Promises, Conditions, and Why Order of Performance Matters
This chapter assumes you know the basics of offer, acceptance, consideration, party, obligation, and performance. The key distinction is between a promise and a condition. That distinction determines whether failing to perform creates a breach or instead prevents the other party's duty from becoming due.
Promises and conditions
A promise is a commitment that a party will do something. If the party does not keep the promise, the party has breached the contract. The other party may usually claim damages, even if the breach does not end the contract.
A condition is an event that must occur, or must not occur, before a contractual duty becomes due or remains enforceable. A condition is not itself a promise. If the condition does not occur, the related duty may never become due. The party whose duty depended on the condition may be excused from performing.
| Term | What it does | Typical consequence of failure |
|---|---|---|
| Promise | Creates a duty to act or refrain from acting | Breach and possible damages |
| Condition | Controls whether a duty is due or continues | Duty may be excused |
| Condition and promise | Does both, if the contract clearly says so | Breach and possible excuse of dependent duty |
For example, a contract may say, “The buyer will pay $10,000 after the architect approves the plans.” The buyer's payment duty may depend on approval. If approval never occurs, payment may not yet be due. The sentence may also contain a promise by the buyer to pay once approval occurs.
Courts interpret uncertain language carefully. They generally prefer treating language as a promise rather than a condition when making a condition would cause a harsh forfeiture. Clear words such as “unless,” “provided that,” “on condition that,” or “only if” can show that the parties intended a condition. The whole contract and the parties' purpose still control.
Order of performance
Contract duties may be:
- Precedent duties, which must be performed first.
- Simultaneous duties, which must be performed at the same time.
- Subsequent duties, which become discharged if a later event occurs.
The contract's wording usually sets the order. If the wording does not, courts often infer an order from the nature of the exchange. A party generally must perform an earlier duty before demanding the other party's dependent performance.
For example, a contractor may have to substantially complete a building before the owner's final payment is due. The owner cannot refuse every payment merely because the contractor has not completed work that was scheduled for a later phase.
Conditions are not automatic escape routes
A party cannot always rely on a failed condition. A party may be unable to invoke a condition if that party wrongfully prevented the condition from occurring. For example, an employer cannot block an inspection and then claim that the inspection condition failed.
Courts may also excuse a condition when insisting on it would cause disproportionate forfeiture and the condition was not central to the exchange. This is different from rewriting a clear bargain. The more important the condition is to the parties' agreed risk, the less likely a court is to excuse it.
Exercise
A contract says a buyer must pay when the seller delivers a valid title document. The seller delivers the goods but never provides the document. Has the buyer breached by withholding payment?
Show answer
Usually no. Delivery of the title document may be a condition to the buyer's payment duty. The buyer's duty may not yet be due, although the seller may have breached a separate promise to provide the document if the contract makes that obligation explicit.