Annotating Steps with Time, Volume and Error Data
A swimlane map that shows only who does what tells you where the work goes. It does not tell you where the work is slow or where it fails. This chapter adds three kinds of data to each step, so you can find the delays and the rework in the next chapter.
This chapter assumes you have a validated current-state map with lanes, a normal path, decisions, and at least one rework loop. It also assumes you know the difference between the time a task takes and the time it waits.
Why annotate at all
An unannotated map invites opinions. People point at the step that feels slow. Data replaces those opinions with numbers that everyone can check. It also ranks the problems. A step that takes 45 minutes but waits 8 hours is a different problem from a step that takes 3 hours with no wait.
Annotate only after the map is validated. If the structure is wrong, the numbers are attached to steps that do not exist or are in the wrong order.
The measures to collect
Collect a small, consistent set for every step. Too many measures slow the collection and make the map unreadable.
| Measure | Abbreviation | What it means | Typical source |
|---|---|---|---|
| Processing time | PT | Time someone actively works on the item | Time study, observation, estimates from the worker |
| Wait time | WT | Time the item sits before work starts | Timestamps in a ticket system or log, queue counts |
| Lead time | LT | Total elapsed time from trigger to end point | End timestamp minus start timestamp |
| Volume | n | Items per day, week or month through the step | System counts, tallies |
| Percent complete and accurate | %C&A | Share of items that arrive at the step with everything needed | Sample of items, checked by the receiving person |
| Error or rework rate | Err | Share of items that must be redone or returned | Defect log, return counts |
Lead time is not the sum of processing times. It is processing time plus wait time across the whole path. In most administrative processes, wait time is the larger part.
Be clear about where wait time belongs
Pick one convention and state it on the map. The usual one is that wait time belongs to the step that the item is waiting to enter. If a request sits in the support queue for 6 hours before review starts, the 6 hours go on "Review request". If you mix conventions, totals still add up, but people argue about which step to blame.
Use the same unit everywhere
Choose one unit for the whole map, such as minutes, and convert at the edges. Mixing "2 days", "45 min" and "1 h" on one map leads to arithmetic mistakes. Say whether a day means a calendar day or a working day. A request that arrives on Friday afternoon waits much longer in calendar time than in working time.
Collecting the data
You have three main options, and they differ in cost and trustworthiness.
- System timestamps. Ticket, workflow or database logs give start and end times without asking anyone. They are the most reliable source for wait time and lead time. They say little about processing time, because a ticket marked "in progress" is not necessarily being worked on.
- Direct observation or a tally sheet. Watch the work, or ask workers to record start and end for a week. This works well for processing time. It costs effort and can change behaviour while people are being watched.
- Estimates from the people who do the work. Quick, and useful for a first pass. Ask for typical, best and worst cases, not one number. Mark estimates as estimates.
Mark the source on the map or in a legend. A reader should be able to tell a measured 6 hours from a guessed one.
Sampling
You rarely need every item. Take a sample that covers a normal period and includes the exceptions. A sample of 30 to 50 items often shows the pattern. If the process has strong cycles, such as month-end peaks, sample across them or note the cycle on the map.
Report spread, not only the average
Averages hide the problem. If most requests wait 2 hours and a few wait 3 days, the average of 9 hours describes neither group. For each wait time, record the median and a high value such as the worst case or the 90th percentile. Put the typical value on the map and the range in your notes.
Putting the numbers on the map
Attach a short data label to each step. Keep the same order every time, for example PT, then WT, then error rate. Put volume and percentages on the arrows leaving a decision, because that is where the flow splits.
The diagram below annotates the request process from earlier chapters. Times are in minutes unless shown otherwise.
Two details to notice. First, the 1440 minutes on "Request missing information" is a wait for the customer to reply. It is a real delay in the process even though nobody on the team is slow. Second, the 80/20 split on the decision tells you how often the rework loop runs, which you need for the totals below.
Calculating the totals
Once the steps carry numbers, calculate three things.
- Happy-path lead time. Add PT and WT for every step on the normal path.
- Expected lead time. Add the cost of each rework loop, weighted by how often it happens.
