Sub topic 3
How to Find Stakeholders: Interviews, Documents and Brainstorming
This chapter assumes you know what a stakeholder is and can tell internal from external and primary from secondary stakeholders. It also assumes you know common project roles such as sponsor, project manager and team member. Here you will learn three techniques for finding stakeholders systematically, how to combine them, and which errors to avoid.
Why Memory Is Not Enough
Most project managers start with the people they already know: the sponsor, the team, the customer. Those are the easy ones. The stakeholders who cause problems later are usually the ones nobody listed: a regulator, a team that runs a connected system, or a department that must support the product after launch.
Identification techniques give you a repeatable way to widen the list. Each technique finds a different kind of stakeholder, so you will normally use all three.
| Technique | Best at finding | Main weakness |
|---|---|---|
| Interviews | Hidden relationships, unwritten expectations, informal influencers | Slow, and limited by whom you already know to ask |
| Document review | Formal parties, regulators, contract partners, affected departments | Documents go out of date and miss informal influence |
| Brainstorming | Broad coverage quickly, creative or unusual candidates | Produces noise and can be dominated by loud voices |
Technique 1: Interviews
An interview is a structured conversation with a person who knows the project, the organization or the problem area. You are not only collecting opinions. You are asking that person to name other people who care about the outcome.
Whom to interview first
Start with people who have a wide view of the organization:
- The sponsor, who knows why the project exists and who approved it.
- Senior managers in affected departments.
- Long-serving staff, who know the informal paths for getting things done.
- Customer-facing staff, who know what users actually complain about.
Questions that surface new names
Generic questions ("Who are the stakeholders?") produce short lists. Concrete questions work better:
- Who will use the result of this project every day?
- Who will lose something (time, authority, budget, a familiar tool) when it changes?
- Who must approve, sign off or be consulted before we can proceed?
- Who has been burned by a similar project before?
- Who is not on this list that you would expect to hear from?
Question 5 is the most useful. It is called snowballing: each interviewee names others, and you interview those people in turn. Stop when new interviews produce no new names.
Recording interview results
Write down each name, the source who mentioned it, and any stated interest. Keeping the source lets you check a doubtful entry later. It also shows which people are named repeatedly, which is a rough signal of influence.
Technique 2: Document Review
Documents record who has formal involvement. They are often more complete than memory, because someone had to write down a name to get a contract signed or a budget approved.
Sources worth reading
| Document | What it can reveal |
|---|---|
| Business case or project charter | Sponsor, funding source, intended beneficiaries |
| Contracts and statements of work | Vendors, partners, legal signatories |
| Organization charts | Departments and reporting lines affected by the change |
| Regulations and standards | Authorities, auditors and compliance bodies |
| Previous project reports and lessons learned | Stakeholders who caused problems or were forgotten before |
| Issue and complaint logs | Customers and users with unmet needs |
| Meeting minutes and email threads | Informal participants and decision makers |
| Process documentation | Teams that hand work to, or receive work from, the area you will change |
What to look for
Read with one question in mind: who is named, who is affected, and who must approve? Mark every person, role, team or organization mentioned. Pay particular attention to hand-offs. A process diagram that shows work moving from team A to team B tells you team B is a stakeholder in any change to team A's output.
Limits of documents
Documents show formal structure, not real influence. An organization chart will not show the senior engineer whose opinion the director always follows. Documents also age. A chart that is eighteen months old may list people who have left. Use documents to build a first list, then check it with interviews.
Technique 3: Brainstorming
Brainstorming is a group session where participants generate as many candidate stakeholders as possible before judging any of them. It is the fastest way to get broad coverage, because each participant sees parts of the organization that you do not.
Running a useful session
- Invite a mixed group: team members, a business representative and someone from operations or support.
- State the project in two or three sentences so everyone has the same picture.
- Give people five to ten minutes to write candidates silently, one per note.
- Collect and group the notes. Duplicates merge; unfamiliar names get a short explanation.
- Only then discuss which candidates belong on the list.
The silent writing step matters. If people call out names, senior voices dominate and quieter participants hold back their ideas.
Prompt categories
Participants often run dry after the obvious names. Prompt them with categories:
- People who fund, approve or govern the project.
- People who build or deliver it.
- People who use it or are affected by it.
- People who support, maintain or operate it afterward.
- Organizations outside the company: regulators, suppliers, partners, community groups.
- People who could block or oppose it.
Limits of brainstorming
Brainstorming produces candidates, not facts. Some entries will be duplicates, some will be too vague ("the public"), and some will matter very little. Treat the output as a list to be checked against interviews and documents.
Combining the Techniques
The techniques work best in sequence, with each one feeding the next.
A practical order is:
- Review documents to collect formal stakeholders cheaply and prepare better interview questions.
- Brainstorm with the team to widen the list.
- Interview to confirm, add informal stakeholders, and capture interests.
- Repeat interviews until no new names appear.
