Measure the Baseline
This chapter assumes you can compute a mean and a standard deviation, know what cycle time, defect rate, and throughput mean, and have already written a hypothesis with a success criterion for your pilot. The baseline is the measurement that gives that criterion something to be compared against.
Why the baseline comes before the pilot
A baseline is a measurement of how the current process performs, taken before the change. Without it, "cycle time fell to 37 minutes" means nothing. You cannot tell whether 37 is an improvement, a normal good week, or the result of an easier mix of work.
The baseline does three jobs:
- It sets the reference value for the success criterion. A target such as "reduce mean cycle time by 10%" needs a number to take 10% of.
- It shows how much the metric varies by itself. If cycle time normally swings between 38 and 50 minutes, a pilot result of 37 is weak evidence.
- It lets you check whether the pilot group was already different from the rest of the organization before anything changed.
Teams that skip the baseline often reconstruct it afterward from memory or from a convenient report. The numbers then tend to flatter the change. Measure first, and record the result before the pilot begins.
Choose the metrics to baseline
Baseline every metric that appears in your hypothesis or your guardrails. That usually means:
- The primary metric the change is meant to move, such as cycle time per unit.
- The guardrail metrics that must not get worse, such as defect rate, rework, or customer complaints.
- Context variables that explain variation, such as volume, product type, shift, or operator experience.
Write an operational definition for each one. An operational definition says exactly what is measured, where the clock starts and stops, what is included, and what is excluded. "Cycle time" is ambiguous. "Minutes from the moment a ticket is assigned to the moment it is marked resolved, excluding time in the Waiting for customer status" is not.
Use the same definition in the baseline and in the pilot. A definition that drifts between the two periods produces a difference that the change did not cause.
Decide how much baseline data you need
The baseline has to cover enough of the process's normal variation to be representative. Two rules of thumb help.
- Cover at least one full business cycle. If volume peaks at month end, a baseline taken in the first two weeks of the month understates the load and the cycle time.
- Collect enough observations to estimate the mean and spread with reasonable confidence. For continuous measures such as cycle time, 20 to 30 observations is a common minimum for a first estimate. For rates such as defect percentage, you need enough units that you expect to see several defects. If the defect rate is 2%, a sample of 50 units may contain one defect or none, which tells you almost nothing.
If your process has strong weekly patterns, collect whole weeks. Partial weeks over-weight whichever days they happen to include.
Check that the process is stable
The baseline only predicts the future if the process was stable while you measured it. A stable process varies within a consistent range with no trend, shifts, or special events. An unstable one has a moving mean, so any "before" figure is only a snapshot.
Plot the baseline data in time order. An individuals control chart (I-chart) is the usual tool. It plots each observation in sequence, with a center line at the mean and control limits at about three standard deviations of the short-term variation, estimated from the moving range.
Look for:
- Points outside the control limits, which point to a special cause such as an outage or a one-off large order.
- A run of eight or more points on one side of the center line, which suggests a shift.
- A steady upward or downward drift, which suggests a trend.
If you find a special cause, investigate it. You can exclude those points from the baseline only if you can name the cause and show it will not recur during the pilot. If the process is unstable for no known reason, fix that first, or at least widen your baseline period and report the instability openly. A pilot run on an unstable process will give an ambiguous answer whatever the result.
Compute the baseline summary
Summarize each metric with a center, a spread, and a count. The mean alone hides the variation that you need in the analysis chapter.
from statistics import mean, stdev, median
baseline_cycle_times = [
42, 45, 39, 48, 44, 41, 46, 43, 47, 40,
44, 45, 41, 49, 43, 42, 46, 44, 40, 45,
43, 47, 41, 44, 46,
] # minutes per unit, collected over 5 working weeks
n = len(baseline_cycle_times)
m = mean(baseline_cycle_times)
s = stdev(baseline_cycle_times)
# Moving-range estimate of short-term variation for an I-chart
moving_ranges = [
abs(baseline_cycle_times[i] - baseline_cycle_times[i - 1])
for i in range(1, n)
]
mr_bar = mean(moving_ranges)
sigma_within = mr_bar / 1.128 # 1.128 is the d2 constant for subgroups of 2
ucl = m + 3 * sigma_within
lcl = m - 3 * sigma_within
out_of_control = [
(i, x) for i, x in enumerate(baseline_cycle_times)
if x > ucl or x < lcl
]
print(f"n = {n}")
print(f"mean = {m:.2f}, median = {median(baseline_cycle_times)}, sd = {s:.2f}")
print(f"I-chart limits: LCL = {lcl:.2f}, UCL = {ucl:.2f}")
print(f"points outside limits: {out_of_control}")The moving-range method estimates spread from consecutive differences, so a slow drift inflates it less than it inflates the overall standard deviation. If the overall standard deviation is much larger than sigma_within, that gap is itself a sign of drift or shifts in the data.
