Sub topic 6
Monitoring with Control Charts
The working model
This chapter assumes you understand DMAIC, process variation, common causes, special causes, and basic run charts. A control chart is a time-ordered graph with a center line and statistically calculated limits. It helps distinguish normal process variation from evidence that something has changed.
The Control phase uses charts to answer a practical question: “Is the improved process still behaving as expected?” A chart does not prove that every result meets the customer specification. Control limits describe the process's natural behavior. Specification limits describe what the customer or business requires.
For example, invoices may need approval within three days. A process can remain statistically stable while consistently taking four days. That process is predictable but unacceptable. It needs improvement, not merely monitoring.
Choosing a chart
Choose the chart according to the type and collection pattern of the data.
| Data situation | Typical chart | Example |
|---|---|---|
| One continuous value at each time point | Individuals and moving range (I-MR) | Approval time for each invoice |
| Several continuous values in each subgroup | X-bar and R or S chart | Cycle time for five invoices each hour |
| Count of defective units | P or NP chart | Defective forms per batch |
| Count of defects | C or U chart | Errors per invoice |
An individuals chart, or I chart, is useful when measurements arrive one at a time or when subgrouping would hide meaningful variation. Its moving range (MR) is the absolute difference between neighboring measurements. The moving range estimates short-term variation.
Calculating individuals-chart limits
For a basic I chart:
- Center line: the average of the observations.
- Average moving range: the average of neighboring absolute differences.
- Upper control limit: average plus 2.66 times the average moving range.
- Lower control limit: average minus 2.66 times the average moving range.
The constant 2.66 converts the moving-range estimate into an estimate of three standard deviations. A lower limit below zero may be replaced with zero when the characteristic cannot be negative.
def individuals_limits(values):
"""Return lower, center, and upper limits for an I chart."""
if len(values) < 2:
raise ValueError("At least two observations are required")
moving_ranges = [abs(b - a) for a, b in zip(values, values[1:])]
center = sum(values) / len(values)
average_moving_range = sum(moving_ranges) / len(moving_ranges)
spread = 2.66 * average_moving_range
return center - spread, center, center + spread
baseline = [2.8, 3.1, 2.9, 3.0, 3.2, 2.7, 3.0, 2.9]
lower, center, upper = individuals_limits(baseline)
new_value = 4.1
print(f"LCL={lower:.2f}, center={center:.2f}, UCL={upper:.2f}")
if new_value < lower or new_value > upper:
print("Out of control: follow the reaction plan")
else:
print("No point beyond the limits")The limits should come from a representative baseline collected while the process is stable. Do not repeatedly recalculate them after every unusual result. Doing so can hide the signal that the process changed.
Reading signals and avoiding errors
A point outside a control limit is strong evidence of a special cause, such as a system change, data-entry error, staffing change, or equipment problem. Other signals include a long run on one side of the center line, a sustained trend, or unusually alternating points. Use the organization’s chosen rules consistently.
Common errors include:
- Treating control limits as specification limits.
- Ignoring the order and timing of observations.
- Changing limits to make an outlier disappear.
- Using too few baseline observations to estimate variation.
- Investigating every ordinary fluctuation.
- Failing to record the cause and the response.
A chart is useful only when its signal triggers a defined reaction plan. The chart identifies evidence; the process owner decides and records the response.
Exercise
A new approval-time value is above the I-chart upper control limit but still below the three-day specification. What should happen first?
Show answer
Follow the reaction plan and investigate the special cause. The value may meet the specification while still showing that the process behavior has changed.