Sub topic 2
What Counts as a Breach
A breach of contract is a failure, without a legal excuse, to perform a contractual duty when performance is due. The failure may involve doing nothing, doing the wrong thing, performing late, or performing in a way that does not meet the contract’s requirements.
This chapter assumes you understand the basic elements of a contract, including offer, acceptance, and consideration. It also assumes you know that a party is a person or organization bound by the contract, and that performance means carrying out a contractual obligation.
A Duty Must Exist and Be Due
Before deciding whether a breach occurred, ask three questions:
- Did the contract create a duty?
- Was the duty’s performance due?
- Did the party perform as the contract required?
A party usually does not breach a duty before the time for performance arrives. However, a clear statement before the due date that the party will not perform may be an anticipatory repudiation. That issue has special rules discussed later in the tutorial.
Performance must match the contract’s terms. A seller who delivers 100 chairs instead of 100 tables has not performed the agreed duty. A contractor who finishes one month late may also have breached, even if the work is otherwise acceptable.
Promises and Conditions
A promise is a commitment to act or refrain from acting. Breaking a promise is generally a breach. The injured party may seek a remedy, such as damages.
A condition is an event that must occur before a contractual duty becomes due or before a party must continue performing. A condition is not itself a promise. If a contract says payment is due only after an inspector approves the work, approval is a condition to payment.
The distinction matters because the failure of a condition may mean that the other party’s duty never became due. For example, if approval is required before payment and approval never occurs, the customer may not yet owe payment. The contractor may not automatically have a breach claim against the customer.
| Contract language | Legal function | Typical result if it does not occur |
|---|---|---|
| “The seller promises to deliver by June 1” | Promise | Late delivery may be a breach |
| “Payment is due if the lender approves the loan” | Condition | Payment duty may never become due |
| “Time is of the essence” | Express timing term | A late performance may have greater consequences |
A party cannot always rely on a failed condition if that party wrongfully prevented the condition from occurring. For example, a buyer cannot deliberately block an inspection and then argue that the inspection condition failed.
Breach Does Not Always End the Contract
Finding a breach answers only the first question. The next question is how serious the breach is.
A minor breach is a failure that does not substantially defeat the contract’s purpose. The contract usually remains in effect. The non-breaching party generally must continue its own performance, while seeking damages for the loss caused by the breach.
A material breach is a serious failure that substantially deprives the other party of the benefit it reasonably expected. Depending on the contract and applicable law, the non-breaching party may be excused from further performance and may seek damages or termination.
Courts do not decide materiality from labels alone. They examine the contract, the parties’ conduct, the importance of the missed duty, and the actual effect of the failure.
A Quick Classification Method
Use this sequence when analyzing facts:
- Identify the exact contractual duty.
- Find the required time, place, quality, and manner of performance.
- Compare the actual performance with those requirements.
- Decide whether performance was excused or prevented.
- Classify the failure as minor or material only after considering its effect on the bargain.
Exercise
A contractor promises to paint an office by July 1 but finishes on July 3. The customer can still use the office, and the delay causes two days of extra rent. Is there a breach, and is it necessarily material?
Show answer
Yes. The late completion is a breach because performance did not meet the agreed deadline. On these facts, it is likely minor rather than material because the customer received the main benefit and can seek damages for the extra rent.