Sub topic 15
Worked Example: Classifying a Breach and Choosing a Response
This chapter assumes you understand offer, acceptance, consideration, party, obligation, and performance. It also assumes the general rule that a minor breach usually leads to damages, while a material breach may excuse the other party from further performance.
The fact pattern
A homeowner hires a contractor to remodel a kitchen for $40,000. The written contract requires the contractor to:
- Finish by June 30.
- Install the specified white quartz countertop.
- Use a named brand of appliances.
- Complete the work in a reasonably workmanlike manner.
- Correct defective work after receiving notice.
The contract does not say that the completion date is “of the essence.” It also does not state that using the named appliance brand is an express condition of the homeowner’s payment.
The contractor finishes on June 30. The work is generally sound, but the contractor installs a similar quartz countertop in a slightly different shade. One cabinet door is misaligned. The contractor offers to replace the countertop and repair the door within two weeks at no extra charge.
The homeowner refuses to pay anything and hires another contractor to redo the entire kitchen.
Step 1: Identify the breached duties
The contractor breached two promises:
- The contractor did not install the specified countertop.
- The contractor left one cabinet door misaligned.
A promise is a commitment that creates a contractual duty. A condition is an event that must occur before a party’s performance is due. The contract contains promises here, but no clear language making the countertop specification a condition of the homeowner’s duty to pay.
The contractor’s failure to finish by June 30 would also matter if the work were late. Here, the contractor completed the work on time.
Step 2: Apply the materiality factors
Courts commonly consider the factors in Restatement (Second) of Contracts section 241. They ask whether the breach is serious enough to deprive the injured party of the expected benefit of the agreement.
| Factor | Application to the example |
|---|---|
| Lost expected benefit | The homeowner received a functioning, substantially completed kitchen, but not the exact countertop promised. |
| Adequate compensation | Money or replacement of the countertop may fairly compensate the homeowner. |
| Forfeiture from termination | Replacing an entire kitchen would discard most of the contractor’s completed work. |
| Likelihood of cure | The contractor promptly offered to replace the countertop and repair the door. |
| Good faith | The contractor completed the project on time and offered a reasonable cure. |
The breach is probably minor rather than material. The countertop difference may matter, especially if the precise color was important, but the facts do not show that the entire purpose of the contract failed. The misaligned door is a small defect. The offer to cure further weakens the argument that the breach is material.
Choosing a response
Because the breach is likely minor, the homeowner generally should not terminate the contract or refuse all payment. The homeowner can:
- Give notice of the defects.
- Allow a reasonable opportunity to cure.
- Seek damages for the cost of correction or the reduced value of the work.
- Withhold an amount reasonably related to the breach, subject to the contract and applicable law.
The homeowner’s decision to hire another contractor to redo the entire kitchen creates a wrongful-termination risk. If a court finds that the first contractor substantially performed and did not materially breach, the homeowner may owe the contract price, reduced by proven damages, rather than receive a complete refund.
Worked conclusion
The better response is to document the defects, accept the offered cure if reasonable, and pursue limited damages if the cure is inadequate. Termination would be safer only if the contract made the exact countertop an express condition, declared the deadline essential, or the defect substantially destroyed the value of the project.
Exercise
If the contractor had refused to replace the countertop and the countertop’s exact color was central to the homeowner’s design, would termination become more defensible?
Show answer
Yes. The refusal to cure and the importance of the exact specification could show that the homeowner lost a substantial part of the expected benefit. The result would still depend on the contract language and the surrounding facts.