Sub topic 5
Mapping the Normal Path First
This chapter assumes you can read a basic flowchart, know which process you want to improve, and understand cycle time (start to finish) and wait time (idle time between steps). It also assumes you have already set the scope and chosen your lanes in earlier chapters. Here you draw the first real content on the map: the normal path.
What the normal path is
The normal path, often called the happy path, is the sequence of steps a typical request follows when nothing goes wrong. Every step succeeds, every input is complete, and every approver says yes. It is the route most work items take most of the time.
You map it first for three reasons.
- It gives you a spine. Decisions, exceptions and rework loops all branch off the normal path. Without the spine you have nothing to attach them to.
- It keeps the first session short. People tend to start with "but sometimes..." stories. Those stories matter, but they bury the basic flow if you tell them first.
- It is easier to check. A normal path of 8 to 15 steps can be read aloud and confirmed in minutes.
A good test: if you picked a recent, ordinary case and followed it through, would it pass through every box you have drawn, in the order you drew them? If yes, the normal path is right.
Define "normal" with data, not memory
"Typical" is a claim that needs evidence. Before you draw, pick the case type that covers the largest share of volume.
- Pull 20 to 30 recent completed cases from the system of record (a ticket tool, an order log, a shared mailbox).
- Group them by the route they took.
- Choose the most common route as your normal path.
If one route covers about 70% of cases, map that route first. If three routes each cover about a third, you do not have one normal path. You have three variants, and you should either map each separately or split the scope.
Work from the trigger forward
Start at the trigger you defined in the scope and move one step at a time toward the end point. At each step, ask one question: "What happens next, and who does it?" The "who" decides the lane. The "what" decides the label.
Follow these rules while you draw.
- One actor per step. If a step needs two people, you have hidden a handoff. Split it into two steps, one per lane.
- Verb plus object. Label each activity with an action and the thing acted on: "Review request", "Create invoice", "Send confirmation". Avoid labels such as "Handle" or "Process" alone.
- Describe what happens, not what should happen. Draw the real sequence, including awkward steps such as "Re-key data into second system".
- Include waiting only as a step if it is a real queue. "Wait for approval" is a real state that you will measure later. Mark it, but do not invent waits that have no owner or cause.
- Stay at one level of detail. Do not draw "Review request" as one box and "Click Save" as another.
A worked example
Take a customer service request process. The trigger is "Customer submits request". The end point is "Customer receives result". Three lanes are in scope: Customer, Support and Fulfillment.
Walking the normal path gives this sequence.
| Step | Actor (lane) | Activity |
|---|---|---|
| 1 | Customer | Submit request |
| 2 | Support | Review request |
| 3 | Support | Confirm information is complete |
| 4 | Fulfillment | Process request |
| 5 | Customer | Receive result |
Step 3 is a check. On the normal path the answer is always "yes", so for now it is drawn as a plain step or as a decision with only the "yes" exit. The "no" exit is added in the next chapter.
Here is the normal path drawn as a Mermaid flowchart. Each subgraph is one lane, and the arrows between subgraphs are the handoffs.
The same path in PlantUML, where each |Name| line switches lanes:
@startuml
|Customer|
start
:Submit request;
|Support|
:Review request;
|Fulfillment|
:Process request;
|Customer|
:Receive result;
stop
@endumlBoth versions show the same thing. Notice that the path crosses a lane boundary three times. Each crossing is a handoff, and the later chapters on handoffs and waste analysis build on them. For now, simply make sure each crossing is drawn.
Placing steps in the right lane
The lane is the actor who performs the work, not the person who owns the outcome or who is told about it. Common mistakes at this stage:
- Placing a step by owner rather than doer. A manager may be accountable for "Approve refund", but if a clerk keys the approval after the manager emails "OK", the keying is the clerk's step.
- Skipping the system lane. If an automated job moves a file or sends an email, that is a step. If you have a System lane, draw it there. Leave it out and the delay between a person's action and the system's reaction disappears.
