Decide what each audience needs to know
This chapter assumes you know basic project vocabulary (scope, milestones, deliverables) and that you have already listed your stakeholders and placed them by influence and interest. Here you turn that analysis into a statement of what each audience needs to hear. Channels, frequency, and owners come in later chapters. Those choices depend on this one.
Why information needs come before channels
Many plans begin with a list of meetings and reports. The plan then fills them with whatever is easy to produce. The result is a weekly status email that nobody reads closely and a sponsor who still asks, "Where are we?"
Start from the question each person is trying to answer. An information need is the knowledge a stakeholder requires to do their part: to approve, to decide, to plan their own work, or to stay confident. A key message is the specific point you want that stakeholder to leave with in a given communication.
If you can't name the decision or action that a piece of information supports, you probably don't need to send it.
From stakeholder analysis to information needs
Your stakeholder analysis gives you two inputs: how much influence a person has and how interested they are. A third input is their role in the project's outcomes. Use all three.
| Stakeholder type | Typical question | Typical information need |
|---|---|---|
| Executive sponsor | Are we on track, and do you need me? | Schedule and budget status, top risks, decisions awaiting approval |
| Delivery team | What do I work on, and what is blocking me? | Priorities, dependencies, decisions made, changes in scope |
| Customer representative | Will I get what I expect, and when? | Progress against milestones, demo of working results, upcoming impact on their staff |
| Steering committee | What must we decide? | Change requests, options with consequences, escalated issues |
| Affected users or other departments | What will change for me? | Dates, what they must do, where to get help |
| Suppliers and vendors | What do you need from me, and by when? | Requirements, delivery dates, acceptance criteria |
These rows are starting points. Your project's actual people may differ, so check each need by asking the stakeholder directly where you can.
Use the influence and interest grid as a guide
The grid suggests a depth of communication, not a topic list:
- High influence, high interest (manage closely): detailed, regular, two-way information. They also need early warning of anything that could surprise them.
- High influence, low interest (keep satisfied): short summaries that stay focused on outcomes and decisions. Don't overload them, but don't leave them out of anything that touches their authority.
- Low influence, high interest (keep informed): clear progress updates and a way to ask questions or give feedback.
- Low influence, low interest (monitor): minimal or on-demand information, such as a page they can look at if they wish.
Categories of information
Most project information fits a few categories. Walking through them for each audience helps you catch gaps.
- Status: progress against schedule, budget, and scope.
- Risks and issues: what might go wrong, what has gone wrong, and what is being done about it.
- Decisions: what is needed, by whom, by when, and what was decided.
- Changes: scope, schedule, or budget changes and their effects.
- Results: deliverables, demos, test results, and acceptance outcomes.
- Asks and actions: what you need from the reader.
- Context: why the project exists and how it supports wider goals. This is rarely needed in every update, but newcomers and executives benefit from it.
A sponsor probably needs categories 1 to 4 and 6. A delivery team needs 3, 4, and 6 most, along with dependencies not listed above. A customer representative needs 1, 5, and 6. Mark these combinations explicitly in the plan.
Level of detail
The same fact changes shape across audiences. Take a delayed integration test.
- For the delivery team: "The payment API test environment is down. Ana is working with the vendor. Use the mock service until it returns. Next update at 15:00."
- For the sponsor: "Integration testing is two days behind because of a vendor environment outage. The milestone date of 14 March is still achievable. No decision needed yet."
- For the customer representative: "A technical delay has moved the demo preview from Tuesday to Thursday. The final delivery date has not changed."
All three statements are true. Each one answers that audience's question and leaves out what they don't need. Writing out one example like this for your most important audiences is a quick way to test whether your plan has distinct messages or just distinct recipients.
Key messages
A key message is a short statement you want repeated and remembered. For a project it might be the goal ("Orders will be processed in half the time by June"), the reason for a change, or the current state ("On track, one risk under watch").
Guidelines for key messages:
- Keep each to one or two sentences.
- State the effect on the audience, not only the activity.
- Keep messages consistent across audiences. Different detail is fine. Contradictory framing is not.
- Update them when the situation changes, and say that you have done so.
Record the result
Capture each audience's needs in a structured entry. This stakeholder record turns the analysis into communication choices:
stakeholder: Executive sponsor
interest: high
influence: high
strategy: manage closely
information_needs:
- schedule and budget status
- top three risks
- decisions awaiting approval
channel: email report
frequency: biweekly
owner: project managerThe information_needs list is the part this chapter produces. The channel, frequency, and owner fields are placeholders until you work through the next chapters. Limiting the list to a few items keeps the report short. "Top three risks" is a deliberate cap. Without one, risk sections tend to grow until the important items are lost.
Mapping needs to a diagram
The flow below shows how information moves from project facts to tailored messages.
Common errors
- Sending everything to everyone. A shared dump of all project data feels transparent but hides the important items. Selection is part of the job.
- Reporting activity instead of outcome. "We held three workshops" tells a sponsor little. "Requirements are agreed for two of three modules" tells them where the project stands.
- Leaving out the ask. If you need something, put it first and give a date. Otherwise it gets lost in the status.
- Hiding bad news in the detail. A red item that appears on page three will be found, but late and with a loss of trust. Put it where the reader will see it first.
- Assuming needs without asking. A sponsor might want a one-line status. Another might want the budget table. A short conversation at kickoff saves months of mismatch.
- Letting messages drift. If the team hears "the date is firm" while the customer hears "the date might move," someone will notice.
Handling different needs in one audience
Groups are rarely uniform. "The delivery team" may include developers, testers, and a designer, and each depends on different information. Two approaches work:
- Split the audience when needs differ strongly, for example engineers and business analysts.
- Keep one audience and use a common update with clearly labeled sections, so each person can find theirs.
Don't split so far that you create more communications than anyone can produce. If you end up with more than about eight to ten distinct audiences, look for ones that can merge.
Checking your list
Before moving on, test each audience's entry with these questions:
- What decision or action does this information support?
- Would this person be surprised or unable to act if they did not get it?
- Can the audience understand it without extra background?
- Is anything on the list there only because it is easy to produce?
- Has someone from that audience, or someone who knows them well, confirmed it?
Remove items that fail question 1. Add items that fail question 2.
Exercise
A customer representative receives the same detailed weekly status report as the delivery team. They rarely respond, and then ask at the monthly review whether the demo date has moved. Using the ideas in this chapter, what is the likely problem, and what would you change in the plan?
Show answer
The report matches the team's information needs (tasks, blockers, technical detail), not the customer's. The customer's question is "Will I get what I expect, and when?" so the date and scope information they need is buried or absent. Change the customer's entry so its information needs are progress against milestones, any date or scope changes with their impact, upcoming demos, and what the customer must do. Write it as a short, separate message with the milestone status first. Confirm the list with the customer representative.
Exercise
Write an information-needs entry for a steering committee in the same structure as the YAML example. Include interest, influence, strategy, three information needs, and leave channel, frequency, and owner as "to be decided".
Show answer
One valid answer: stakeholder: Steering committee interest: medium influence: high strategy: keep satisfied information_needs: - decisions needed, with options and consequences - change requests affecting scope, schedule, or budget - escalated issues and top risks channel: to be decided frequency: to be decided owner: to be decided Interest and strategy may differ if you justify them, for example high interest with "manage closely". Each need should tie to a decision the committee must make.