Sub topic 9
Prepare the people involved
This chapter assumes you can already state a pilot hypothesis, you have a baseline, and you have chosen a pilot scope. It also assumes you know basic process measures such as cycle time and defect rate. Here the focus is the people side: who must know about the pilot, what they need to hear, and how they learn the changed process well enough to give it a fair test.
Why people preparation affects the result
A pilot measures a process change. If the people running it are confused, resistant, or untrained, the pilot measures their confusion instead. A good change can look bad because operators skipped steps. A bad change can look good because a motivated team worked extra hard.
Preparation protects the validity of the result. It has three parts:
- Identify and engage the stakeholders.
- Communicate the purpose, scope, and rules of the pilot.
- Train the pilot participants and check that they can do the new process.
Identify the stakeholders
A stakeholder is anyone who is affected by the pilot or who can affect it. List them before the pilot starts. A stakeholder map for a pilot usually has these groups:
| Group | What they care about | What you need from them |
|---|---|---|
| Executive sponsor | Business case, risk, cost | Approval, protection from competing priorities |
| Process owner | Ongoing performance of the process | Agreement on the change and the decision rule |
| Pilot participants | Daily workload, being blamed for errors | Honest use of the new process, honest feedback |
| Supervisors | Output targets, staffing | Release of time for training, support on the floor |
| Neighboring teams | Hand-offs, upstream and downstream effects | Early warning of side effects |
| Customers | Quality, delivery, service | Notice if they will see any difference |
| Data and IT staff | Systems, reports, access | Data extracts, tool changes |
Pay special attention to the groups outside the pilot scope. A change inside one team often shifts work to the team next to it. If those neighbors learn about it only when problems arrive, they will distrust the result later.
Name the roles
Give each role a named person, not just a team:
- Pilot lead. Runs the pilot day to day and owns the plan.
- Process owner. Holds authority over the process and signs the go, adjust, or stop decision.
- Data owner. Responsible for the data collection plan and its quality.
- Local champion. A respected person inside the pilot group who answers questions and reports concerns.
- Safety or quality contact. Watches the guardrail metrics and can call a stop.
The last role connects to your rollback plan. If a guardrail is breached, someone must have the authority to act without a long approval chain.
Communicate before, during, and after
Plan communication as a short schedule, not an afterthought. Decide what each message says, who sends it, and when.
| Moment | Audience | Core message |
|---|---|---|
| Before launch | All stakeholders | Why we are piloting, what changes, for whom, for how long |
| Before launch | Pilot participants | What their job looks like now, how they will be supported, how data will be used |
| At launch | Pilot group and neighbors | Start date, who to contact, how to report a problem |
| During the pilot | Sponsor and process owner | Short progress report against the plan and guardrails |
| After the pilot | Everyone informed earlier | The result, the decision, and the reasons |
Say what the pilot is and is not
Participants often assume that a pilot means a decision has already been made. Others fear that the data will be used to rate individuals. State plainly:
- The pilot tests the process, not the people.
- The decision has not been made. It depends on the pre-agreed criteria.
- How the data will be used, and that individual performance will not be reported unless that is truly the case.
- That raising a problem is wanted and will not be penalized.
If you cannot honestly make one of these statements, resolve that before launch. Broken promises about data use are hard to repair and make later feedback unreliable.
Collect input early
People who do the work often know where a new process will break. Hold a short walkthrough of the planned process with a few participants before you finalize it. Ask them where steps are unclear, where a hand-off is missing, and what a busy day would do to the procedure. Record the changes you make because of this input. This improves the design and gives participants a stake in the result.
Train for the pilot
Training has a specific goal in a pilot: every participant should perform the changed process as designed, so that the pilot tests the design. This is called process fidelity.
Build the training package
A practical package includes:
- A one-page description of the changed process, with the old and new steps side by side.
- A worked example using realistic cases, including a difficult one.
- A practice session where participants perform the process with a coach.
- A quick reference card at the workstation or in the tool.
- A named contact for questions during the first days.
Keep the training in proportion to the change. A small step change may need thirty minutes. A change in tools or roles may need several sessions and supervised first runs.
Check competence, not attendance
Attendance records show who was in the room. They do not show who can do the work. Use a short check, such as having each participant walk through a sample case, and note who needs a second session. Do this for everyone, including experienced staff, because experts tend to fall back on habit.
