Sub topic 8
The parts of a status update
This chapter assumes you can write a clear workplace email, you know how to put the bottom line first, and you have a project or work stream to report on. It covers the standard parts of a status update and what belongs in each. Rating, risks, and asks get their own chapters, so they appear here only briefly.
Why use a fixed set of parts
A status update answers the same questions every time: where are we, what did we finish, what is next, and what could go wrong. A fixed order means readers know where to look. A manager who only cares about blockers can jump straight there.
The parts, one by one
| Part | Question it answers | What to include |
|---|---|---|
| Summary | What should I know in ten seconds? | Overall state and the one main point |
| Done | What changed since last time? | Finished outcomes with numbers or dates |
| Next | What happens before the next update? | Planned outcomes and when |
| Risks and blockers | What could stop us? | Issue, impact, and the date it matters |
| Ask | What do you need from me? | Who, what, and by when, or "None" |
Summary
The summary is the bottom line for the whole update. Write it last, even though it appears first. One or two sentences is enough.
Done
List outcomes, not activity. "Worked on the address form" tells the reader nothing. "Shipped the new address form to staging" tells them what exists now. Add a count or date wherever you can.
Next
List what you plan to finish, not what you plan to "look into." Each item should be something the reader can check at the next update.
Risks and blockers
A blocker is something that already stops work. A risk is something that might. Name the issue, its impact, and the date it starts to matter. Chapters later in this tutorial cover how to phrase these.
A complete example
Subject: Checkout redesign: weekly status, Nov 27 (At risk)
Summary: On track for the Dec 15 launch except for payment testing, which is two days behind.
Done this week:
- Shipped the new address form to staging
- Fixed 14 of 18 open accessibility bugs
Next week:
- Finish payment provider testing
- Start load testing
Risks and blockers:
- Payment sandbox has been down since Tuesday. Launch slips about 2 days if it is not restored by Dec 2.
Ask: Can someone from Platform contact the payment provider by Monday?Notice how the parts connect. The summary names payment testing, the risk explains why it is late, and the ask is the fix for that risk. If the ask had nothing to do with the risk, a reader would reasonably wonder what was missing.
Common errors
- Activity instead of outcomes. "Met with vendors" says what you did. "Chose Vendor B" says what changed.
- Vague progress. "Making good progress" cannot be checked. "40 of 52 services migrated" can.
- Next items with no timing. "Start load testing" is better with "by Wednesday."
- Burying the risk. A blocker in the fourth bullet of Done will be missed. Keep it in its own section.
- A summary that contradicts the rest. If the subject says "On track" and the risks section lists a blocked launch, the reader will trust neither.
- Leaving out empty sections. If there are no risks, write "None" so the reader knows you checked.
Template
Use the same skeleton each cycle and fill in the brackets.
Subject: [Project name]: weekly status, [date] ([On track | At risk | Off track])
Summary: [One or two sentences: overall state and the main thing the reader should know.]
Done:
- [Outcome with a number or date]
Next:
- [Planned outcome and when]
Risks and blockers:
- [Issue, impact, date it matters]
Ask: [Who, what, by when. Write "None" if there is no ask.]Exercise
A draft update says: "Done: Worked on the reporting dashboard. Next: Keep going on it. Risks: None really." Rewrite the Done and Next lines so they follow this chapter's guidance. Invent plausible numbers and dates.
Show answer
Possible answer. Done: "Built 5 of 8 dashboard charts; the sales and refund charts are live in staging." Next: "Build the remaining 3 charts and send the dashboard for review by Thursday." Risks: "None" is acceptable only if you checked. Done now lists outcomes with counts, and Next lists a checkable result with a date.