Sub topic 5
Crashing: trading cost for time
Crashing shortens a project by adding resources to critical-path activities, and it costs extra money for every day saved. This chapter covers what crashing is, why it works only on certain activities, and how a small network behaves when you crash it. It also covers the mistakes that make crashing fail in practice.
Prerequisites
This chapter assumes you can do the following:
- Read an activity network, with durations and predecessors.
- Find the critical path by adding durations along each path.
- Explain float as the delay an activity can absorb without delaying the project.
Earlier chapters cover these skills. The next two chapters cover crash cost slope and the full step-by-step procedure in detail. Here the slope appears only as far as the worked example needs.
What crashing is
Crashing means shortening activity durations by adding resources, accepting higher cost in return. The scope stays the same. The work is the same work, done faster.
Typical ways to crash an activity:
- Authorize overtime or weekend shifts for the people already assigned.
- Assign additional people to the activity.
- Pay for expedited delivery of materials or equipment.
- Move work to a faster or more expensive vendor.
- Rent more powerful equipment or tools.
Each method converts money into calendar time. You pay for overtime premiums, extra headcount, express shipping or a contractor's rush rate. In return the activity finishes in fewer days.
Why only critical activities count
The project duration equals the length of the longest path through the network. Shortening an activity that is not on the longest path does not change that length, so the project finish date does not move.
Suppose a project has two parallel paths. One is 11 days long and the other is 10 days long. If you spend money to shorten the 10-day path to 8 days, the project still takes 11 days. You paid for nothing.
The rule for crashing is therefore: only crash activities on the critical path. Crashing a non-critical activity wastes money unless it has used up all its float and the path has become critical.
A worked network
The chapter's running example has four activities. Each has a normal duration, a minimum (crash) duration, and a crash cost per day, which is called the slope.
| Activity | Normal days | Crash limit (days) | Crash cost per day | Predecessors |
|---|---|---|---|---|
| A | 3 | 2 | 500 | none |
| B | 5 | 3 | 400 | A |
| C | 4 | 3 | 300 | A |
| D | 3 | 2 | 600 | B, C |
The network has two paths:
- A, B, D: 3 + 5 + 3 = 11 days
- A, C, D: 3 + 4 + 3 = 10 days
The critical path is A, B, D at 11 days. Path A, C, D has 1 day of float.
Suppose the sponsor wants the project done in 9 days, which is 2 days faster than the plan.
Step one: crash the cheapest critical activity
The critical path contains A, B and D. Their slopes are 500, 400 and 600 per day. B is cheapest, so crash B by one day. B goes from 5 to 4 days.
- A, B, D: 3 + 4 + 3 = 10 days
- A, C, D: 3 + 4 + 3 = 10 days
The project is now 10 days, and the cost so far is 400. Both paths are critical. The float on the C path is gone.
Step two: the cheapest activity no longer helps
The project must drop from 10 to 9 days. Both paths are now 10 days, so one reduction must shorten both. Consider the options:
| Option | Effect on A, B, D | Effect on A, C, D | Project duration | Cost |
|---|---|---|---|---|
| Crash B again | 9 | 10 | 10 (no gain) | 400 |
| Crash C | 10 | 9 | 10 (no gain) | 300 |
| Crash A | 9 | 9 | 9 | 500 |
| Crash D | 9 | 9 | 9 | 600 |
| Crash B and C | 9 | 9 | 9 | 700 |
Crashing C is cheapest per day at 300, and it is the cheapest activity in the whole network. It still does nothing on its own, because path A, B, D stays at 10 days. The cheapest valid move is to crash A, which sits on both paths, at 500.
Total crash cost for a 9-day project: 400 + 500 = 900.
Two lessons come out of this example:
- The cheapest activity overall is not necessarily the right one to crash.
- A shared activity can beat two cheaper activities, because one day saved on A counts on both paths.
Checking the result in code
This script repeats the greedy logic. It crashes one day at a time. It considers an activity only if the reduction really shortens the project, and it picks the cheapest such option.
activities = {
# name: normal duration, minimum (crash) duration, crash cost per day, predecessors
"A": {"dur": 3, "min": 2, "slope": 500, "preds": []},
"B": {"dur": 5, "min": 3, "slope": 400, "preds": ["A"]},
"C": {"dur": 4, "min": 3, "slope": 300, "preds": ["A"]},
"D": {"dur": 3, "min": 2, "slope": 600, "preds": ["B", "C"]},
}
def project_duration(durs):
finish = {}
for name, a in activities.items(): # listed in dependency order
start = max((finish[p] for p in a["preds"]), default=0)
finish[name] = start + durs[name]
return max(finish.values())
durs = {n: a["dur"] for n, a in activities.items()}
target = 9
spent = 0
while project_duration(durs) > target:
now = project_duration(durs)
options = []
for n, a in activities.items():
if durs[n] > a["min"]:
trial = {**durs, n: durs[n] - 1}
if project_duration(trial) < now: # only helps if it shortens the project
options.append((a["slope"], n))
if not options:
break
slope, n = min(options)
durs[n] -= 1
spent += slope
print(f"crash {n}: {now} -> {project_duration(durs)} days, +{slope}")
print(f"duration {project_duration(durs)} days, crash cost {spent}")The output is:
crash B: 11 -> 10 days, +400
crash A: 10 -> 9 days, +500
duration 9 days, crash cost 900The trial step is the important line. It asks whether the project actually gets shorter, which is a more reliable test than asking whether the activity is "on the critical path". When two paths tie, that test correctly rejects C and B and accepts A. The greedy method here is a teaching device. It works on this network, but a larger network with many parallel paths can have cheaper combinations that a one-day-at-a-time greedy choice misses.