Plan for turnover and absence
Pilots last weeks. People take leave, swap shifts, or leave the team. Decide in advance how a new or returning person is trained before they join the pilot work. Record when it happens, because a change in staffing in the middle of the pilot can affect the data.
Protect fairness of the test
Preparation can distort results if done carelessly. Watch for these effects:
- Attention effect. People who know they are observed often work harder or more carefully. This can inflate the improvement. Reduce it by keeping observation light and by comparing against a control group that receives similar attention where possible.
- Selection of enthusiasts. If only volunteers join, the results may not hold for the wider group. Your scope selection chapter covers representativeness. Training should treat volunteers and assigned staff the same.
- Over-coaching. If the pilot group gets far more help than the full rollout will provide, the result will not scale. Plan support at a level you can later afford for everyone.
- Hidden workarounds. Participants may adapt the process in ways you did not design. Without fidelity checks, you will credit the design for something a workaround produced.
Monitor fidelity during the pilot
Track how closely people follow the new process. A simple fidelity log lists the key steps and notes whether each was done as designed.
steps = ["verify_order", "new_checklist", "second_review", "log_result"]
observations = [
{"person": "A", "done": {"verify_order", "new_checklist", "second_review", "log_result"}},
{"person": "B", "done": {"verify_order", "new_checklist", "log_result"}},
{"person": "C", "done": {"verify_order", "log_result"}},
]
for obs in observations:
followed = sum(1 for s in steps if s in obs["done"])
missed = [s for s in steps if s not in obs["done"]]
print(f"{obs['person']}: {followed}/{len(steps)} steps followed, missed: {missed}")Output:
A: 4/4 steps followed, missed: []
B: 3/4 steps followed, missed: ['second_review']
C: 2/4 steps followed, missed: ['new_checklist', 'second_review']Here, person C skipped two of the four steps. If the pilot results are disappointing, you need to know whether the design failed or whether it was not followed. A pattern of skipped steps may also show that a step is too slow, unclear, or unnecessary. That is useful feedback about the design.
Handle feedback and resistance
Resistance is information. People usually resist for a reason: extra work, unclear benefit, fear of blame, or a genuine flaw in the design. Respond in this order:
- Listen and record the concern in a log.
- Check whether it points to a real defect in the process or the training.
- Fix training or clarity problems quickly.
- For design problems, avoid changing the process mid-pilot unless a guardrail is at risk. Mid-pilot changes make the data hard to interpret. If you must change it, record the date and treat the periods before and after as separate.
Set up a simple channel for feedback, such as a shared form, a weekly ten-minute check-in with the local champion, or both. Report back what you did with the feedback. People stop giving it when nothing seems to happen.
Common errors
- Training only the supervisors and expecting them to pass it on.
- Announcing the pilot by email only, with no chance to ask questions.
- Forgetting the neighboring teams until a hand-off fails.
- Treating training attendance as proof of competence.
- Giving the pilot group extra staff or coaching that the rollout will not have.
- Changing the process mid-pilot without recording it.
- Promising that data will not be used for individual evaluation, then using it that way.
Exercises
Exercise
A pilot of a new approval step shows no reduction in cycle time. A fidelity log shows that 5 of 8 participants skipped the new step on busy days. What should you conclude, and what should you do before deciding to stop?
Show answer
You cannot conclude that the design failed, because most participants did not perform it as designed. First find out why the step was skipped: unclear instructions, too much time, or lack of support. Fix the training or the step if that is the cause, then either extend the pilot with the fixed process or rerun it, recording the change date. Stopping now would judge a process that was not tested.
Exercise
Name three stakeholder groups outside the pilot team that should be told before launch, and state one thing you need from each.
Show answer
Any three of these. The executive sponsor, for approval and protection from competing priorities. Neighboring teams, for early warning of side effects at hand-offs. Supervisors, for releasing staff time for training. Data and IT staff, for data extracts or tool changes. Customers, for awareness of any visible change.
Exercise
The pilot group receives a full-time coach, but the full rollout will have none. Why is this a problem for the pilot result, and how would you fix the plan?
Show answer
The improvement may come from the coaching rather than the process change, so it may not appear at scale (over-coaching). Fix the plan by limiting coaching to the level the rollout can afford, or by measuring and reporting the result with and without extra support so the decision accounts for it.