Sub topic 9
Fast-tracking: doing work in parallel
Fast-tracking shortens a schedule by running activities in parallel that the plan had in sequence. It adds no resources and cuts no scope. The price is paid in risk: work starts before its inputs are final. This chapter covers how overlap works mechanically, how to compute its schedule gain, and how to choose which activities to overlap.
You should already be comfortable with the earlier chapters: the critical path, float, and the reasons a project gets compressed. The chapter on dependency types and leads comes next. Here you only need the idea that a finish-to-start dependency means "B starts after A finishes".
What fast-tracking changes
A schedule network is a set of activities joined by dependencies. Most plans use finish-to-start (FS) links because they are the safest. Activity B waits for A to be completely done, so B starts from a finished, stable input.
Fast-tracking relaxes some of those links. B begins while A is still in progress. In practice there are two ways to do this:
- Add a lead. The FS link stays, but B is allowed to start a set number of days before A finishes. A lead is a negative lag, such as "FS minus 3 days".
- Change the dependency type. An FS link becomes start-to-start (SS), so B starts shortly after A starts. SS is usually paired with a finish-to-finish (FF) constraint, so that B cannot finish before A finishes.
Both change the logic of the network. The activities and their durations stay the same. Only the order constraints between them loosen.
The arithmetic of overlap
Suppose Design takes 6 days and Build takes 8 days. In sequence the pair takes 14 days. If Build can start 3 days before Design finishes, the pair takes 11 days.
design, build = 6, 8
sequential = design + build # finish-to-start: 14 days
build_start = 3 # build starts 3 days before design finishes
overlapped = max(design, build_start + build) # 11 days
print(sequential, overlapped, sequential - overlapped) # 14 11 3The max matters. The pair finishes when the later of the two activities finishes. With a short Build and a large overlap, Design would be the last to finish, and further overlap would gain nothing. The gain from a lead is therefore capped by the successor's duration. A 3-day lead on a 2-day Build saves at most 2 days.
Applying a lead along a chain
Real schedules have more than two activities. The next function computes the finish of a chain of activities where each link has its own lead. It tracks the start of the previous activity so that a lead can never push an activity to begin before its predecessor has started.
def chain_finish(durations, leads):
"""durations: days for each activity in order.
leads: days each activity may start before its predecessor finishes
(one value per link, so len(leads) == len(durations) - 1)."""
prev_start = 0
prev_finish = durations[0]
for dur, lead in zip(durations[1:], leads):
start = max(prev_start, prev_finish - lead)
finish = max(prev_finish, start + dur) # cannot finish before predecessor
prev_start, prev_finish = start, finish
return prev_finish
durations = [6, 8, 4] # Design, Build, Test
print(chain_finish(durations, [0, 0])) # 18 days, all finish-to-start
print(chain_finish(durations, [3, 0])) # 15 days, Build overlaps Design by 3
print(chain_finish(durations, [3, 2])) # 13 days, Test also overlaps Build by 2Each added lead removes days from the chain, and each lead adds a place where work can go wrong. The third line looks attractive on paper. It also stacks two risky overlaps on one path.
Only critical-path overlap shortens the project
The rule from the critical path chapter applies unchanged. A project finishes when its longest path finishes. Overlapping two activities on a path that has float shortens that path, but the project end date does not move.
Consider two parallel paths:
| Path | Activities | Duration (days) | Float |
|---|---|---|---|
| 1 (critical) | Design, Build, Test | 18 | 0 |
| 2 | Procure, Install | 14 | 4 |
Overlapping Procure and Install by 2 days gives Path 2 a duration of 12 and increases its float to 6. The project still takes 18 days and you have taken on risk for nothing. Overlap a pair on Path 1 and the project shortens, until Path 1 drops to the length of the next longest path. After that point, the near-critical path becomes critical and further overlap on Path 1 gains less than its nominal amount.
Choosing what to overlap
Not every FS link can be loosened. Dependencies come in kinds, and the kind decides whether overlap is even possible.
- Mandatory (hard) logic. Physical or legal necessity. You cannot install a roof before the walls exist. These links usually cannot be overlapped, or only at the edges.
- Discretionary (soft) logic. Preferred practice, set by the planning team. "We finish all design before any build" is often a preference. These are the natural candidates.
