Sub topic 11
Run and monitor the pilot
This chapter assumes you have already written the hypothesis, success criteria, guardrails, rollback plan and data collection plan, and that you trained the pilot team. It covers the period between "go live" and "collect the final data": how to keep the pilot honest, spot trouble early, and avoid ruining the evidence while you watch it.
What running a pilot involves
A pilot has two jobs at once. The team operates the changed process to deliver real work. You also run an experiment on that process. These jobs pull against each other. Operators want to fix problems as they appear, but every undocumented fix changes what you are testing.
Monitoring therefore has three goals:
- Confirm the change is being applied as designed (fidelity).
- Confirm the data is complete and trustworthy.
- Confirm that no guardrail metric is moving toward its limit.
Monitoring is not for deciding whether the pilot "worked". That judgment waits for the analysis, using the criteria you fixed in advance.
Before day one
Spend a short session on go-live readiness. A checklist works well:
- The written procedure for the changed process is at the workstation, not only in a shared folder.
- Every pilot participant has completed training and knows the stop-and-call rules.
- The measurement method works. Someone has recorded a test entry end to end.
- The comparison group is identified, and its data collection is running.
- Named people own the daily review, the guardrail check and the rollback decision.
- Everyone knows the planned end date and the interim review dates.
If an item fails, delay the start. A pilot that starts with broken measurement produces weeks of unusable data.
Set a monitoring cadence
Match review frequency to the risk and the process speed. A pilot in a call center that handles hundreds of cases a day needs a daily glance. A monthly billing change may need a check at each billing run.
| Review | Frequency | Who | Purpose |
|---|---|---|---|
| Guardrail check | Every shift or day | Pilot owner | Catch harm early and trigger rollback review |
| Data completeness check | Daily | Data owner | Find missing or suspicious records while they can still be recovered |
| Fidelity check | Weekly, plus spot checks | Process lead | Confirm the team follows the new procedure |
| Interim review | Planned points, such as weeks 1 and 3 | Sponsor and team | Review issues and risks, not the result |
Keep the daily checks short and mechanical. Automate them if you can.
What to watch
Watch four kinds of signal:
| Signal | Example | Likely meaning | Response |
|---|---|---|---|
| Guardrail drift | Defect rate rising above the agreed limit | The change may be causing harm | Follow the rollback plan |
| Missing data | Fewer records than units processed | Collection steps are being skipped | Fix the collection step and note the gap |
| Protocol deviation | Operators skip a new inspection step | The pilot is no longer testing the designed change | Retrain and log the affected period |
| Unusual values | A day far outside baseline variation | Real effect, special event, or measurement error | Investigate and annotate before analysis |
Separate noise from signals
Day-to-day results vary even when nothing has changed. Use the baseline to judge what "unusual" means. Compute the baseline mean and standard deviation, then flag any day that falls outside about three standard deviations of the baseline mean. A single flagged point is a prompt to investigate. It is not a verdict.
For guardrails, use the limit from your plan, not a new one. For a small daily volume, one defect can swing the rate sharply, so require that a breach persists, such as two consecutive days, before escalating to a rollback review. A severe safety or compliance breach should skip this rule and trigger an immediate stop.
A simple daily monitor
The script below applies those rules to daily records. It checks data completeness, the defect guardrail with a persistence rule, and cycle time against baseline limits.
