Sub topic 8
Cure: When a Breach Can Be Fixed
This chapter assumes you understand contract formation, contractual duties, and the difference between a minor breach and a material breach. A cure is a correction of defective performance, such as repairing faulty work or delivering missing items. Cure matters because it can reduce the harm from a breach and may prevent the other party from terminating the contract.
What cure means
A party cures by correcting its failure within the time allowed by the contract or applicable law. The correction must usually provide the performance promised, not merely an excuse or a partial improvement.
For example, a builder who installs the wrong kitchen cabinets may cure by replacing them with the specified cabinets. A seller who ships ten items instead of twelve may cure by sending the missing two.
Cure does not erase every consequence of the original breach. The non-breaching party may still recover reasonable losses caused by the delay, inspection, removal, storage, or other effects of the defective performance.
Cure under common law
For service, construction, employment, and other non-goods contracts, common law usually asks whether the breach is material. A material breach substantially deprives the other party of the expected benefit. The non-breaching party may suspend its own performance and may have grounds to terminate.
If the breach is minor, the contract generally continues. The breaching party must perform the remaining duties, and the other party normally seeks damages rather than termination.
A later cure can affect the materiality analysis. Courts may consider:
- How much of the promised performance was delivered.
- How serious the defect was.
- How quickly and reliably it could be corrected.
- Whether correction would impose a significant burden on the injured party.
- Whether the breaching party acted in good faith.
- Whether the contract sets a deadline or makes time essential.
A cure may turn an apparently serious problem into a minor breach when it restores the expected result without substantial delay or expense. It may not help when the deadline was central, the defect cannot be repaired, or the breach shows that the promised performance will not be delivered.
| Situation | Likely effect of cure |
|---|---|
| Small defect fixed promptly | Supports treating the breach as minor |
| Major defect fixed after a critical deadline | May remain a material breach |
| Defect cannot be repaired | Cure is unavailable |
| Contract expressly allows a correction period | The agreed process controls, subject to applicable law |
Contractual cure rights
A contract can create a notice-and-cure procedure. It may require the injured party to describe the default in writing and give a stated number of days to correct it before termination. These provisions make the parties’ expectations clearer and reduce disputes about whether termination was premature.
A termination clause may also define defaults that permit immediate termination. Read that clause with any cure provision. A contract might allow immediate termination for insolvency or intentional misconduct but require a cure period for late payment.
The party receiving notice should respond carefully. It should identify the alleged breach, state the proposed correction, meet the deadline, and reserve its rights if the notice is disputed. The other party should avoid treating an incomplete promise to cure as completed performance.
Cure under the UCC
For a sale of goods, the Uniform Commercial Code generally gives a seller a right to cure a nonconforming tender in some circumstances. Before the contract deadline, the seller may make a conforming delivery. If the seller reasonably believed the buyer would accept the defective delivery, the seller may receive additional time to cure.
The UCC’s perfect tender rule can give a buyer broader rejection rights than common law, but installment contracts use a different standard. A buyer usually may reject an installment only when the nonconformity substantially impairs that installment or the entire contract, depending on the circumstances.
Exercise
A contractor installs the wrong but equally durable tiles. The contract requires written notice and gives the contractor 14 days to replace them. The owner terminates two days after giving notice. What is the main problem with the termination?
Show answer
The owner likely terminated prematurely. The contract appears to require an opportunity to cure, and the facts suggest the defect may be curable rather than material after proper correction.