- External dependencies. A supplier delivery or a regulator's approval. Overlap here means acting on an assumption about someone else's output.
Good candidates tend to share three traits:
- The predecessor's output stabilizes early. For example, the architecture of a software module is fixed after the first few days of design, while the detailed documents are still being written.
- The successor can start with partial input. Build can begin on the parts of the design that are already approved.
- Changes to the predecessor are cheap to absorb. Rework on the successor's early work is small, because that work is low in volume or easy to redo.
Poor candidates are links where the predecessor's final step is the one that settles the answer, such as a test result that decides which of two designs to build.
Splitting activities to create overlap
Many FS links are too coarse to overlap directly. A common technique is to split the predecessor into parts and let the successor start when only the first part is done. "Design" becomes "Design core" (3 days) and "Design details" (3 days). "Build" then depends on "Design core" instead of the whole of Design.
This is the same arithmetic as a 3-day lead, but the dependency is now explicit in the network. The link says what the successor actually needs. A lead only states a time offset, which hides that assumption. A split also makes the risk visible: if "Design details" later changes something that "Build" relied on, the network shows exactly which pair is exposed.
Fast-tracking compared with simply working in parallel
Some activities are parallel from the start because they do not depend on each other. That is normal scheduling, not fast-tracking. Fast-tracking applies when you take activities that the logic says should be in sequence and deliberately overlap them. The word "deliberately" matters: you are accepting that the original ordering existed for a reason and you are choosing to bypass part of it.
This is also why fast-tracking must be recorded in the schedule baseline and the risk register. A reader who sees Build starting before Design ends should find a note explaining what Build is allowed to assume.
Common errors
- Overlapping off the critical path. Risk is added and no schedule time is gained.
- Ignoring the finish constraint. If B starts early but needs A's final result, B cannot truly finish before A does. Leave out the FF constraint and the schedule shows a finish date that cannot happen.
- Treating the gain as certain. The 3 days saved in the example assume no rework. Work that depends on unfinished input may need redoing, and the next chapter quantifies that.
- Stacking overlaps on one path. Each added overlap increases the chance that something upstream changes. Two small overlaps are more dangerous than one, because a late change can invalidate both downstream activities.
- Forgetting resource load. Overlap means two activities need people at the same time. If the same team staffs both, the overlap may be impossible without adding people, which is crashing, not fast-tracking.
- Using fast-tracking on mandatory logic. If the dependency is physical, the overlap exists only on paper.
A short decision checklist
Before you fast-track a pair of activities, ask these questions in order:
- Is the pair on the critical path, and how much float does the next path have?
- Is the dependency discretionary, or can it be split so that the successor depends only on a stable part?
- Which parts of the predecessor's output could still change, and what would that change cost the successor?
- Do the two activities compete for the same people?
- Is the overlap recorded in the baseline with its assumption written down?
If question 1 fails, stop. If questions 2 to 4 give weak answers, the saved days are likely to be given back as rework.
Exercise
A chain has Design (6 days), Build (8 days) and Test (4 days), all finish-to-start, so it takes 18 days. A second path through the project takes 16 days. You apply a 3-day lead between Design and Build. By how many days does the project duration shrink, and why? Assume no rework.
Show answer
The chain drops to 15 days, but the second path still takes 16 days. The project is now limited by the second path, so the project duration shrinks from 18 to 16 days, a gain of 2 days, not 3. The extra day of lead only moves the critical path onto the second path.
Exercise
Build has a duration of 2 days and follows Design (6 days) with finish-to-start logic. You allow Build to start 5 days before Design finishes, with the constraint that Build cannot finish before Design finishes. What is the finish of the pair, and what is the saving?
Show answer
Build starts on day 1 (6 minus 5) and would finish on day 3, but it cannot finish before Design does, so the pair finishes on day 6. The sequential duration is 8 days, so the saving is 2 days, which equals Build's whole duration. A lead larger than the successor's duration gains nothing extra.
Exercise
Name two reasons a planner might leave a finish-to-start link unchanged even though the pair is on the critical path.
Show answer
Any two of: the dependency is mandatory logic that physically or legally requires the predecessor to finish first; the predecessor's output is still unstable, so the rework risk outweighs the days saved; the same people would have to staff both activities at once, so the overlap is not resource-feasible.