Check that the plan works
A communication plan is a set of assumptions. You assumed that the sponsor wants a biweekly email, that the team reads the stand-up notes, and that a blocker raised in chat reaches the right person. Until you test those assumptions, you don't know whether the plan works. This chapter covers how to collect feedback, which measures to use, and how to turn the results into specific changes.
This chapter assumes you have a communication matrix like the one built in the previous chapter: audiences, information, channels, frequency, and owners. You should also know basic project vocabulary such as milestone, deliverable, and risk.
What "works" means
A plan works when the right people get the right information in time to act on it. That statement has three parts, and each can fail on its own.
- Reach: the message arrives. The email is delivered, the meeting happens, and the person attends or reads the notes.
- Understanding: the audience reads the message and takes the same meaning from it that you intended.
- Action: the audience does what the message required, such as approving a change, unblocking a task, or adjusting their own plans.
Many plans are judged only on reach ("we sent the report"). A report that is sent and never read has reached its audience in name only. Measure all three, in that order, because a failure at an earlier step makes the later ones impossible.
Choose what to measure
Pick a few measures per audience. Each one should connect to a part of the matrix, so that a bad result points to something you can change.
| Part of the plan | Question | Example measure |
|---|---|---|
| Channel | Does the message arrive? | Email open rate, meeting attendance, read receipts in chat |
| Format | Can people understand it? | Share of recipients who can restate the key point when asked |
| Frequency | Is the timing right? | Number of "I didn't know" surprises per month; complaints about too many meetings |
| Content | Is it the right information? | Questions that recipients ask repeatedly, which signal missing content |
| Owner | Does the owner deliver? | Share of scheduled communications sent on time |
| Escalation | Do issues reach decision makers in time? | Days between a blocker being raised and being resolved |
Two kinds of measure are useful, and they catch different problems.
- Activity measures count what happened: reports sent, meetings held, attendance. They are easy to collect and good at finding missed deliveries.
- Outcome measures show what the communication produced: decisions made on time, rework caused by misunderstanding, surprises. They are harder to collect and better at finding content or format problems.
An activity measure alone can mislead you. A team can hold every stand-up on schedule and still miss a dependency because nobody mentioned it.
Collect feedback directly
Numbers tell you something is wrong, and people tell you why. Use several methods, since each has blind spots.
Short surveys
Send a pulse survey every few weeks. Keep it to three to five questions and make it quick to answer. A useful set looks like this:
- Do you get the project information you need to do your job? (Scale of 1 to 5)
- Do you get it early enough to act on it? (Scale of 1 to 5)
- Is there anything you receive that you don't need?
- Is there anything you need that you don't receive?
- What is one thing you would change?
Questions 3 and 4 find the two classic problems: noise and gaps. Question 5 gives people a place to say something you didn't think to ask about.
Short conversations
For the high-influence stakeholders, such as the executive sponsor and key customer representatives, a survey is too impersonal and these people rarely answer one. Ask them directly in a five-minute conversation at the end of a regular meeting: "Is the report giving you what you need? What would you drop or add?" Write down the answer afterwards.
Retrospectives
The delivery team can review communication in a regular retrospective. Add one standing question, such as "Where did we learn something late this iteration?" Specific stories ("We found out about the API change after we had built against the old one") are more useful than general opinions.
Observation
Watch what happens, not only what people say. If you send a decision request and nobody replies, the channel or the format has failed regardless of what the survey says. Look at questions people ask in chat, items that come up repeatedly in meetings, and decisions that are made without the right people present.
Look for the signals of a failing plan
Some problems appear regularly. Learn to recognize them so that you can trace each one back to a part of the matrix.
| Symptom | Likely cause | Where to look in the matrix |
|---|---|---|
| Stakeholders say they were surprised by a delay | Frequency too low, or escalation trigger too late | Frequency, escalation rule |
| Reports are sent but nobody replies or acts | Format too dense, or no clear request in the message | Format, key message |
| Meetings run long and attendance drops | Too many meetings, or wrong attendees | Frequency, audience list |
| The same question is asked repeatedly | Missing information | Information column |
| Messages are late or skipped | Owner is overloaded or unclear | Owner column |
| People route around the plan with side conversations | Official channel is too slow or not trusted | Channel |
| Blockers sit for weeks | Escalation path is unclear or not used | Escalation rule |
A symptom can have more than one cause. Treat the cause in the table as the first hypothesis, then confirm it with a short conversation before you change the plan.
