Finding Waste, Delay and Bottlenecks on the Map
This chapter assumes you already have a validated current-state swimlane map. That means lanes, a scope with a trigger and end point, the normal path, decisions and rework loops, and step annotations for processing time, wait time and error rate. You should also know that lead time is processing time plus waiting time. Here you read the map as evidence and decide where to improve.
What you are looking for
A swimlane map does not show waste directly. You infer it from patterns of lanes, arrows and numbers. Three questions guide the reading:
- Where does work wait? This is delay. It usually appears as a gap between the end of one step and the start of the next.
- Where does work go backwards or repeat? This is rework, a defect cost.
- Where does the flow narrow? This is a bottleneck. One lane or step has less capacity than the demand sent to it.
Most improvement effort belongs to these three. Few steps are waste themselves. The waste sits between steps, in the queues, loops and handoffs.
Classifying each step
Give every step one of three labels:
- Value-adding: the customer would pay for it, and it changes the product or service in a way they want.
- Necessary non-value-adding: the customer does not value it, but the organisation needs it, for example a legal check or an audit record.
- Waste: neither of the above.
Be careful with the second label. It is easy to use as an excuse. For each step labelled "necessary", ask who requires it and what happens if it is removed. If nobody can name a rule or a risk, treat it as waste until someone can.
The eight wastes as map signals
Lean lists eight wastes, often remembered as TIMWOODS. Each one leaves a recognisable mark on a swimlane map.
| Waste | What it looks like on the map |
|---|---|
| Transport | Many arrows that carry files, forms or tickets between lanes with no processing in between |
| Inventory | A queue marker or a "batch" before a step, with a count of items waiting |
| Motion | The same person switching between systems or screens within one step |
| Waiting | A large wait annotation between two steps, or an approval lane with long idle time |
| Overproduction | A step that creates a report, copy or approval nobody downstream uses |
| Overprocessing | Repeated checks, re-keying data, or detail beyond what the next step needs |
| Defects | A rework loop, or a decision that returns work to an earlier lane |
| Skills (unused talent) | A skilled lane doing clerical steps, or an expert approving trivial cases |
Delay: separating wait from work
Delay is the most common finding. Compare the two annotations on each step. Processing time is the minutes someone actually works on the item. Wait time is the minutes the item sits before that work begins. In most administrative processes, wait time is far larger than processing time.
The summary measure is flow efficiency:
flow efficiency = processing time / lead time
Values under 10% are common in office processes and are not a sign that the map is wrong. They show that people are busy while work sits idle.
The script below uses the support-request process from earlier chapters. Rework is weighted by its probability, because only 30% of requests take that branch. It ranks where the waiting happens.
steps = [
{"name": "Submit request", "lane": "Customer", "process": 5, "wait": 0},
{"name": "Review request", "lane": "Support", "process": 10, "wait": 240},
{"name": "Process request", "lane": "Fulfillment", "process": 45, "wait": 480},
{"name": "Receive result", "lane": "Customer", "process": 2, "wait": 60},
]
REWORK_RATE = 0.30
rework = {"name": "Request missing information", "lane": "Support",
"process": 15, "wait": 1440}
rows = [(s["name"], s["lane"], s["process"], s["wait"]) for s in steps]
rows.append((rework["name"], rework["lane"],
rework["process"] * REWORK_RATE, rework["wait"] * REWORK_RATE))
total_process = sum(r[2] for r in rows)
total_wait = sum(r[3] for r in rows)
lead_time = total_process + total_wait
print(f"Lead time: {lead_time:.1f} min")
print(f"Flow efficiency: {total_process / lead_time:.1%}")
for name, lane, proc, wait in sorted(rows, key=lambda r: r[3], reverse=True):
print(f"{name:<28}{lane:<12}wait {wait:>7.1f} min ({wait / total_wait:.0%} of all waiting)")The output is:
Lead time: 1278.5 min
Flow efficiency: 5.2%
Process request Fulfillment wait 480.0 min (40%)
Request missing information Support wait 432.0 min (36%)
Review request Support wait 240.0 min (20%)
Receive result Customer wait 60.0 min (5%)
Submit request Customer wait 0.0 min (0%)Two lessons follow. First, only about 5% of the lead time is work. Second, the rework branch is rare (30% of cases) but accounts for 36% of all expected waiting. Reducing incomplete submissions would cut more delay than speeding up Support's review.
