Analyze stakeholders by influence and interest
This chapter assumes you can already list the stakeholders of a project, which the previous chapter covered. It also assumes you know basic project vocabulary such as scope, milestone, and deliverable. Here you turn a flat list of names into a ranked view that tells you how much communication effort each person or group needs, and what kind.
Why a list of stakeholders is not enough
A stakeholder list answers the question "who?" It does not tell you how much attention each person needs. If you give every stakeholder the same weekly report, two things go wrong. Busy decision makers stop reading, and people who are directly affected get too little detail.
Stakeholder analysis is the step where you judge each stakeholder on a few dimensions and choose a communication strategy from the result. The output feeds the next chapter, where you decide what each audience needs to know. It also feeds the escalation paths you will define later.
The most common dimensions are:
- Influence (or power): how much the person can change the project's direction, budget, schedule, or outcome.
- Interest: how much the project's results or progress matter to the person, and how much attention they are likely to pay.
- Expectation: what the person wants from the project and what they would count as success.
- Attitude: whether they currently support, ignore, or resist the project.
Influence and interest are the core pair. Expectations and attitude refine your choices.
The influence and interest grid
The grid places each stakeholder in one of four cells, using two questions. Is their influence high or low? Is their interest high or low? Each cell has a standard strategy.
| Influence | Interest | Strategy | What it means in practice |
|---|---|---|---|
| High | High | Manage closely | Frequent, two-way contact. Involve them in decisions. |
| High | Low | Keep satisfied | Short, infrequent updates. Do not overload them, but never surprise them. |
| Low | High | Keep informed | Regular updates and a way to ask questions or give feedback. |
| Low | Low | Monitor | Minimal effort. Check occasionally that their position has not changed. |
Scoring rather than guessing
"High" and "low" are judgments, and judgments drift. A simple way to make them consistent is to score each dimension from 1 to 5 and set a threshold, for example 4 or above counts as high. Score them with the team, not alone, because different people see different sides of a stakeholder.
Ask concrete questions:
- Can this person approve, block, or reprioritize work, budget, or release dates?
- Does this person control a resource we need, such as people, an environment, or a signature?
- Will their daily work change when the project delivers?
- Do they ask about the project without being prompted?
Yes to the first two raises influence. Yes to the last two raises interest.
Worked example
Suppose a project replaces the order-entry software of a mid-sized distribution company. The team has identified these stakeholders and scored them from 1 to 5.
| Stakeholder | Influence | Interest | Cell | Strategy |
|---|---|---|---|---|
| Executive sponsor | 5 | 4 | High / High | Manage closely |
| Finance director | 4 | 2 | High / Low | Keep satisfied |
| Warehouse supervisors | 2 | 5 | Low / High | Keep informed |
| Order-entry clerks | 2 | 5 | Low / High | Keep informed |
| IT security officer | 4 | 2 | High / Low | Keep satisfied |
| Facilities team | 1 | 1 | Low / Low | Monitor |
The finance director scores low on interest because the budget is already approved, but high on influence because they can freeze it. The result is "keep satisfied": a short budget note each month, and an immediate call if cost forecasts change. The order-entry clerks have little formal power, but they will use the system every day. They fall into "keep informed", and their feedback can reveal usability problems early.
Recording the result
Write each analysis result down in a consistent structure so that it can be reviewed and updated. The following entry captures the outcome for the sponsor and the communication choices that follow from it.
stakeholder: Executive sponsor
interest: high
influence: high
strategy: manage closely
information_needs:
- schedule and budget status
- top three risks
- decisions awaiting approval
channel: email report
frequency: biweekly
owner: project managerThe first four fields are the analysis. The remaining fields are the decisions that later chapters will explain in detail. Keeping them together in one record helps you see why a choice was made, which matters when someone asks later why the sponsor gets a report and the clerks do not.
Go beyond the grid: expectations and attitude
The grid says how much effort to spend. It does not say what to say. Two stakeholders in the same cell can need very different handling.
Expectations
For each important stakeholder, write down in one sentence what they expect from the project. Compare it with what the project will actually deliver. A gap here is a communication risk. For example, the warehouse supervisors may expect the new system to cut their reporting work, while the project scope only covers order entry. If nobody tells them, they will be disappointed at go-live.
Attitude
Add a current attitude and a desired attitude. A common scale is:
- Unaware
- Resistant
- Neutral
- Supportive
- Champion
A high-influence stakeholder who is resistant is the most urgent case in the whole analysis. The strategy "manage closely" still applies, but the content changes. You need to listen first, find out their concerns, and address them directly. A report alone will not move them.
You can add these fields to the record:
stakeholder: Finance director
interest: low
influence: high
strategy: keep satisfied
expectation: no budget overrun beyond 5 percent
current_attitude: neutral
desired_attitude: supportiveEdge cases and common errors
Stakeholders move between cells. Interest and influence change over the project. The IT security officer may have low interest for months and then become highly involved during the security review before release. Treat the analysis as a snapshot, and set a date for the next review. The plan maintenance chapter covers how to do that.
Groups hide differences. "Customers" is not one stakeholder. A large customer with a contract clause about delivery dates and a small user who sends feature requests need different handling. Split a group when its members would land in different cells.
Influence is not the same as seniority. A senior manager may have no say over the project, while a systems administrator who controls the test environment can delay it by weeks. Score influence by what the person can actually affect.
Hidden influencers. Some people sit outside the formal structure but shape opinions, such as a respected senior clerk whose view the whole team follows. Ask team members "whose opinion does this group listen to?" and add those people.
Low interest does not mean low need. A stakeholder in the "keep satisfied" cell may not want detail, but they still need to hear about anything that touches their concerns. Reduce the volume, not the reliability.
Sensitive notes. An analysis that says "resistant" or "difficult" about named people can cause harm if it leaks. Store it with limited access, and use neutral wording. Write "concerned about workload" instead of "obstructive". The version shared with the whole team can show only the strategy, channel, and frequency.
Over-engineering. For a small project, six to ten stakeholders in a simple table is enough. Do not spend more time on scoring than on communicating.
From analysis to the next steps
After this step you should have, for each stakeholder or group:
- A cell on the grid and the resulting strategy.
- A short statement of expectations.
- A current and desired attitude, for the stakeholders where it matters.
These results drive the following choices. The strategy sets the intensity of contact, which feeds frequency and channel. The expectations and concerns shape the key messages. The high-influence stakeholders become the first recipients on your escalation path.
Exercise
A project has a regional operations manager who has no authority over the budget or schedule, but whose team of 40 people will use the new system daily. She emails the project manager every week with questions. Which cell does she belong to, what is the strategy, and what would make you move her to a different cell?
Show answer
She has low influence and high interest, so she belongs in "keep informed". The strategy is regular updates and a way for her to ask questions and give feedback, for example a monthly update and a named contact. She would move to "manage closely" if she gained influence, for example if the sponsor made her approval a condition for go-live, or if her team's acceptance became a formal release criterion.
Exercise
Your analysis shows a high-influence, high-interest stakeholder whose attitude is "resistant". Name two things the plan should include for this person that a supportive stakeholder in the same cell would not need.
Show answer
Possible answers: a one-to-one conversation early to learn the specific concerns; a written record of the concerns and how each one was addressed; a named owner who is senior enough to take the concerns seriously; and a check-in after each decision that affects them. The goal is to move their attitude toward neutral or supportive, so the plan needs listening and follow-up, not only status reports.