A feedback and review loop
Checking the plan is a loop, not a one-time audit. The steps repeat on a fixed schedule.
Run the loop at a steady interval. For a project that lasts a few months, a check every four to six weeks is common. For a short project, a single check at the midpoint may be enough. Also run it after any event that exposed a communication failure, such as a missed milestone caused by a late message.
Record the results
Keep a simple record so that you can see trends and show the sponsor what you changed. A short log is enough. The YAML below records one review of the sponsor report.
review_date: 2026-11-20
communication: Executive sponsor status report
measures:
- name: delivered on time
target: 100%
result: 83%
- name: sponsor can restate top risk
target: yes
result: no
feedback:
- "The report is too long. I read only the first page."
- "I did not realize the vendor delay affects the launch date."
cause: top risks are on page three; no explicit impact statement
change:
- move top three risks to the first section
- add one line per risk stating the effect on milestones
- owner to send by noon on the scheduled day
next_check: 2026-12-18Notice that the log ties each change to a measured result and a stated cause. It also sets a date for the next check, which closes the loop. Without that date, the change is never confirmed.
Interpret results with care
Feedback can mislead you. Keep these cautions in mind.
- Small samples: with a team of eight, one unhappy person is 12% of your data. Look for repeated points across people and methods, not a single answer.
- Polite answers: people often say a report is "fine" to avoid giving offense. Ask for specifics: "What did you do with the last report?" is harder to answer politely than "Do you like it?"
- Silence is not approval: a stakeholder who never responds may be satisfied, or may have stopped reading. Check with a direct question.
- Loud voices: one senior person's preference can drive changes that hurt other audiences. Weigh feedback against each audience's needs in the stakeholder analysis.
- Measuring what is easy: open rates are simple to count and say little about whether anyone understood. Pair them with at least one outcome measure.
- Over-correcting: do not change the whole plan after one bad week. Change one or two things, then check again, so that you can tell which change helped.
Close the loop with the audience
When you change the plan, tell the people who gave feedback. A short note is enough: "You said the report was too long. From next week the top three risks appear on the first page, and the details are in an appendix." This does three things. It shows that feedback leads to action, it prepares people for the change, and it invites correction if your fix misses the problem.
Share only the changes that affect each audience. The delivery team does not need to hear about the change to the sponsor report unless it alters their work.
Worked example
A project manager runs a six-month software rollout. After six weeks she checks the plan.
- Collect: she sends a four-question survey to the delivery team and holds a five-minute conversation with the sponsor. She also counts on-time reports.
- Compare: the team rates timeliness at 2 out of 5. Three people mention that they learned about a requirements change from a customer, not from the team. The sponsor says she reads only the first page of the report.
- Find the cause: requirement changes go through the monthly steering meeting, and the matrix has no route to tell the team sooner. The sponsor report puts risks on page three.
- Change: she adds a rule that approved changes are posted in the team chat within one working day, owned by the product owner. She moves the risk summary to page one of the report.
- Announce: she posts both changes in the team channel and tells the sponsor in the next meeting.
- Re-check: she schedules the next review for four weeks later and adds "learned of a change late" to the retrospective.
Each step maps to a column in the matrix: channel, frequency, content, and owner. That mapping is what makes the review useful.
Exercise
A project manager sends a biweekly status report to the steering committee. Delivery is on time every cycle, but in a review two members say they "never know what decision is needed from us," and one decision waited five weeks. Name the likely cause, which part of the matrix to change, and one measure to track the fix.
Show answer
The reports reach the audience, so the failure is in content or format: the report does not state the decision requested. Change the Information column (and the format) so that each report opens with a "Decisions needed" section listing the decision, the deadline, and the effect of delay. Track a measure such as the number of days between a decision being requested and being made, or the share of decision requests answered by their deadline. A secondary check is asking members whether they can name the decisions currently waiting for them.
Exercise
Your survey of the delivery team returns a score of 4.5 out of 5 for "I get the information I need," yet two milestones were affected by late discovery of dependencies. Give two reasons the survey might disagree with the outcome, and one other method you would use.
Show answer
Possible reasons: people rated the information they receive without knowing what they are missing, so gaps are invisible to them; and polite or hurried answers produced high scores. The survey measures perception, while the delays are an outcome. Other methods: run a retrospective question such as "Where did we learn something late?", review the two delayed milestones to trace where each dependency should have been communicated, and look at the questions asked repeatedly in chat.