishes
overlapped = max(design, build_start + build) # 11 days
print(sequential, overlapped, sequential - overlapped) # 14 11 3The overlap saves 3 days on paper. That figure assumes build never has to redo anything. If design changes after the build has started, the build team redoes some work. Say the overlap causes 1 day of rework. The real finish is then 12 days, and the saving is 2 days, not 3.
Two further effects reduce the gain.
- The saving is capped by the successor. The overlapped finish is the later of two things: the predecessor's finish and the successor's start plus its duration. In the code, the
maxpicksbuild_start + build= 11, since 11 is larger than 6. Overlapping more does not help once the successor drives the finish, unless the successor itself is also shortened. - Rework grows with the overlap. Starting build when design is nearly done risks little. Starting it when design is half done means building on decisions that are still open. Rework rarely rises in a straight line as the overlap grows.
Fast-tracking also changes how the critical path behaves. The overlapped pair is tied together by a start-to-start or finish-to-finish relation with a lead. A change to the predecessor now moves the successor immediately. The pair becomes more sensitive, and the path through it is often the one most likely to slip.
Combining the techniques
A real compression plan usually uses both techniques, in a deliberate order.
- Re-check the critical path. Compress only activities on it. Identify near-critical paths too, since they will join the critical path as it shrinks.
- List the candidates for each technique. For crashing, list slopes and crash limits. For fast-tracking, list the discretionary dependencies that could take a lead, with a rough rework estimate.
- Take the cheapest and lowest-risk days first. Zero-cost options such as removing an unnecessary lag come before anything else. A low-risk overlap and a cheap crash come next. The expensive crashes and the risky overlaps come last.
- Recalculate after every change. Each change can shift which path is critical, and fast-tracking changes the network itself.
- Stop when the next day costs more than it is worth or the risk exceeds what the sponsor accepts.
The techniques also interact, so apply them in a sensible order.
- Fast-track first when the overlap is low-risk. Overlapping removes work from the critical path without buying anything, and it may leave fewer critical days to crash.
- Crash the successor of an overlapped pair with care. After overlapping, the successor's duration drives the finish, so shortening it gains days one for one. But adding people to work that is already built on unsettled inputs raises rework risk. Rework from that overlap will not be fixed by more people.
- Do not crash activities that fast-tracking has already shifted off the critical path. The days would be wasted.
Common mistakes
- Treating the crash cost as linear. Slopes are per activity, and the cost per project day rises as paths become critical together.
- Counting fast-tracking gains before rework. Show both the gross and the expected saving.
- Crashing a non-critical activity. It uses money and leaves the finish date unchanged.
- Forgetting to recalculate. After each change, a different path may now be critical.
- Compressing without a value for a day. Without that number, there is no principled place to stop.
Exercise
In the four-activity network, each day of delay costs the project 550. Using the cost curve (11 days: 0, 10 days: 400, 9 days: 900, 8 days: 1500, 7 days: 2200), how many days should you compress, and what is the total crash cost? Why does the next day not pay off?
Show answer
Compress to 9 days, at a total crash cost of 900. The step costs are 400 (11 to 10), 500 (10 to 9), 600 (9 to 8) and 700 (8 to 7). Saving a day is worth 550. The first two steps cost less than 550, so they pay off. The step to 8 days costs 600, which is more than the 550 gained, so you stop at 9 days.
Exercise
Design takes 6 days and build takes 8. Build starts 3 days before design finishes, and the overlap is expected to cause 1 day of build rework. What is the expected finish, and how many days does fast-tracking really save compared with the sequential 14 days?
Show answer
Without rework, the overlapped finish is max(6, 3 + 8) = 11 days. With 1 day of rework the expected finish is 12 days. The real saving is 14 - 12 = 2 days, not the 3 days shown before rework.
Exercise
Why can crashing a single activity fail to shorten the project when two paths are both critical, and what should you do instead?
Show answer
The project finish is set by the longest path. If two paths have the same length, shortening one leaves the other unchanged, so the finish does not move. You must shorten both paths by the same day, either with one activity they share or with one crash on each path. The cost of that day is the sum of the slopes, so the cheapest option must be chosen from combinations, not single activities.