You can reorder these. If you are new to an organization, interviews may need to come first because you do not yet know which documents matter.
Worked Example
A company plans to replace its customer support ticketing tool. The project manager runs the three techniques.
Document review. The charter names the sponsor, Dana Lee. The vendor contract names the software supplier. A compliance policy references an external regulator, Acme Regulators, which requires an audit trail of customer communications. The process documentation shows that support tickets feed the billing team's refund process.
Brainstorming. The team writes candidates silently and produces: support agents, the support lead, customers, IT operations, the billing team, the vendor, the regulator, trainers, and "management." The group agrees "management" is too vague and replaces it with named roles.
Interviews. Sam Ortiz, the support lead, says the sales team uses ticket history before renewal calls. Sam also mentions that a long-serving agent informally trains all new hires. Neither group appeared in any document or the brainstorm.
The combined result is a candidate list with the source of each name. This script merges the findings and shows which stakeholders were found by only one technique. Those are the ones to double-check.
sources = {
"documents": {"Dana Lee", "Software vendor", "Acme Regulators", "Billing team"},
"brainstorm": {"Support agents", "Sam Ortiz", "End users", "IT operations",
"Billing team", "Software vendor", "Acme Regulators", "Trainers"},
"interviews": {"Sales team", "Senior support agent", "Sam Ortiz"},
}
found_by = {}
for technique, names in sources.items():
for name in names:
found_by.setdefault(name, set()).add(technique)
for name in sorted(found_by):
techniques = sorted(found_by[name])
flag = " <- single source, verify" if len(techniques) == 1 else ""
print(f"{name}: {', '.join(techniques)}{flag}")In this output, "Sales team" and "Senior support agent" appear only in interviews. That does not make them unimportant. It shows that without interviews they would have been missed, and it tells you to confirm their involvement with a second person.
Edge Cases and Common Errors
Stopping at the first list
A list built in one afternoon is a draft. Treat the first list as incomplete until a round of interviews produces no new names.
Listing roles when you need people, or the reverse
"The finance department" is too broad to engage. Record the department, then name a specific contact. In the other direction, naming only a person creates risk if that person leaves. Record both the person and their role.
Over-reliance on the organization chart
Formal authority and real influence differ. Ask in interviews, "Whose opinion would the director ask before deciding?"
Missing the quiet or distant groups
Stakeholders who are far from the project team are the easiest to forget: end users in other regions, downstream teams, the maintenance group, and external bodies such as regulators or community groups. Use the prompt categories above and ask explicitly about people who operate or support the result.
Confusing identification with engagement
At this stage you are only finding names. Do not decide yet who matters most or how to talk to them. Later chapters cover rating power and interest, and choosing engagement approaches. Judging too early leads you to drop low-ranked candidates before you have learned their interests.
Sensitive information
Interviews often produce frank comments about colleagues. Interview notes that say "Sam will resist this" should be kept private and not copied into a shared register without care. Record the factual interest ("expects training before launch") in the shared document, not the personal assessment.
Recording the Output
Capture results in a form that can be sorted and reused. A short CSV works for the identification stage. The following example keeps the name, how they were found, who suggested them, and whether the entry has been verified.
name,role,found_by,suggested_by,verified
Dana Lee,Executive sponsor,documents,,yes
Acme Regulators,Compliance authority,documents,,yes
Billing team,Refund processing,documents; brainstorm,,yes
Sales team,Uses ticket history in renewals,interviews,Sam Ortiz,no
Senior support agent,Informal trainer,interviews,Sam Ortiz,noThe found_by and suggested_by columns are not part of the final register. They are working notes that let you check and defend each entry. The next chapters add interests, expectations, power and influence to the register.
Summary Checklist
- Start from documents, widen with brainstorming, and confirm with interviews.
- Ask concrete questions, especially "Who else should I talk to?"
- Keep the source of each name.
- Record both roles and named people.
- Keep going until interviews stop producing new names.
- Delay judgment about importance until interests are captured.
Exercise
During an interview for a warehouse system replacement, the operations manager mentions that the delivery drivers' union must be notified of any change to scanning devices. The union appears in no project document and was not named in the brainstorm. What should you do with this name, and what does the situation tell you about the techniques you used?
Show answer
Add the union to the candidate list immediately, record the operations manager as the source, and mark the entry unverified until you have confirmed it with a second person or a document such as the union agreement. Then ask the operations manager for a contact name and keep interviewing, since the new name shows the list is not yet complete. The situation shows that document review and brainstorming missed an informal or external stakeholder, which is why interviews are needed to confirm and extend the list.
Exercise
A brainstorm produces the entries "management," "users," and "IT." Why are these a problem for the register, and how would you improve them?
Show answer
Each entry covers many people with different interests, so you cannot work out expectations or an engagement approach for them. Split them into specific groups and contacts, for example "Regional sales director," "Call-centre agents," and "Network operations team," and name a contact person for each. Keep the role as well as the person's name so the entry survives staff changes.