The cost-time trade-off
For any activity, more crashing means more cost. The relationship between duration and direct cost is usually drawn as a curve. The usual simplification is a straight line between the normal point and the crash point. Under that assumption, each day saved costs the same amount, which is the slope.
For B, normal duration is 5 days and crash duration is 3. Full crashing saves 2 days at 400 per day, so it adds 800 to the direct cost.
At the project level, crashing has an additional effect on total cost. Direct costs rise as you crash. Indirect costs fall, because the project runs for fewer days. Indirect costs include management overhead, site rental, equipment hire and, in some contracts, delay penalties or early-completion bonuses. Total cost is the sum of the two, and in principle it has a lowest point.
Crashing makes economic sense while each day saved costs less than the indirect cost or penalty it avoids. If the project carries a penalty of 700 per day of delay, crashing B at 400 per day pays for itself. Crashing D at 600 per day still saves money. Crashing at 800 per day does not.
Crash limits
Every activity has a crash limit, a minimum duration below which no amount of money helps. In the example, A cannot go below 2 days, and B cannot go below 3. Limits exist for several reasons:
- Some work has a physical duration, such as concrete curing or a regulatory review period.
- Extra people need space, tools and coordination, and past a point they get in each other's way.
- Tasks have a sequential core that cannot be split. Nine people cannot produce a baby in one month.
- Approvals and procurement have fixed lead times.
When every activity on the critical path is at its crash limit, the schedule cannot be shortened by crashing at all. That floor is the shortest possible project duration. In the example network, crashing everything gives 2 + 3 + 2 = 7 days for A, B, D and 2 + 3 + 2 = 7 days for A, C, D, so the floor is 7 days.
Common errors
Intermediate practitioners usually run into these problems:
- Crashing off the critical path. The money buys float, not schedule.
- Ignoring path ties. After one crash, a second path often becomes critical. The next crash must shorten every critical path at once, or the project does not move.
- Assuming linear cost. The straight-line slope is an approximation. Real overtime has diminishing productivity, and the second and third crash days on an activity often cost more than the first.
- Adding people to work that does not split. New team members need onboarding, and communication paths grow. An activity can get slower when staff is added.
- Forgetting side effects. Overtime increases defect rates and fatigue. Expedited materials can arrive with less quality checking. These effects raise risk and can reappear later as rework.
- Counting only direct costs. Without the indirect-cost saving, crashing looks like a pure loss. Without the risk cost, it looks like a pure gain.
When to use crashing
Crashing fits best when:
- The critical activities are labor-intensive and can be split among more people.
- Money is available but the date is fixed, for example a regulatory deadline or a launch event.
- The cost per day saved is below the cost per day of delay.
- The cost of the added resources is predictable.
It fits poorly when the budget is tight, when the critical work is knowledge-heavy and hard to share, or when the team is already at capacity. The following chapters cover the alternative, fast-tracking, and how to choose between the two.
Summary of the method
- Find the critical path and every near-critical path.
- List the critical activities that still have room to crash, with their slopes.
- Pick the cheapest change that really shortens the project, which means all tied critical paths.
- Recompute the network. Paths can change after each step.
- Repeat until the target is met or no activity can be crashed further.
- Compare the total crash cost with the savings or penalties avoided.
Exercise
In the example network, suppose C's slope were 100 per day instead of 300, and the target is still 9 days. Starting from the normal schedule (11 days), what is the cheapest way to reach 9 days, and what does it cost? Remember that C is not on the critical path at the start.
Show answer
Step one: only path A, B, D (11 days) is critical, so crashing C alone changes nothing. Crash B by one day for 400, giving 10 days with both paths critical. Step two: both paths must drop by one day. Options are A at 500, D at 600, or B plus C at 400 + 100 = 500. A and B plus C tie at 500. Either way the total is 400 + 500 = 900. The low slope on C does not make it useful until it is on a critical path, and even then it only helps when paired with B.
Exercise
A project has a delay penalty of 450 per day. Using the example network and slopes, is it worth crashing from 11 days to 9 days? Compare the crash cost with the penalty avoided.
Show answer
Crashing to 9 days costs 900. It saves 2 days, which avoids 2 x 450 = 900 in penalties. The two amounts are equal, so crashing breaks even on direct numbers. Looking at each day separately: the first day costs 400, which is below 450, so it is worth it. The second day costs 500, which is above 450, so it is not worth it on cost alone. The best choice is to crash only the first day to reach 10 days, saving 50 net. Risk from the crash and any other schedule value could change that decision.