Sub topic 5
Replace vague claims with specifics
This chapter assumes you can write workplace English, use email or team chat, and know what a project or work stream is. You should also know that a memo puts the bottom line first, which earlier chapters covered.
A vague claim forces the reader to ask a follow-up question. A specific claim lets them judge the situation alone. In a short update, that difference decides whether the message ends the conversation or starts another one.
Why vague claims fail
Phrases like "going well," "good progress," and "a few issues" describe how the writer feels. They don't describe the work. Two readers can take the same phrase to mean very different things. One hears "almost done" and the other hears "halfway."
A specific claim gives the reader something to check. Compare these two versions.
Vague: Things are going well and we're making good progress on the migration.
Specific: We have migrated 40 of 52 services. The remaining 12 are scheduled for Dec 4.The specific version answers the questions the reader would otherwise send: how many are done, how many remain, and when the rest will finish. The reader can also compare it with the next update and see whether the plan is holding.
The four kinds of specifics
Most vague claims can be fixed with one of four details.
| Detail | Replaces | Example |
|---|---|---|
| A count | "a lot," "several," "most" | 14 of 18 bugs fixed |
| A date | "soon," "shortly," "later" | Dec 4 |
| A measure | "slow," "unstable," "expensive" | Export fails for about 3% of invoices |
| A name | "the team," "someone," "the vendor" | Platform team, Vendor B |
Choose the detail the reader will use. A manager deciding whether to add people needs dates and counts. A finance partner approving spend needs amounts.
A rewrite in three steps
Take this draft line: "We've had some delays with testing and it should be done soon."
- Find the vague words. Here they are "some delays" and "soon."
- Ask the question a reader would ask. How long is the delay? Why? When exactly will testing finish?
- Put the answers in the sentence.
The result: "Payment testing is two days behind because the sandbox has been down since Tuesday. We expect to finish Dec 9 if it is restored by Dec 2."
The new sentence is longer, but the reader needs no follow-up. Specifics also carry their own cause and impact, so you often don't need extra explanation.
Common errors
- Numbers without a base. "Fixed 14 bugs" is weaker than "fixed 14 of 18 open bugs." The second shows how much remains.
- Precision you don't have. Don't invent a figure to sound exact. Write "about 3%" if the number is an estimate, and say so.
- Dates without a condition. "Done Dec 9" hides the risk. Write "Dec 9, if the sandbox is restored by Dec 2."
- Numbers the reader can't read. Report outcomes, not activity. "Held 6 meetings with the vendor" says less than "agreed the contract terms with the vendor."
- Too many specifics. Include the figures that support the point and leave out the rest. Five numbers that matter beat fifteen that don't.
Specifics in the status update
The weekly status example from this tutorial uses specifics in every section. "Fixed 14 of 18 open accessibility bugs" is a count with a base. "Launch slips about 2 days if it is not restored by Dec 2" is an impact tied to a date. "Can someone from Platform contact the payment provider by Monday?" names who, what, and by when.
Exercise
Rewrite this line with specifics, using these facts: 9 of 12 interviews are complete, the last 3 are on Dec 3, and the report is due Dec 10. Line: "The research is progressing nicely and we should wrap up soon."
Show answer
"We have completed 9 of 12 interviews. The last 3 are on Dec 3, and the report is due Dec 10." The answer replaces "progressing nicely" with a count and a base, and replaces "soon" with two dates.
Exercise
A writer says "Fixed 20 bugs and the export is mostly reliable now." Name two problems with this line and say what to add.
Show answer
"20 bugs" has no base, so add how many are open in total (for example, "20 of 35"). "Mostly reliable" is a vague measure, so add a rate, such as "the export now fails for about 1% of invoices, down from 3%."