Sub topic 9
Choosing an Engagement Approach for Each Group
What this chapter covers
You assume here that you can already build a stakeholder register and rate each stakeholder on power and interest from 1 to 5. You also know how the power/interest grid sorts people into four quadrants. This chapter takes the next step. It turns a grid position into a concrete way of working with each person or group.
An engagement approach is a deliberate choice about how much you involve a stakeholder, in which direction information flows, and who on the team owns the relationship. The grid tells you where a stakeholder sits. The approach tells you what to do about it.
From grid position to starting approach
Each quadrant suggests a default approach. Treat it as a starting point and adjust it with what you know about the person.
| Quadrant | Power | Interest | Default approach | Typical actions |
|---|---|---|---|---|
| Manage closely | High | High | Collaborate and consult | Regular one-to-one meetings, early review of decisions, shared ownership of risks |
| Keep satisfied | High | Low | Consult on key points | Short briefings before milestones, escalation only when their concerns are touched |
| Keep informed | Low | High | Inform, and listen | Newsletters, demos, feedback channels, training sessions |
| Monitor | Low | Low | Watch | Occasional check of the register, general announcements |
Two points are easy to miss.
- Each quadrant has a direction of communication. "Keep informed" is mostly one-way (you send). "Manage closely" is two-way, and the stakeholder can change your plans.
- The approach describes effort, not worth. A "Monitor" stakeholder is not unimportant as a person. They just do not need your scarce time right now.
The diagram below shows how a stakeholder moves through the decision.
Current and desired engagement
The grid ignores attitude. A high-power, high-interest stakeholder who actively opposes the project needs a different approach from one who champions it, even though both land in "Manage closely".
A common tool for this is the stakeholder engagement assessment. For each stakeholder you record two levels:
- Current level: where they are now.
- Desired level: where the project needs them to be.
A widely used scale has five levels.
- Unaware: does not know about the project or its effects.
- Resistant: knows about it and opposes the change.
- Neutral: knows about it and neither supports nor opposes it.
- Supportive: knows about it and backs the change.
- Leading: actively works to make the project succeed.
The gap between current and desired level is what your engagement actions must close. If Dana, the executive sponsor, is "Supportive" and needs to be "Leading", you might ask her to open the kickoff and to chair the steering group. If the regulator is "Neutral" and only needs to stay "Neutral", you do nothing beyond a scheduled update.
Not every stakeholder needs to be "Leading". Pushing everyone toward the top level wastes effort and can annoy people who prefer to stay out of the way. Set the desired level by asking what the project needs from that person.
Matching tactics to the gap
Once you know the gap, pick tactics that fit it.
| Gap | Likely cause | Tactics |
|---|---|---|
| Unaware to Neutral | No one has told them | Direct briefing, a short written summary, a named contact |
| Resistant to Neutral | Fear of loss, past bad experience, or a real concern you have not addressed | One-to-one conversation to find the cause, change the plan where the concern is valid, involve them in a pilot |
| Neutral to Supportive | They see no benefit to them | Show what they gain, share evidence from early results, ask for their input on a decision that affects them |
| Supportive to Leading | They lack a role or time | Give a visible role, such as sponsor of a workstream, and agree how much time it takes |
Resistance deserves special care. It often carries information. A support lead who resists a launch date may be telling you that training is not ready. Listen for the reason before you try to change the attitude. This links to the previous chapter on conflicting interests: when resistance comes from a real clash between stakeholders, raise it for a decision instead of trying to talk one side around.
Choosing the channel and the owner
An approach also needs a channel and an owner.
- Channel: the way you reach the person. Examples are a weekly call, a steering group, an email digest, a shared dashboard, or a hallway conversation. Match the channel to the stakeholder's habits and to how much detail they need.
- Owner: one named person on the team who is responsible for the relationship. Without an owner, everyone assumes someone else is handling the regulator, and no one does.
Pick the owner by relationship and seniority. A junior team member should not be the only contact for an executive. Equally, the project manager cannot personally manage forty end users, so assign a representative group or a team member to handle them.
For large groups, engage through representatives. Rather than speaking to every end user, form a user panel of five to ten people who cover the different roles, and use them for testing and feedback. State clearly how they were chosen, or other users may feel unrepresented.
Recording the approach in the register
Engagement information belongs in the stakeholder register or in a linked sheet. Add columns for the following:
- Quadrant
- Current level
- Desired level
- Approach and main tactic
- Channel and frequency
- Owner
The next chapter covers the communication plan in detail. For now, a short entry in the register is enough.
The following Python script extends the grid logic from earlier. It reads each stakeholder, finds the quadrant, and flags those whose current level is below the desired level, so you can see where action is needed.