- Mixing "where it is stored" with "who acts". A shared drive is not an actor.
When two actors truly do a step together, such as a joint review meeting, draw it in one lane and add a note naming the other participant. Or draw it as a step that spans lanes, if your tool allows that. Be consistent about whichever you choose.
Keep the flow direction consistent
Choose one reading direction and hold it. With horizontal lanes, time runs left to right. With vertical lanes, time runs top to bottom. Arrows that run backward are a signal: a backward arrow almost always means rework, which belongs in the next chapter, not on the normal path. If you find a backward arrow while drawing the normal path, check whether the step is really normal or whether you are mixing in an exception.
Check the path as you draw
After each step, run a short check.
- Does this step have exactly one incoming arrow on the normal path?
- Does it have exactly one outgoing arrow (apart from decision points)?
- Does the output of the previous step match the input of this one? If "Review request" produces a decision but "Process request" needs a completed form, something is missing between them.
- Is there any step that no one could name an owner for? An ownerless step is often a gap in the process.
Gather the information from the right source
A map drawn from a manager's description often shows the designed process, not the real one. Use these sources, in order of reliability.
- Observation. Sit with the person doing the work, or watch a screen recording.
- Traced cases. Follow two or three real cases through records and timestamps.
- Interviews. Ask each lane's people to describe their own steps. Ask each person only about their own lane, then stitch the answers together.
- Documented procedures. Use these last, as a draft to compare with what you saw.
Differences between sources are useful findings. Do not smooth them over. Note them beside the step so you can resolve them when you validate the map.
When to stop drawing the normal path
The normal path is complete when:
- Every step from trigger to end point is present.
- Every step sits in the lane of its actor.
- Every lane crossing is drawn as an arrow.
- Someone who works in the process agrees that "this is how an ordinary case goes".
You do not need times, volumes or error rates yet. Resist the urge to add them. Measures are added after the full as-is map has been validated, and adding them too early slows the session and distracts from getting the sequence right.
Common errors at this stage
| Error | Effect | Fix |
|---|---|---|
| Drawing exceptions in the first pass | The map becomes a tangle and the main flow is unclear | Park exceptions on a list and add them next |
| Mapping the ideal, not the actual | The map hides the real problems | Observe or trace real cases |
| Steps too fine or too coarse | Either 60 boxes or 3 boxes | Aim for steps that take minutes to hours, not seconds or weeks |
| Several actors in one step | Handoffs are invisible | Split the step by actor |
| Vague labels such as "Process" | Readers cannot tell what happens | Use verb plus object |
Exercise
A purchase request process has the trigger "Employee submits purchase request" and the end point "Supplier receives purchase order". In the first interview, the buyer says: "The manager approves it, I check the budget, I send the order. Sometimes the budget check fails and I send it back, and sometimes the manager is on leave and the director approves." Using the Employee, Manager, Buyer and Supplier lanes, list the steps of the normal path in order, with the lane for each. Say what you do with the two "sometimes" statements.
Show answer
Normal path: (1) Employee: Submit purchase request. (2) Manager: Approve request. (3) Buyer: Check budget. (4) Buyer: Create purchase order. (5) Buyer: Send purchase order. (6) Supplier: Receive purchase order. The "budget check fails" statement is a decision with a rework loop, and the "manager on leave, director approves" statement is an exception route. Neither goes on the normal path. Write both on a parked list and add them in the next pass, after checking in recent cases how often each happens. One further check: whether "Create purchase order" and "Send purchase order" are really separate steps, which you would confirm by observing the buyer.
Exercise
You pull 30 completed cases. 14 followed route A, 9 followed route B, and 7 followed route C. Can you call route A "the normal path"? What do you do?
Show answer
Route A covers 14 of 30 cases, about 47%, which is not a clear majority. It is the most common route, but more than half of the cases took another route. Map route A first as the baseline, then map B and C as variants, or narrow the scope (for example by request type) so that each map has one dominant route. Check why the routes differ before choosing, because the split may point to a hidden rule, such as case size or customer type.