Sub topic 10
Surface Risks and Blockers Early
This chapter assumes you can write a basic status update with done and next sections, and that you know how to put the bottom line first. Here you will learn how to report problems while there is still time to fix them.
Risks and blockers are different things
A blocker is a problem that is stopping work now. A risk is a problem that might happen and would hurt the plan if it did. The reader responds differently to each, so label them correctly.
| Type | State | Reader's likely response |
|---|---|---|
| Blocker | Already happening | Remove it, or accept the delay |
| Risk | Might happen | Decide whether to prepare, watch, or ignore |
A blocker you describe as a risk gets too little urgency. A risk you describe as a blocker causes needless alarm.
Why early matters
A problem is cheapest to fix when it is first noticed. Every day you wait, options disappear. A reader told on Monday that a vendor is late can reassign people. A reader told on launch day can only apologize.
Report a risk when you first have a reason to believe it, even if you are not sure. Say how sure you are. "I think this is likely" is more useful than silence followed by a surprise.
The four parts of a good risk entry
Each entry should answer four questions in one or two sentences:
- What is the issue? Name it plainly.
- What is the impact? Say what slips, costs more, or breaks.
- When does it matter? Give the date by which it must be fixed.
- What is the plan or ask? Say what you are doing, or what you need from the reader.
Compare these two versions:
Weak: We are having some issues with the payment sandbox, which may affect timelines.
Strong: The payment sandbox has been down since Tuesday. Launch slips about 2 days if it is not restored by Dec 2. I have opened a ticket with the provider and need Platform to escalate (see Ask).The weak version has no date, no size of impact, and no next step. The reader must write back with questions. The strong version lets them act immediately.
Where it goes in the update
Put risks and blockers after the progress sections and before the ask. If a risk changes the overall rating, also mention it in the summary at the top, because some readers stop after the first lines.
Subject: Checkout redesign: weekly status, Nov 27 (At risk)
Summary: On track for the Dec 15 launch except for payment testing, which is two days behind.
Risks and blockers:
- Blocker: Payment sandbox has been down since Tuesday. Launch slips about 2 days if it is not restored by Dec 2.
- Risk: Load testing needs the staging cluster, which another team may reserve the week of Dec 8. If that happens, testing moves past Dec 10.
Ask: Can someone from Platform contact the payment provider by Monday?Starting each entry with "Blocker:" or "Risk:" lets the reader scan for the more urgent items.
Common mistakes
- Burying the problem. A blocker in the fifth bullet of "Done this week" will be missed.
- Listing everything. Ten minor risks hide the two that matter. Keep the ones that could change a date, a cost, or a decision.
- Describing without sizing. "There may be delays" gives no number. Write "about 2 days" or "up to 3 weeks".
- Reporting a problem without a path. Even "I do not yet have a fix; I will update you Wednesday" gives the reader something to rely on.
- Writing "None" when you are unsure. If you have no risks to report, check first. If you are guarding against bad news, the habit will cost you trust.
A quick test
Before you send, read only the risks section and ask whether a reader who knows nothing else about the project could tell what is wrong, how bad it is, by when, and what you want them to do.
Exercise
Rewrite this entry so it is useful: "The data import might cause some problems later." Assume the import fails on files over 2 GB, 6 of 40 files are that large, and the final import is due Dec 9. You are testing a split-file workaround.
Show answer
Risk: The data import fails on files over 2 GB, and 6 of the 40 files are that large. If the workaround is not confirmed by Dec 9, the final import is delayed. I am testing a split-file workaround and will report the result by Dec 3.
Exercise
A vendor has not delivered a component and your team cannot continue testing. Is this a risk or a blocker, and what four things should the entry contain?
Show answer
It is a blocker, because work is already stopped. The entry should state the issue (component not delivered), the impact (testing cannot continue and the date it slips), the date by which it must be resolved, and your plan or ask (for example, who should contact the vendor).