Identify who needs to hear from you
Stakeholder identification is the step where you build the list of people and groups your communication plan has to serve. This chapter assumes you know basic project vocabulary (scope, milestones, deliverables), have worked on or with a project team, and have goals, constraints, and risks from the previous chapter in hand. You do not need to rank or analyze stakeholders yet. That comes in the next chapter.
What counts as a stakeholder
A stakeholder is any person or group that can affect the project, is affected by it, or believes they are. The third part matters. A department that thinks your project will change its work will react as if it will, whether or not that is true.
Stakeholders are not the same as team members. The team does the work. Stakeholders include the team, but also people who fund, approve, use, support, regulate, or simply live with the result.
The list drives everything else in the plan. A missing stakeholder gets no messages, no owner, and no escalation path. The usual consequence is a late surprise: a security reviewer who was never told about a deadline, or a support team that first hears about a release on launch day.
Work from the project, not from memory
Most people list the stakeholders they talk to every week. Those are the ones you already know. The risk lies with the ones you do not.
Use the project context as a source of prompts. Each goal, constraint, and risk implies people.
| Source from the project | Question to ask | People it may reveal |
|---|---|---|
| Goal | Who benefits if we succeed? Who pays for it? | Sponsor, customers, business owners |
| Deliverable | Who will use it, operate it, or support it? | End users, help desk, operations |
| Constraint: budget | Who approves and tracks spending? | Finance, procurement |
| Constraint: regulation | Who checks that we comply? | Legal, compliance, auditors |
| Constraint: dependency | Whose work must finish before ours can proceed? | Other project teams, vendors |
| Risk | Who can reduce it, and who suffers if it happens? | Specialists, affected departments |
| Change to current work | Whose daily routine changes? | Staff in affected teams |
Work through the table with the project charter or scope statement open. Write down every role the questions turn up, even if you are unsure the person matters. Removing a name later is cheap. Discovering one in the final week is not.
Internal and external stakeholders
Split the list into two groups, because they usually need different channels and different levels of formality.
- Internal stakeholders belong to your organization: the sponsor, the project team, functional managers, other departments, executives, and the people whose processes will change.
- External stakeholders do not: customers, vendors and contractors, regulators, partners, and sometimes the public or the press.
External communication often has extra constraints. Contracts may fix how and when you must notify a vendor. A regulator may require written notice. Messages to customers may need approval from marketing or legal before they go out. Note these constraints now, since the channel chapter will rely on them.
Techniques for finding hidden stakeholders
No single technique finds everyone. Combine two or three.
- Review project documents. The charter, scope statement, requirements, contracts, and risk register all name people and groups. Check the org chart for the departments they belong to.
- Ask the people you already know. Put one question to the sponsor, the team, and early customer contacts: "Who else should we talk to, or who will be upset if they are not told?" The second half of that question surfaces people who hold informal influence.
- Walk the lifecycle. Follow the product or change from request to approval, build, test, release, and support. Note who touches it at each step.
- Check past projects. Lessons-learned notes from similar projects often include entries such as "we forgot to involve the security team."
- Follow the money and the rules. List who approves spending and who enforces policy or law.
- Run a short workshop. Ask a small group to write names on notes for ten minutes, then group them. This works well when the project crosses several departments.
Repeat the list review whenever the scope changes. Stakeholders are discovered throughout a project, not once.
Record what you know
For each stakeholder, capture only what you can support now. A short register is enough at this stage:
- Name or group, and a contact person if it is a group
- Role in relation to the project
- Internal or external
- How they relate to the work (funds it, uses it, approves it, supports it, is affected by it)
- Anything already known about expectations or concerns
Leave the influence and interest columns empty until the next chapter. Filling them in too early is a common mistake, because first guesses tend to stick.
Here is the sort of entry that carries into the later analysis. This example uses the structure from the plan's stakeholder record, with only the identification fields filled in:
stakeholder: Executive sponsor
type: internal
role: funds the project and approves major changes
known_concerns:
- schedule and budget status
- top three risks
- decisions awaiting approval
interest: to be assessed
influence: to be assessed
owner: project managerThe later chapters add the strategy, channel, and frequency fields to this same entry.
