Sub topic 9
Rate status honestly and explain it
This chapter assumes you can already lead a message with its bottom line and list progress, next steps, and risks in a fixed layout. Here you will learn to choose a status rating and justify it in one sentence.
What a rating is for
A status rating is a single label at the top of an update that tells the reader how worried to be. The three common labels are:
| Rating | Meaning | Reader's likely response |
|---|---|---|
| On track | The plan will be met as written. | Keep reading only if interested. |
| At risk | The plan can still be met, but something threatens it and you are acting on it. | Read the risk and decide whether to help. |
| Off track | The plan will not be met without a change in scope, date, or resources. | Read now and decide. |
Readers often check the rating first and decide from it whether to read the rest. A wrong rating therefore misdirects their attention.
Choose the rating from evidence
Pick the rating by asking what you know about the commitment, not how the week felt. A useful test has three questions:
- Will the committed date, scope, and budget hold if nothing changes?
- Is there a known threat with a date by which it matters?
- Do you have a plan that removes the threat before that date?
If the answer to the first question is yes, use On track. If it is no, but the answers to the second and third show a recoverable threat, use At risk. If the date, scope, or budget will not hold even with your current plan, use Off track.
flowchart TD
A[Will date, scope, and budget hold?] -->|Yes, no known threat| B[On track]
A -->|Yes, but a threat exists| C{Can you remove it before it matters?}
A -->|No| D[Off track]
C -->|Yes, plan in place| E[At risk]
C -->|No| DThe block above is only a sketch of the logic, so it is not a rendered diagram. The diagram below shows the same decision in the required format.
Explain it in one sentence
Put the rating and a one-sentence reason together at the top. The sentence must name the cause and its effect on the date.
Subject: Checkout redesign: weekly status, Nov 27 (At risk)
Summary: On track for the Dec 15 launch except for payment testing, which is two days behind.A weak reason gives the reader nothing to check:
Subject: Checkout redesign: weekly status, Nov 27 (At risk)
Summary: Some challenges this week, but the team is working hard.A strong reason names the cause, the size of the delay, and the date it matters:
Summary: The payment sandbox has been down since Tuesday. Launch slips about 2 days if it is not restored by Dec 2.Common mistakes
- Staying green too long. Teams often report On track until the problem is undeniable. Move to At risk as soon as you know about a threat, because early warning gives the reader time to help.
- Using At risk as a hedge. If the date will be missed, say Off track. Calling a certain miss At risk delays the decision.
- Changing the rating without saying why. When the rating moves from last week, state the change: "Moved from On track to At risk because..."
- Rating effort instead of outcome. A busy week on a project that will miss its date is still At risk or Off track.
Worked example
Last week the migration was On track. This week, a vendor delays a database license by four days, and the cutover date is fixed.
Weak: "Status: On track. A few small delays."
Better: "Status: At risk (was On track). The database license arrives four days late. Cutover on Dec 10 still holds if the license arrives by Dec 3. I have asked the vendor for a firm date."
The better version states the change, the cause, the date it matters, and the action taken.
Exercise
A project's launch date is fixed for Dec 15. This week you learned that a required approval will take until Dec 20, and no one can speed it up. Which rating do you use, and what one-sentence reason do you write?
Show answer
Off track, because the date cannot hold with the current plan. For example: "Off track (was At risk). The legal approval will not arrive until Dec 20, five days after the Dec 15 launch, and it cannot be accelerated. I need a decision on moving the launch or launching without the affected feature."
Exercise
Rewrite this reason so the reader can check it: "Status: At risk. We hit some issues with testing."
Show answer
A good rewrite names the cause, the size, and the date, for example: "Status: At risk. 9 of 40 test cases fail on the payment flow. Launch slips about 3 days if they are not fixed by Dec 1."