Sub topic 12
Common Mistakes and How to Avoid Them
This chapter assumes you have read the earlier chapters. You should know what a stakeholder is and how internal, external, primary and secondary stakeholders differ. You should also be able to find stakeholders through interviews, document review and brainstorming, keep a stakeholder register, and place people on a power/interest grid. Here we look at where that work goes wrong in practice and at checks that catch the problems early.
Why the Same Mistakes Keep Appearing
Stakeholder work fails quietly. A missed stakeholder usually shows up months later as a late requirement, a blocked approval or a hostile user group at launch. By then the fix is expensive. Most failures come from four causes:
- The list was built from memory instead of a method.
- The register records assumptions as if they were facts.
- Ratings were set once and never revisited.
- The grid was treated as a verdict instead of a starting point.
The diagram shows where each family of mistakes enters the workflow.
Mistakes in Identification
Relying on Memory
A list written from memory contains the people you already work with. It leaves out the people you have never met, who are often the ones who surprise you. The fix is to use at least two independent techniques and compare the results. For example, run a brainstorming session with the team, then check the list against the project charter, contracts, organization charts and the systems the project touches. Names that appear in documents but not in the brainstorm are your gaps.
A useful habit is to ask every interviewee the same closing question: "Who else should I talk to, and who might object to this?" Each interview then widens the list instead of only confirming it.
Listing Groups Instead of People
Entries such as "IT", "Finance" or "Management" feel complete but cannot be acted on. You cannot schedule a conversation with a department, and different people in the same department often want different things. Name a person for each group. If the group is genuinely large, like end users, name a representative or a sampled set of people, and record how you chose them.
Forgetting External and Secondary Stakeholders
Teams tend to list the people in their own organization first and stop. External stakeholders such as regulators, suppliers, partners and the community are easy to omit because nobody on the team talks to them daily. They also tend to have formal power: a regulator can stop a launch.
Secondary stakeholders are affected indirectly, for example the finance team who will process the new invoices, or the help desk who will field questions. They rarely appear in the project charter. Walk through the product's whole lifecycle (build, deploy, use, support, retire) and ask who touches it at each step.
Confusing Role with Stakeholder
"Project manager" and "team member" are roles. A stakeholder entry needs a specific person, what they hold at stake, and what they expect. Also watch for the reverse mistake, where someone is listed only by name and nobody records why they matter. A register entry without a stated interest cannot support any later decision.
Mistakes in Assessment
Recording Assumptions as Interests
It is tempting to write "wants lower cost" for the sponsor without asking. Assumed interests are often wrong, and they are rarely labeled as assumptions. Add a source field to each entry, such as "interview, 12 Nov" or "assumed". Treat every "assumed" entry as a task: confirm it in the next conversation.
Also separate an interest from a position. A stakeholder's position is what they say they want ("we need the report by Friday"). Their interest is the reason behind it ("the board meets Monday"). Registers that store only positions make conflicts look unsolvable, because two positions can clash while the interests behind them are compatible.
Equating Low Power with Low Importance
The grid ranks stakeholders by power and interest. It does not rank them by how much the project affects them. In the sample register, end users have power 1 and interest 5. The grid puts them in "Keep informed", which sounds passive. Yet if end users reject the product, the project has failed, whatever the sponsor thinks.
Add a separate impact rating, or a note, for groups who bear the consequences of the change. Where impact is high, treat "Keep informed" as a minimum and add active consultation, such as usability testing or a user representative on the project.
Trusting the Threshold Too Much
The script in the spine maps a rating of 3 or higher to "high". That is a convention, not a measurement. A stakeholder rated 3 on power and one rated 2 land in different quadrants, yet the real difference may be tiny. Two practical habits help:
- Review everyone within one point of the threshold by hand. These borderline cases are where the grid is least reliable.
- Rate each stakeholder with a short written reason. "Power 4: approves the budget" is checkable. "Power 4" is not.
Ratings also vary by rater. If two team members rate the same person differently, that disagreement is useful information. Discuss it before averaging it away.
Ignoring Conflicts Between Stakeholders
When two stakeholders want incompatible things, the register shows it only if you look for it. A common mistake is to resolve the conflict silently, by favoring whoever has more power. This often works until the overruled party discovers it later. The better approach is to record the conflict, name the parties and the interests behind each position, and take it to the person with authority to decide, usually the sponsor. Record the decision and the reasoning in the register or the decision log.
Mistakes in Engagement and Maintenance
One Message for Everyone
If every stakeholder receives the same weekly status email, the sponsor skims it, the regulator never sees what it needs, and the support team gets no training information. Match content, frequency and channel to the quadrant and to the stated expectation. The sample register already hints at this: Acme Regulators expect a documented audit trail, which a status email does not provide.
Letting the Register Go Stale
A register created at kickoff and never edited describes the project as it was planned, not as it is. People change jobs, new vendors join, scope shifts, and interest levels move as the project moves from design to rollout. Three practices keep it current:
- Give the register one named owner, usually the project manager.
- Set a fixed review interval, for example monthly, and also review at each phase boundary.
- Define triggers that force an immediate review: a scope change, a new sponsor, a reorganization, a missed milestone, or an unexpected complaint from someone not on the list.
An unexpected complaint deserves special attention. It means someone with an interest was missed, so add them and ask what else the process missed.
Putting Candid Notes Where Stakeholders Can Read Them
A register often contains frank assessments such as "resistant to change" or "influence exceeds title". If the register is shared widely, those notes can damage relationships and trust. Decide who may read the register before you write in it, and keep sensitive assessments in a restricted copy.
