Sub topic 7
Prioritizing with a Power/Interest Grid
Prerequisites and what this chapter covers
This chapter assumes you have already built a stakeholder register, as covered in the earlier chapters. It also assumes you can rate a stakeholder's power and influence. You should be comfortable reading a short Python script and a CSV file.
By the end, you will be able to rate stakeholders on power and interest, place them on a power/interest grid, read the four quadrants, and avoid the usual errors in rating and placement.
Why a register is not enough
A register with 40 stakeholders is complete but hard to act on. You cannot give every person the same attention. Time spent briefing a low-impact observer is time not spent with a sponsor whose support decides the project.
Prioritization answers one question: where should limited engagement effort go? The power/interest grid is a simple tool for that. It sorts stakeholders using two ratings you should already have in the register.
- Power is a stakeholder's ability to affect the project. This may be formal authority (approving budget, stopping work) or informal influence (shaping opinion, controlling a key resource).
- Interest is how much the stakeholder cares about the project's outcome or is affected by it.
The grid is a way to decide on an engagement approach. It does not describe what a person is like.
The four quadrants
The grid has interest on one axis and power on the other. Each axis is split into low and high, which gives four quadrants. Each quadrant has a default approach.
| Quadrant | Power | Interest | Default approach | Typical example |
|---|---|---|---|---|
| Manage closely | High | High | Involve in decisions, consult often | Executive sponsor |
| Keep satisfied | High | Low | Meet their needs, avoid overloading them | Compliance authority |
| Keep informed | Low | High | Share updates, collect feedback | Support team, end users |
| Monitor | Low | Low | Watch for change, minimal effort | Distant departments |
Reading each quadrant
Manage closely. These stakeholders can change the project and want to. Involve them in key decisions, meet them regularly, and ask for their input before you commit. Surprises here are expensive.
Keep satisfied. These stakeholders have power but little interest. They are usually not watching day to day. The risk is that they become interested suddenly, for example when a regulator reviews your audit trail. Meet their requirements fully, and keep communication short and relevant. Too many updates can pull them into the project's details and raise their interest when you do not want it to.
Keep informed. These stakeholders care a lot but cannot directly steer the project. They are often the people who use the result. Do not dismiss them. Their feedback improves the product, and a large group of unhappy low-power people can become a source of influence through complaints, resistance or escalation.
Monitor. Spend little effort here, but do not remove these stakeholders from the register. Review them whenever the project changes.
Step 1: Rate power and interest
Use a numeric scale so the placement is repeatable. The register in this tutorial uses 1 (low) to 5 (high) for both ratings.
A scale with numbers has a benefit over labels like "high" and "low". Two people can compare ratings, discuss the gap, and agree on a number. Labels invite arguments about words.
For power, ask:
- Can this person approve, block or reverse a decision?
- Do they control money, people, or a needed resource?
- Do other stakeholders follow their lead?
For interest, ask:
- How much will the project change this person's work or life?
- Have they asked questions or attended meetings?
- Do they have a stated expectation in the register?
Write a one-line reason beside each rating. A rating without a reason cannot be checked later. Here is the register from earlier chapters, with the two ratings included.
name,role,type,interest,expectation,power,interest_level
Dana Lee,Executive sponsor,internal,Return on investment,Delivery within budget,5,4
Sam Ortiz,Customer support lead,internal,Fewer support tickets,Training before launch,2,5
Acme Regulators,Compliance authority,external,Legal compliance,Documented audit trail,5,2
End users,Daily users of the product,external,Usable workflow,Minimal disruption,1,5The column named interest holds the stakeholder's topic of concern, as text. The column named interest_level holds the numeric rating. Keep these two separate. Mixing them is a common source of confusion when you export the register to other tools.
Step 2: Choose a threshold
Where does "low" end and "high" begin? On a 1 to 5 scale, a common choice is that 3 and above counts as high. That choice affects results, so state it openly.
A threshold of 3 puts the midpoint in the high group. A threshold of 4 is stricter and moves more stakeholders into lower-attention quadrants. Pick one threshold, write it in the register's notes, and use it for every stakeholder. Changing the threshold for one person to get the answer you expect defeats the purpose.