Bottlenecks: where capacity is below demand
A bottleneck is the step or lane whose capacity limits the output of the whole process. Waiting often signals one, but not always. A queue can come from batching or from an approver who is simply away. Test for a bottleneck by comparing demand to capacity.
Take the Fulfillment step above. If one person processes a request in 45 minutes and works 480 minutes a day, capacity is about 10 requests a day. If 14 requests arrive daily, the queue grows by about 4 a day. No amount of improvement in Support will shorten lead time, because work only piles up in front of Fulfillment.
On the map, look for these signs:
- A queue count that grows over weeks instead of staying stable.
- A lane whose people are always busy while downstream lanes are idle.
- A step upstream whose output is held back, or "expedited" by escalation.
- A lane with high utilisation. Above roughly 85%, queues lengthen sharply even when average capacity exceeds demand, because arrivals are uneven.
Handoffs and loops as hotspots
Count the arrows that cross a lane boundary. Each handoff is a place where work can wait, get lost or be misread. Mark a handoff for attention when one of these holds:
- The receiving lane has no clear queue owner.
- Information is re-keyed, attached by email, or interpreted differently by the next lane.
- The same item crosses between the same two lanes more than once.
- The handoff moves work to a lane that adds no processing, only forwarding.
Rework loops deserve the same scrutiny. For each loop, ask which decision triggers it and what information was missing or wrong when the work first passed through. The fix is usually earlier in the process, at the point where the defect was created, not at the check that finds it. In the example, a required-fields form at submission addresses the loop at its source.
Prioritising what you found
Build a short list of hotspots and score each on three factors: share of the total delay, how often it occurs, and how easily it can be changed. Do not work on items alphabetically or in map order.
| Hotspot | Evidence on the map | Share of waiting | Effort |
|---|---|---|---|
| Fulfillment queue | 480 min wait, demand above capacity | 40% | Medium |
| Incomplete requests | 30% rework, 1440 min wait | 36% | Low |
| Review queue | 240 min wait | 20% | Low |
The second row has the best return in this example. It is a small change at the start of the process with a large effect on lead time.
Edge cases and pitfalls
- Averages hide variation. A step that averages 20 minutes but ranges from 5 to 180 causes more downstream queueing than its average suggests. Collect a range or percentile, not only the mean.
- Bottlenecks move. Once you widen Fulfillment, the constraint shifts to the next-slowest step. Recalculate capacity after each change.
- Wait time is often unmeasured. If the tool only records the start and end of a step, you can't see the gap between steps. Use timestamps from handoffs, such as ticket creation and first-touch times.
- Local fixes can be harmful. Speeding up Support's review while Fulfillment is the bottleneck only builds a bigger queue in front of it.
- Some waiting is deliberate. A cooling-off period or a regulatory hold is a constraint, not waste. Document why it exists and leave it out of improvement targets.
- Do not count staff busyness as a goal. High utilisation in a lane is a risk for flow, not a sign of efficiency.
Summary of the method
- Label each step as value-adding, necessary non-value-adding or waste.
- Rank waiting by size, and weight rework by its probability.
- Compare capacity to demand to confirm any suspected bottleneck.
- Review every cross-lane handoff and every loop for root causes.
- Score hotspots by impact and effort, and carry the top items into the future-state map.
Exercise
A map shows three steps. Intake: 10 min processing, 30 min wait. Approval: 5 min processing, 600 min wait. Archive: 5 min processing, 20 min wait. What is the lead time and flow efficiency, and which step should you investigate first?
Show answer
Processing total is 10 + 5 + 5 = 20 min. Wait total is 30 + 600 + 20 = 650 min. Lead time is 670 min. Flow efficiency is 20 / 670, about 3.0%. Investigate Approval first, because it holds 600 of the 650 waiting minutes (about 92%). Confirm whether it is a capacity bottleneck or a batching or availability issue before changing it.
Exercise
A team lane handles 8 items a day at most, and 11 arrive each day. Management proposes training the upstream lane to work faster. Explain why this will not shorten lead time, and name a better target.
Show answer
The team lane is the bottleneck, since capacity (8) is below demand (11), so the queue grows by 3 items a day. A faster upstream lane only delivers work to that queue sooner. Better targets are the team lane's capacity (more people, simpler steps, or removing work that adds no value), or reducing the demand reaching it, such as stopping defective or unnecessary items upstream.