Automating the Easy Checks
Some mistakes are mechanical: empty fields, ratings outside the 1 to 5 range, entries nobody has reviewed in months. A short script can find these on every review so people can spend their time on the judgment calls. The script below extends the register format from earlier chapters with a last_reviewed column and prints every problem it finds. In this sample, one entry has a missing expectation, one has a stale review date, and one has an impossible rating.
import csv
import io
from datetime import date
REGISTER = """name,role,type,interest,expectation,power,interest_level,last_reviewed
Dana Lee,Executive sponsor,internal,Return on investment,Delivery within budget,5,4,2026-10-20
Sam Ortiz,Customer support lead,internal,Fewer support tickets,,2,5,2026-05-02
Acme Regulators,Compliance authority,external,Legal compliance,Documented audit trail,5,2,2026-10-20
End users,Daily users of the product,external,Usable workflow,Minimal disruption,1,7,2026-10-20
"""
def audit(rows, today, max_age_days=90):
problems = []
seen = set()
for row in rows:
name = row["name"].strip()
if name.lower() in seen:
problems.append(f"{name}: duplicate entry")
seen.add(name.lower())
for field in ("interest", "expectation"):
if not row[field].strip():
problems.append(f"{name}: empty {field}")
for field in ("power", "interest_level"):
try:
value = int(row[field])
except ValueError:
problems.append(f"{name}: {field} is not a whole number")
continue
if not 1 <= value <= 5:
problems.append(f"{name}: {field} {value} is outside 1-5")
age = (today - date.fromisoformat(row["last_reviewed"])).days
if age > max_age_days:
problems.append(
f"{name}: not reviewed for {age} days (limit {max_age_days})"
)
if not any(r["type"].strip() == "external" for r in rows):
problems.append("Register: no external stakeholders listed")
return problems
rows = list(csv.DictReader(io.StringIO(REGISTER)))
for problem in audit(rows, today=date(2026, 11, 28)):
print(problem)Running it prints:
Sam Ortiz: empty expectation
Sam Ortiz: not reviewed for 210 days (limit 90)
End users: interest_level 7 is outside 1-5The script cannot tell you whether the ratings are right. It only guarantees the register is complete and recent enough to be worth discussing. The last check, "no external stakeholders listed", targets the most common identification gap described earlier.
A Quick Reference
| Mistake | Typical symptom | Prevention |
|---|---|---|
| List built from memory | Surprise objections late in the project | Use two or more techniques and compare results |
| Groups instead of people | Nobody is actually contacted | Name a person or representative per group |
| Missing external or secondary parties | Blocked approvals, unplanned support load | Walk the full product lifecycle |
| Assumed interests | Engagement misses what people care about | Add a source field and confirm assumptions |
| Low power read as low importance | End users reject the result | Rate impact separately and consult high-impact groups |
| Grid treated as a verdict | Borderline cases misplaced | Review ratings near the threshold; write reasons |
| Conflicts resolved silently | Resentment when discovered | Record the conflict and escalate to the decision maker |
| Same message to all | Key people miss what they need | Tailor content, channel and frequency |
| Stale register | Plans based on outdated people and interests | Owner, fixed interval and trigger events |
| Register shared too widely | Damaged trust | Restrict access and publish a reduced version |
Putting It Together
A practical review of any stakeholder register asks five questions in order:
- Did we use more than one technique to find people, and did each interview ask who else we missed?
- Is every entry a named person with a stated interest, an expectation and a source?
- Have we looked at impact on groups with low power, and at borderline ratings?
- Are known conflicts recorded with an owner for the decision?
- Is the review date recent, and is there a named owner and a defined trigger for the next review?
If you can answer yes to all five, you have avoided most of the failures described here.
Exercise
Your register rates "End users" as power 1 and interest 5, so the grid places them in "Keep informed". A colleague says this means a monthly newsletter is enough. Give two reasons this may be a mistake and one action you would take.
Show answer
First, the grid reflects power and interest, not impact. If end users bear the consequences of the change and reject the product, the project fails even though they have little formal power. Second, a newsletter is one-way communication, so it cannot reveal whether the assumed interests ("usable workflow", "minimal disruption") are accurate. Action: rate impact separately, then add two-way engagement such as usability testing or a named user representative on the project, and record the findings in the register with a source.
Exercise
Two stakeholders disagree. The sponsor wants the launch on 1 March. The support lead wants it delayed until training is finished. A teammate proposes simply following the sponsor because the sponsor has more power. What should you do instead, and what should the register record?
Show answer
Record the conflict, naming both parties, and write down the interests behind each position (the sponsor may be driven by a budget or board date, the support lead by ticket volume and readiness). Then take it to the person with authority to decide, usually the sponsor, along with options such as a phased launch or accelerated training. The register or decision log should record the conflict, the interests, the options considered, the decision and its reasoning, so the overruled party is not surprised later.
Exercise
In the audit script, the check 1 <= value <= 5 flags an "End users" interest rating of 7. Name two mistakes from this chapter that the script cannot detect, even when it reports no problems.
Show answer
Any two of the following. Rating a person incorrectly but within range, such as giving a regulator power 2. Recording an assumed interest as if it were confirmed. Leaving out a stakeholder entirely other than the check for having no external stakeholders at all. Listing a group instead of a named person. Silently overriding a conflict. These need human judgment or conversation, not field validation.