from statistics import mean, stdev
baseline = [42, 45, 39, 48, 44, 41, 46, 43] # cycle time in minutes, before the change
center = mean(baseline)
sigma = stdev(baseline)
lower, upper = center - 3 * sigma, center + 3 * sigma
DEFECT_LIMIT = 0.03 # guardrail agreed before the pilot
PERSISTENCE_DAYS = 2 # consecutive breach days that trigger escalation
MIN_COMPLETENESS = 0.90 # share of units that must have a data record
days = [
{"day": 1, "units": 40, "records": 40, "defects": 1, "cycle_mean": 39.5},
{"day": 2, "units": 40, "records": 40, "defects": 1, "cycle_mean": 37.8},
{"day": 3, "units": 40, "records": 38, "defects": 0, "cycle_mean": 36.9},
{"day": 4, "units": 40, "records": 40, "defects": 2, "cycle_mean": 37.2},
{"day": 5, "units": 40, "records": 31, "defects": 1, "cycle_mean": 36.5},
{"day": 6, "units": 40, "records": 40, "defects": 0, "cycle_mean": 34.2},
{"day": 7, "units": 40, "records": 40, "defects": 2, "cycle_mean": 36.4},
{"day": 8, "units": 40, "records": 40, "defects": 2, "cycle_mean": 36.8},
]
breach_streak = 0
for d in days:
flags = []
rate = d["defects"] / d["units"]
if d["records"] < MIN_COMPLETENESS * d["units"]:
flags.append("missing data")
if rate > DEFECT_LIMIT:
breach_streak += 1
flags.append(f"defect rate {rate:.3f} over limit")
else:
breach_streak = 0
if not lower <= d["cycle_mean"] <= upper:
flags.append("cycle time outside baseline limits, investigate")
if breach_streak >= PERSISTENCE_DAYS:
flags.append("ESCALATE: start rollback review")
status = "; ".join(flags) if flags else "ok"
print(f"Day {d['day']}: {status}")Running it flags day 4 for a defect breach and day 5 for missing data. Day 6 falls below the baseline lower limit of about 34.9 minutes, so someone must check whether the reading is real or a recording error. Days 7 and 8 breach the guardrail in succession, so day 8 escalates.
Document everything that happens
Keep a pilot log with a dated entry for each event: staff absences, equipment failures, supply shortages, changes to the procedure, holidays, and any unusual customer or demand pattern. At analysis time, this log explains outliers and tells you which periods to exclude or treat separately.
Record each entry with the date, what happened, who was affected, what was done, and whether the pilot or comparison group was involved.
Intervene carefully
When a problem appears, choose among three responses:
- Fix the execution. Operators are not following the procedure, so retrain or clarify. The pilot continues unchanged. Note the affected period.
- Pause. An external event, such as a system outage, makes the data meaningless. Stop the clock and restart afterwards.
- Change the design. The procedure itself is flawed. Treat this as a new pilot. Record the old data as a separate phase, and do not blend the two phases in the final analysis.
Small mid-pilot tweaks are tempting, but they leave you unable to say what produced the result. Collect improvement ideas in a list for the adjust phase.
Keep early results in perspective
Early days are rarely typical. Operators are learning the procedure, which tends to slow things down. Attention from sponsors can also make people work harder than usual (the Hawthorne effect), which flatters the results. Both effects fade, so judge the pilot on the full planned period. A strong first week is not a reason to end early. A slow first week is not a reason to stop, unless a guardrail is breached.
If you want a rule for early stopping on efficacy, set it in the pilot plan before you start. Looking at results repeatedly and stopping when they look good inflates the chance of a false win.
Common errors
- Peeking and tweaking. Changing the process after seeing early numbers makes the final result impossible to interpret.
- Silent data gaps. Missing records are often not random. Busy periods get skipped, and busy periods are when the process is under most stress.
- Treating one point as a trend. React to a persistent pattern, except for severe harm.
- Letting the comparison group drift. If the control group gets informal versions of the change, the contrast shrinks.
- No named owner. Without one accountable person, guardrail alarms get noticed by everyone and acted on by no one.
Close the data collection
When the planned period ends, stop collecting on the agreed date. Reconcile the records against the units processed, fill gaps where you can, and lock the dataset. Add the pilot log and a short note on every deviation. These go into the analysis step as inputs.
Exercise
A pilot's guardrail limit for defects is 3%. On day 3 the defect rate is 5% on 40 units, and on day 4 it is back to 2%. The plan says to escalate after two consecutive breach days, unless the harm is severe. What should the team do, and what should they record?
Show answer
Do not start a rollback review, because the breach was a single day and was followed by a return under the limit. Record the day 3 breach and its likely causes in the pilot log, and look at the affected units. Keep monitoring so that a second consecutive breach would escalate. If the day 3 defects had involved a safety or compliance issue, the team should have stopped immediately regardless of the persistence rule.
Exercise
Halfway through the pilot, the team finds that the new inspection step is being skipped on night shifts. List two responses that protect the pilot's validity and one response that damages it.
Show answer
Protective responses: retrain the night shift and log the dates when the step was skipped, so those days can be analyzed separately or excluded. Alternatively, pause the pilot on night shifts until fidelity is restored. A damaging response is to quietly remove the inspection step from the procedure, because then the pilot no longer tests the designed change and earlier data cannot be combined with later data.