Sub topic 3
Deciding What Needs to Be Controlled
This chapter assumes you understand the DMAIC phases, process variation, common and special causes, critical-to-quality (CTQ) characteristics, and basic run or control charts. The Control phase does not require monitoring everything. It requires controlling the few characteristics that determine whether the improved process continues to meet its purpose.
Start with the customer and the process goal
A characteristic is a measurable feature of a product, service, or process. A CTQ characteristic is one that matters directly to the customer or to a critical requirement.
Begin with the improved process outcome. Ask:
- What result must remain stable?
- Which customer requirement could fail if the process drifts?
- Which metric showed the original problem?
- Which inputs or steps strongly affect that metric?
- What would create safety, legal, financial, or compliance risk?
For example, an invoice approval project may have reduced approval time. The output characteristic is approval cycle time. Other important characteristics may include approval accuracy, required authorization, and the percentage of invoices returned for missing information.
Trace important outputs to their causes
A useful selection method is to connect each important output to the process inputs and steps that influence it. Do not automatically control every input. Select inputs when evidence shows that they affect a CTQ, or when failure would create unacceptable risk.
Use the improvement analysis as evidence. Useful sources include cause-and-effect analysis, regression results, failure mode and effects analysis, capability results, and trial data. A characteristic that seems important but has no demonstrated connection to the outcome may need observation rather than formal control.
Prioritize by risk and influence
A practical screening table prevents weak choices and excessive monitoring.
| Candidate characteristic | Why it matters | Evidence or risk | Control decision |
|---|---|---|---|
| Approval cycle time | Customer and cash-flow requirement | Improved metric; can regress | Control |
| Approver authorization level | Compliance requirement | High consequence if missed | Control |
| Screen color preference | No CTQ connection | Low risk and no effect shown | Do not control |
| Percentage of incomplete submissions | Drives rework and delay | Strong relationship to cycle time | Control or monitor |
Control a characteristic when it has high customer impact, high failure consequence, strong influence on the CTQ, or a history of instability. A lower-risk characteristic may need a periodic check instead of continuous statistical monitoring.
Avoid overcontrol
Overcontrol creates work without protecting the result. Too many measures can hide important signals, encourage people to chase normal variation, and make ownership unclear. Each controlled characteristic should have a defined purpose, a reliable measurement method, a target or specification, a review frequency, and a reaction when the result signals trouble.
A specification describes what the customer or business requires, such as approval within three days. A control limit describes the normal behavior of a stable process. These are different. A process can be stable but consistently miss the specification, or it can meet the specification while showing an unusual shift that needs investigation.
Document the selection decision
Record why each characteristic is controlled, monitored periodically, or excluded. Include the owner and the point in the process where the measurement is available. This record helps the process owner maintain the controls after project closure and prevents future teams from removing a measure without understanding its purpose.
Exercise
An improved process has five candidate metrics. One metric directly affects customer satisfaction, one is legally required, two are stable internal activity counts, and one is easy to collect but has no known effect on the outcome. Which should receive formal control first?
Show answer
Control the customer-facing metric and the legally required metric first. Consider the activity counts only if evidence shows they influence a CTQ. Do not formalize the easy-to-collect metric without a meaningful connection to the process outcome.