Sub topic 12
Auditing and Sustaining the Gains
Assume you understand DMAIC, common and special causes of variation, critical-to-quality (CTQ) characteristics, and basic control charts. This chapter focuses on what happens after handover: checking that the new process still works, confirming the benefits, and closing the project without losing control.
Why sustainment needs planned audits
A process can meet its target immediately after an improvement project and then regress. Staff may change, demand may increase, suppliers may vary, or someone may bypass a new standard. An audit checks whether the agreed process is still being followed and whether its results remain stable.
An audit is a planned comparison between actual practice and a defined requirement. The requirement may come from standard work, a control plan, a customer specification, or a safety rule.
Audits should examine both process behavior and results:
- Process compliance: Are people following the approved steps?
- Measurement discipline: Are data collected with the defined method and frequency?
- Performance: Are CTQs and project metrics still meeting their targets?
- Response effectiveness: Did staff act correctly when a signal or defect occurred?
- Ownership: Is the process owner reviewing and acting on the findings?
Avoid treating an audit as a search for blame. Its purpose is to find conditions that could allow the old problem to return.
Design a sustainment schedule
Use a higher audit frequency soon after handover, then reduce it when evidence shows that the process is stable. The process owner should approve the schedule and assign each audit to a named person.
| Period | Typical audit focus | Example frequency |
|---|---|---|
| First month | Standard work, data collection, reaction plan | Weekly |
| Months two to three | Process compliance and CTQ results | Biweekly |
| After stability is demonstrated | Results, risks, and unresolved findings | Monthly or quarterly |
The exact schedule depends on risk, customer impact, process maturity, and the cost of failure. A high-risk process may need frequent audits permanently.
Track benefits with evidence
Benefit validation compares the approved baseline with post-improvement performance. Use the same definitions, time windows, and units where possible. Otherwise, an apparent gain may result from changed measurement rules rather than a better process.
Track both outcome and balancing measures. An outcome measure might be invoice cycle time. A balancing measure might be payment errors. Improving speed while increasing errors is not a sustained benefit.
Record:
- The baseline period and baseline value
- The post-improvement period and current value
- The target and acceptance rule
- The data source and calculation method
- Any unusual conditions or exclusions
- The person who verified the result
A control chart can show whether the process remains stable. A benefit report can show whether the financial, service, quality, or capacity target remains achieved. These answer related but different questions.
Close the project responsibly
Project closure should occur only after the process owner accepts the controls, the required audit results are available, and benefits have been validated. Keep unresolved risks visible rather than hiding them in a closure report.
The closure record should identify:
- The verified benefits and their evidence
- Open actions, owners, and due dates
- The date of the next sustainment review
- Any remaining assumptions or risks
- The location of the control plan and standard work
- The project sponsor’s approval
Common sustainment failures
Gains often disappear because audits check paperwork instead of process behavior, metrics are reported without action thresholds, or corrective actions have no due date. Another common failure is stopping measurement immediately after the project team leaves. Keep monitoring long enough to observe normal workload changes, staff turnover, and seasonal effects.
Exercise
A process meets its target for four weeks after handover, but audits show that operators have stopped recording the required measurement. What should the process owner do?
Show answer
Restore the measurement method, determine why it was missed, contain any risk created by the missing data, retrain or revise the standard as needed, and verify the correction through a follow-up audit.