Keep the raw data, the operational definitions, the collection dates, and this summary together. The pilot analysis will refer back to all of them.
Use the baseline to set a realistic target
Now you can test whether your success criterion is achievable and detectable. Suppose the baseline mean is 43.9 minutes with a standard deviation of about 2.9. A target of a 10% reduction means a mean of about 39.5 minutes, a drop of 4.4 minutes. That drop is about 1.5 standard deviations, which a small pilot can plausibly detect.
A target of a 2% reduction is under one minute. That is well inside the normal noise, so the pilot would need a very large sample to show it, and a change that small may not justify the cost of rollout anyway. The baseline lets you see this before you commit, and adjust the criterion or the sample size in the later planning step.
Choose the baseline type
There are two common ways to get a baseline, and they answer different questions.
| Approach | What it is | Strength | Weakness |
|---|---|---|---|
| Historical baseline | Data from the same process in a past period | Cheap, available immediately | Conditions may have changed since; data quality may be unknown |
| Concurrent baseline | Data from a control group measured during the pilot period | Same season, same demand, same conditions | Needs a comparison group and extra effort |
Often you use both. A historical baseline tells you the process is stable and sets the target. A concurrent control group protects against changes that happen in the same weeks as the pilot, such as a seasonal rise in volume. The next chapters on pilot design come back to the comparison group.
If you rely only on a historical baseline, state that clearly in your plan and list the conditions you will check to confirm nothing else changed.
Common baseline errors
- Measuring only the pilot site. If the pilot site is already faster than average, a baseline taken elsewhere will exaggerate the improvement. Baseline the pilot site itself.
- Changing the definition midway. Recording "start" at ticket creation before and at ticket assignment during the pilot creates an artificial gain.
- Cherry-picking a bad period. Choosing a baseline window that includes an outage makes the current process look worse than it is.
- Observing people while they know it. Workers who know they are being timed often speed up. This is the Hawthorne effect. Use data the system already records when possible, and collect the baseline before announcing the pilot widely, or announce the measurement program without tying it to the change.
- Ignoring data quality. Check for missing values, duplicate records, and timestamps entered by hand. Sample a few records and trace them to the source.
- Using the mean alone on skewed data. Cycle times often have a long right tail. Report the median and a high percentile such as the 90th alongside the mean.
A baseline checklist
Before you move on, confirm each of these:
- Every metric has a written operational definition.
- The data covers at least one full cycle of normal variation.
- The process looks stable on a time-ordered chart, or the instability is documented.
- The summary includes center, spread, and sample size.
- The data source and collection dates are recorded.
- The baseline is saved where it cannot be quietly changed.
Exercise
A team plans to pilot a new intake form. They have five weeks of cycle time data. The I-chart shows one point far above the upper control limit, from the week of a system outage, and the rest look stable. The mean with the outlier is 46 minutes and without it is 44 minutes. What should they do about the baseline?
Show answer
Confirm that the outlier has a known, specific cause (the outage) and that nothing suggests the outage will recur during the pilot. If so, exclude that point and use the 44-minute baseline, and record the exclusion and the reason in the baseline documentation. Do not drop the point silently or only because it is inconvenient. If the cause is unclear, keep the point, extend data collection, and report the instability.
Exercise
Why should a baseline for a metric with a 2% defect rate be based on more than 50 units, and what does a small sample cost you?
Show answer
At a 2% rate, 50 units give an expected one defect, so the observed count could easily be zero or three. The estimated rate would swing between 0% and 6%, which is too imprecise to serve as a guardrail reference or to detect a real change. A larger sample (several hundred units or more) gives a rate estimate narrow enough to compare against the pilot.
Exercise
The pilot site's historical baseline is 44 minutes. During the pilot weeks, demand rises sharply because of a seasonal peak, and the pilot site records 41 minutes. What is wrong with concluding that the change saved 3 minutes, and how would a better baseline help?
Show answer
The comparison mixes the effect of the change with the effect of the seasonal peak, which probably slowed the process. The true effect could be larger or smaller than 3 minutes. A concurrent baseline from a control group measured in the same weeks, under the same demand, separates the change from the season, so the difference between pilot and control reflects the change.