Minor Breach: The Contract Survives
Assume you understand how a contract is formed and know the terms party, obligation, and performance. This chapter focuses on common-law contracts, such as service and construction agreements. Sales of goods under the UCC use different rules.
What a minor breach means
A minor breach is a failure to perform exactly as promised that does not substantially defeat the purpose of the contract. It is also called a partial breach or nonmaterial breach.
The breaching party remains responsible for the defective or late performance. However, the breach is not serious enough to excuse the other party from its remaining duties. The contract continues.
For example, a contractor agrees to install ten interior doors by June 1. The contractor installs all ten doors, but one door has a minor scratch that does not affect its use. The owner may claim the reasonable cost of fixing the scratch. The owner usually may not cancel the entire construction contract because of that defect.
The main consequence: continued performance
When a breach is minor, the non-breaching party generally must continue performing its own remaining contractual duties. It may not treat the contract as ended merely because performance was imperfect.
The non-breaching party can still:
- Demand performance of the missing or defective part.
- Claim damages caused by the breach.
- Ask for a reasonable cure when cure is possible.
- Preserve its rights by objecting clearly and promptly.
Whether a breach is minor depends on the whole agreement and the facts. A small defect in an important component may be more serious than a larger defect in an unimportant component.
Damages without termination
The usual remedy for a minor breach is damages, which are money awarded to place the injured party as close as possible to the position it would have occupied if the contract had been performed.
Common measures include:
- The reasonable cost to repair or complete the work.
- The difference in value between the promised performance and the performance received.
- Reasonably foreseeable consequential losses, if the injured party proves them.
- Incidental expenses caused by the breach.
The injured party must usually take reasonable steps to mitigate, or reduce, its losses. It cannot allow avoidable damage to grow and then charge all of it to the breaching party.
| Situation | Usual result |
|---|---|
| Minor defect, contract purpose achieved | Continue the contract and seek damages |
| Serious failure, contract purpose defeated | Possible excuse from remaining duties and termination |
| Defect that can reasonably be fixed | Give appropriate opportunity to cure |
Cure and reservation of rights
A breaching party may be able to cure, meaning fix, the defective performance. A court may consider the cost, timing, inconvenience, and contract language when deciding whether a proposed cure is reasonable.
The non-breaching party should state its position carefully. For example: “We will continue under the agreement, but we reserve our right to seek damages for the late delivery.” This helps show that continued performance is not an unconditional waiver of the claim.
The non-breaching party should not call the contract terminated unless the breach is material or the contract clearly grants that right. Wrongful termination can itself be a breach. The party that wrongly ends the agreement may become liable for the other party’s resulting losses.
Exercise
A designer delivers a website two days late. The website has all agreed features, and the client can use it for its intended launch. May the client automatically terminate the contract?
Show answer
No. The delay may be a minor breach unless the contract makes the deadline an express condition or the facts show that timing was essential. The client may claim proven damages and should usually continue performing its own duties.