Step 3: Place stakeholders with a script
You can place stakeholders by hand on a whiteboard. A script is useful once the register grows, because it applies the same rule every time and can be re-run after changes.
import csv
import io
REGISTER = """name,role,type,interest,expectation,power,interest_level
Dana Lee,Executive sponsor,internal,Return on investment,Delivery within budget,5,4
Sam Ortiz,Customer support lead,internal,Fewer support tickets,Training before launch,2,5
Acme Regulators,Compliance authority,external,Legal compliance,Documented audit trail,5,2
End users,Daily users of the product,external,Usable workflow,Minimal disruption,1,5
"""
def quadrant(power, interest, threshold=3):
high_power = power >= threshold
high_interest = interest >= threshold
if high_power and high_interest:
return "Manage closely"
if high_power:
return "Keep satisfied"
if high_interest:
return "Keep informed"
return "Monitor"
def place_all(text, threshold=3):
rows = csv.DictReader(io.StringIO(text))
placed = {}
for row in rows:
power = int(row["power"])
interest = int(row["interest_level"])
placed[row["name"]] = quadrant(power, interest, threshold)
return placed
for name, label in place_all(REGISTER).items():
print(f"{name}: {label}")Running it prints:
Dana Lee: Manage closely
Sam Ortiz: Keep informed
Acme Regulators: Keep satisfied
End users: Keep informedNotice that two stakeholders land in the same quadrant. That does not make them identical. Sam Ortiz is an internal lead who can be asked for training help, and end users are a large external group. The grid sets a starting approach, and you refine it using the register.
Testing the threshold
Because the threshold changes the outcome, try more than one. Add this to the script and run it.
for threshold in (3, 4):
print(f"Threshold {threshold}")
for name, label in place_all(REGISTER, threshold).items():
print(f" {name}: {label}")At threshold 4, Dana Lee (power 5, interest 4) stays in "Manage closely". Stakeholders with a rating of exactly 3 are the ones who move. If many people sit on the boundary, rating more carefully is worth the time. Those are the ones where placement is most likely to be wrong.
Common errors in rating and placement
Rating by title
A senior title does not equal project power. A vice president of an unrelated department may have no say over your project. A junior analyst who controls the data you need may have a lot. Rate power on what the person can do to this project.
Treating the sponsor's view as the whole picture
Rating only from your own point of view leaves out how other stakeholders see each other. Ask others, "Who would you need on side to get this approved?" The answers expose influence you did not know about.
Rating interest as support
High interest does not mean a stakeholder is in favor. A person can care a great deal and want the project to fail. The grid says how much attention a stakeholder needs. It does not say whether they support the project. Record support or resistance in a separate column, and read it together with the quadrant.
Freezing the grid
A grid built in the first week is wrong by month three. Interest rises when a change reaches someone's team. Power changes when people are promoted, reorganized or replaced. The next chapters return to keeping the register current, but note now that every placement should carry a date.
Ignoring boundary cases
A stakeholder rated 3 for power sits close to the line. One conversation can change the rating. Mark borderline stakeholders in the register so you re-check them first.
Dropping the "Monitor" group
Low power and low interest today can change. A group that is told nothing might become interested when the change reaches them. Keep them on the register and review the list on a schedule.
Using the grid in practice
A workable routine looks like this:
- Add the power and interest ratings to every register row, with a short reason for each.
- Fix the threshold and record it.
- Run the placement and review the result with at least one other person who knows the project.
- Look at the boundary cases and the surprising placements first. Those usually reveal missing information.
- Record the default approach for each quadrant next to each stakeholder.
- Date the placement and set a review point.
Where the grid falls short
The grid uses two factors only. It does not show a stakeholder's attitude, the size of the impact on them, or the conflicts between them. Two stakeholders in the same quadrant may need different handling because one is supportive and the other resists. Later chapters add conflicting interests and engagement choices on top of the grid. Treat the grid as the first filter, and not as the final decision.
Summary
- The power/interest grid sorts stakeholders into four quadrants using two numeric ratings.
- Each quadrant gives a default approach: manage closely, keep satisfied, keep informed, or monitor.
- The threshold for "high" must be fixed, recorded and applied to everyone.
- A script gives repeatable placement and makes it cheap to re-run after the register changes.
- Common errors are rating by title, treating interest as support, and never updating the grid.
Exercise
A regulator rates power 5 and interest 2 on a 1 to 5 scale, with a threshold of 3. Midway through the project, the regulator announces an inspection of your project's records and their interest rises to 4. What happens to the placement, and what should you change in how you deal with them?
Show answer
The placement moves from "Keep satisfied" to "Manage closely", because both power and interest are now at or above the threshold. You should move from meeting their requirements with brief updates to involving them in decisions and meeting regularly, and you should record the date and reason for the new rating.
Exercise
Using the quadrant function from this chapter, what does quadrant(power=3, interest=2) return with the default threshold, and what does it return with threshold=4?
Show answer
With the default threshold of 3 it returns "Keep satisfied", because power 3 is high and interest 2 is low. With threshold 4 it returns "Monitor", because neither rating reaches 4. This shows why stakeholders on the boundary need extra care.