LEVELS = ["Unaware", "Resistant", "Neutral", "Supportive", "Leading"]
APPROACH = {
"Manage closely": "Collaborate and consult",
"Keep satisfied": "Consult on key points",
"Keep informed": "Inform and listen",
"Monitor": "Watch",
}
def quadrant(power, interest, threshold=3):
high_power = power >= threshold
high_interest = interest >= threshold
if high_power and high_interest:
return "Manage closely"
if high_power:
return "Keep satisfied"
if high_interest:
return "Keep informed"
return "Monitor"
# name, power, interest, current level, desired level, owner
stakeholders = [
("Dana Lee", 5, 4, "Supportive", "Leading", "Project manager"),
("Sam Ortiz", 2, 5, "Resistant", "Supportive", "Change lead"),
("Acme Regulators", 5, 2, "Neutral", "Neutral", "Compliance officer"),
("End users", 1, 5, "Unaware", "Supportive", "User panel coordinator"),
]
for name, power, interest, current, desired, owner in stakeholders:
q = quadrant(power, interest)
gap = LEVELS.index(desired) - LEVELS.index(current)
status = f"close a gap of {gap} level(s)" if gap > 0 else "hold steady"
print(f"{name}: {q} -> {APPROACH[q]}; {status}; owner: {owner}")Running it prints one line per stakeholder. Sam Ortiz, for example, appears as "Keep informed" with a gap of two levels. That combination is a signal. The grid says to inform him, but a resistant, high-interest person usually needs more than a newsletter. Here the gap should override the default, and you would plan a conversation to find out why he resists.
Edge cases
Several situations call for judgment rather than a fixed rule.
- Borderline ratings. A stakeholder rated 3 for power sits exactly on the threshold used in the script. Small rating changes then move them across a quadrant boundary. When a rating is borderline, choose the more engaged approach and review it at the next checkpoint.
- Stakeholders who move. Interest often rises sharply near launch. The register should show when to revisit the approach. The chapter on keeping the register current covers this in detail.
- Groups with mixed attitudes. "End users" is not one stakeholder in practice. Split the group when attitudes or needs differ, for example by department or by shift pattern, and give each part its own approach.
- Hidden influencers. Someone with a low formal rating, such as an executive assistant who controls a calendar, may have real practical power. If your actions keep stalling at a certain person, revisit their power rating.
- Capacity limits. A team can only hold so many close relationships. If more than a handful of stakeholders land in "Manage closely", rank them by project impact and move some to a lighter approach, or share the load across several owners.
- Engagement that backfires. Over-communicating with a "Keep satisfied" executive can reduce goodwill. Ask them how much contact they want and record the answer.
A worked example
Consider a project that replaces a customer support tool.
- Dana Lee, the sponsor, is in "Manage closely". Her current level is Supportive, and the project needs her to be Leading, because the budget needs defending in a review. Tactic: a fortnightly one-to-one and a request to present at the steering group. Owner: project manager.
- Sam Ortiz, the support lead, is rated power 2 and interest 5. That is "Keep informed", but he is Resistant because he fears the launch will outpace training. Tactic: a one-to-one to understand the concern, then a joint decision on training dates. Owner: change lead.
- Acme Regulators are in "Keep satisfied". They are Neutral and need to stay Neutral. Tactic: a briefing before each milestone that affects the audit trail. Owner: compliance officer.
- End users are in "Keep informed" but Unaware. Tactic: a short announcement, then a user panel for testing. Owner: user panel coordinator.
Notice that only two of the four people actually follow the default approach for their quadrant without change. The other two need an adjustment because of their current attitude or their need for a more active role. That is a typical result and a good reason to track the gap.
Checking whether the approach works
An approach is a hypothesis. Test it.
- Reassess the current level at each phase end or major milestone.
- Look for evidence, not impressions: attendance, response time, decisions made on time, and the tone of feedback.
- If a tactic has run for two cycles and the gap has not shrunk, change the tactic or the owner.
- Record what you changed and why, so the next person understands the history.
Summary of key points
- The grid gives a default approach. The gap between current and desired engagement tells you whether to override it.
- Every stakeholder or group needs a channel and a named owner.
- Large groups are best reached through representatives, chosen openly.
- Resistance usually points to an unmet concern, so find the cause first.
- Review the approach at each phase and change it when it does not close the gap.
Exercise
A regulator is rated power 5, interest 2, so the grid places it in "Keep satisfied". Its current level is Neutral and the project needs it to be Neutral. A second stakeholder, a team lead rated power 2 and interest 4, is Resistant and the project needs them Supportive. State the approach for each and say which one the default quadrant action would fail to serve.
Show answer
The regulator gets the default approach: consult on key points, such as a briefing before milestones, with no gap to close. The team lead is in "Keep informed", but a newsletter would not serve them. Their gap is two levels (Resistant to Supportive), so you need a one-to-one conversation to learn the cause of the resistance and then act on any valid concern. The default quadrant action fails for the team lead.
Exercise
Using the Python script in this chapter, what would the output line for a stakeholder ("Priya", power 4, interest 5, current "Neutral", desired "Supportive", owner "Product manager") look like?
Show answer
Priya: Manage closely -> Collaborate and consult; close a gap of 1 level(s); owner: Product manager