Grouping to keep the plan usable
A project of any size can produce dozens of names. A plan that lists forty individual people will not be maintained. Group stakeholders who share the same information needs and treat them as one audience.
Examples of good groupings:
- "End users in the finance department" instead of twelve named analysts
- "Delivery team" instead of each developer and tester
- "Vendor account team" instead of every vendor contact
Keep an individual entry for anyone whose needs are unique or whose influence is high, such as the sponsor or a key approver. Within a group, name one representative who receives the message and passes it on.
Grouping has a limit. If one member of a group has a very different need or a veto, give that person a separate entry. Merging a skeptical senior manager into "Business users" hides the one person who most needs a tailored message.
Common errors
Listing only the people you meet. Teams that sit far from the project, such as operations, legal, or support, are the usual omissions. Use the table above to find them.
Confusing the requester with the user. The person who asked for a tool is often not the person who will use it every day. Both need to be on the list, with different needs.
Treating "the business" or "the customer" as one stakeholder. These are labels for many groups. Break them down until each entry has a recognizable set of needs.
Forgetting people who can block you. Reviewers, auditors, and gatekeepers rarely appear in project meetings. They can still stop a release. Identify them early.
Assuming silence means no stakes. A group that does not complain may simply not know what is coming.
Building the list once. Staff change roles, reorganizations happen, and scope grows. A list that was complete at kickoff will be wrong by the midpoint.
From identification to the plan
Identification connects to two later steps. The first is analysis, where you judge each stakeholder's influence and interest. The second is ownership, where you decide who on the project is responsible for the relationship with each audience. A complete register makes both easier. The chapter after this one covers analysis.
The flow for this chapter looks like this:
Worked example
A company is replacing its expense-reporting tool. The first list comes from the project kickoff:
- Finance director (sponsor)
- Project team
- Employees who submit expenses
The table of prompts produces more names. The tool will connect to payroll, so payroll staff are affected. The vendor hosts the system, so the vendor account manager is external and relevant. Company policy requires audit review of financial tools, so internal audit has an approval role. The help desk will answer user questions after launch. Travel managers approve expenses and will see a new approval screen.
The grouped register looks like this:
| Stakeholder | Type | Relationship to the project |
|---|---|---|
| Finance director | Internal | Sponsor, approves budget and changes |
| Project team | Internal | Builds and configures the tool |
| Employees who submit expenses | Internal | Daily users of the new tool |
| Travel managers | Internal | Approve expense claims in the new workflow |
| Payroll team | Internal | Receives reimbursement data |
| Internal audit | Internal | Reviews controls before release |
| Help desk | Internal | Supports users after launch |
| Vendor account team | External | Hosts and configures the system |
The list grew from three entries to eight. Internal audit and the help desk would likely have been missed without the lifecycle walk-through, and either could have delayed launch.
Exercise
A team is building a mobile app for a retail chain. The initial stakeholder list contains the product owner, the developers, and "customers." Name three questions or techniques you would use to find missing stakeholders, and give one example of a group each might reveal.
Show answer
Possible answers: (1) Walk the lifecycle, from request to build, test, release, and support. This reveals the app store release manager and the customer support team. (2) Check constraints and rules, such as payment handling and privacy law. This reveals compliance, legal, and the payment provider. (3) Ask the sponsor and product owner who will be upset if not told. This reveals store managers whose staff will help customers with the app. Also split "customers" into groups such as shoppers, loyalty members, and in-store staff who use the app, since each has different needs.
Exercise
A project plan lists 30 named employees from the sales department as separate stakeholders. What is wrong with this approach, and when would you still keep an individual entry for one of them?
Show answer
Thirty separate entries make the plan hard to maintain, and most of those people share the same information needs. Group them as one audience such as "Sales team" with a representative who passes the message on. Keep an individual entry for a person whose needs differ or who has high influence, for example the sales director who approves the rollout or a manager who has a veto.