- Process cycle efficiency (PCE). Divide total processing time by total lead time. A PCE of 7% means the item is being worked on for 7% of the time it is in the process.
A short script keeps the arithmetic honest and makes it easy to change a number and recompute.
# Each step: (name, processing minutes, wait minutes before the step)
happy_path = [
("Submit request", 10, 0),
("Review request", 15, 360),
("Process request", 45, 480),
("Receive result", 5, 120),
]
# Extra steps taken when information is incomplete
rework_loop = [
("Request missing information", 10, 1440),
("Submit request", 10, 0),
("Review request", 15, 360),
]
rework_rate = 0.20 # share of items that take the loop
def totals(steps):
pt = sum(s[1] for s in steps)
wt = sum(s[2] for s in steps)
return pt, wt, pt + wt
pt, wt, lead = totals(happy_path)
print(f"Happy path: processing {pt} min, waiting {wt} min, lead {lead} min")
print(f"Happy path PCE: {pt / lead:.1%}")
r_pt, r_wt, r_lead = totals(rework_loop)
exp_pt = pt + rework_rate * r_pt
exp_lead = lead + rework_rate * r_lead
print(f"Expected: processing {exp_pt:.0f} min, lead {exp_lead:.0f} min "
f"({exp_lead / 60:.1f} h)")
print(f"Expected PCE: {exp_pt / exp_lead:.1%}")The script prints a happy-path lead time of 1035 minutes with a PCE of 7.2%. With the 20% rework loop included, the expected lead time rises to 1402 minutes (about 23.4 hours) and PCE falls to 5.8%. The rework loop costs 367 minutes per item on average. That is more than the whole processing time of the happy path, and it comes from one decision.
Combining error rates
Error rates compound across steps. If 80% of requests arrive complete and 95% of processed requests are correct, the share of items that go through both steps without rework is 0.80 × 0.95 = 0.76. This is the rolled throughput yield. Roughly one item in four is touched again, even though each step looks acceptable on its own.
Reading the numbers
Look for three patterns before you move on to waste analysis.
- Wait much larger than processing. Here, "Review request" has 15 minutes of work and 360 minutes of queue. Speeding up the reviewer's typing will not help. The queue will.
- A loop with a high rate or a long wait. The 20% loop with a 24-hour customer wait is the single largest contributor to expected lead time.
- Low %C&A at a step's input. A step that often receives incomplete items is paying for an upstream problem. Mark the lane that creates it.
Common problems with annotation
- Mixed definitions. One person reports processing time including interruptions, another excludes them. Write down the definition before collecting.
- Stale data. A number from last year's volume or the old system describes a different process. Date your data.
- False precision. "PT 12.37 min" from three observations is not more accurate than "about 12". Round to the accuracy you have.
- Cluttered maps. If labels hide the flow, move the full data into a table keyed by step name and keep only PT, WT and error rate on the map.
- No owner for each number. Name who supplied it, so someone can answer when the number is challenged.
Exercise
A step takes 20 minutes of work. Items wait 4 hours (240 minutes) before it starts. The step is followed by a final step with 10 minutes of work and no wait. What is the lead time for these two steps, and what is their PCE?
Show answer
Lead time is 20 + 240 + 10 + 0 = 270 minutes. Processing time is 20 + 10 = 30 minutes. PCE = 30 / 270 = 11.1%.
Exercise
In the example map, 15% of items fail the "Information complete?" check instead of 20%. The rework loop adds 1835 minutes to each item that takes it. By how much does the expected lead time drop compared with the 20% case?
Show answer
The expected loop cost falls from 0.20 × 1835 = 367 minutes to 0.15 × 1835 = 275.25 minutes. The expected lead time drops by about 92 minutes, from 1402 to roughly 1310 minutes.
Exercise
Why is it a poor choice to put only the average wait time on a step whose waits range from 10 minutes to 3 days?
Show answer
The average describes neither the typical case nor the worst case, so it hides the long waits that customers actually notice. Record the median and a high value, such as the 90th percentile or worst case, and note the spread.