Recognizing the Eight Wastes Inside NVA Steps
This chapter assumes you can read a basic process map and distinguish value-added (VA), non-value-added (NVA), and business-necessary non-value-added (BNVA) steps. The focus here is recognizing patterns inside NVA work so that improvement actions target causes rather than symptoms.
NVA work does not change the product or service in a way the customer would pay for. Lean groups much of this work into eight wastes. The wastes are commonly remembered with the mnemonic TIMWOODS:
- Transport
- Inventory
- Motion
- Waiting
- Overproduction
- Overprocessing
- Defects
- Skills, meaning underused human capability
The eight wastes
| Waste | What it means | Example in an order process |
|---|---|---|
| Transport | Unnecessary movement of materials, documents, or information | Moving a paper order between three offices |
| Inventory | Excess items, work, or information waiting to be processed | A backlog of unprocessed orders |
| Motion | Unnecessary movement by people | Searching for a scanner or walking to retrieve a form |
| Waiting | Idle time caused by delays or queues | An order waits for an approval signature |
| Overproduction | Creating work before it is needed | Printing reports that no one has requested |
| Overprocessing | Doing more work than the customer or process requires | Entering the same data into four systems |
| Defects | Errors that require correction, replacement, or explanation | Fixing an incorrect customer address |
| Skills | Failing to use people's knowledge and abilities | Asking a trained analyst to perform only data entry |
Transport and motion are different. Transport moves something. Motion moves a person. A document sent between departments is transport; an employee walking across the building to find that document is motion.
How waste appears in a process map
A process map often shows waste as time between VA steps. For example, assembling a product may be VA, while moving parts to the assembly area, waiting for a missing component, and correcting an assembly error are NVA activities around it.
When annotating a map, record the waste category beside the step and capture its duration, frequency, and cause. A five-minute wait that occurs once is different from a five-minute wait that occurs on every order.
Looking beyond the visible step
Waste can be hidden inside a step that appears necessary. For example, “review order” may include checking a field, re-entering data, waiting for a system response, and correcting an earlier error. Separate these activities where possible. The classification should describe the work actually performed.
Some waste is caused by another waste:
- Overproduction creates inventory.
- Inventory increases waiting and handling.
- Defects create rework, extra transport, and extra motion.
- Overprocessing can create defects when information is copied repeatedly.
- Poor use of skills can conceal simpler process changes because staff spend time compensating for a weak system.
Use observations and data rather than labels alone. Ask who or what is waiting, moving, being corrected, or produced too early. Then trace the waste to a cause such as batch scheduling, unclear requirements, poor layout, missing standard work, or unreliable equipment.
Choosing an improvement target
Prioritize waste that has high customer impact, high frequency, long duration, or a strong connection to defects and delays. Eliminate work when it has no purpose. Reduce it when some part is required. Simplify it when the same result can be achieved with fewer handoffs or decisions.
Do not automatically remove every inspection. An inspection may be BNVA when a regulation, contract, or serious risk control requires it. First ask whether the inspection can be prevented through better process control. If it must remain, reduce its effort and place it as close as possible to the source of risk.
Exercise
An employee copies customer data from one system into another, waits for a supervisor's batch approval, and corrects frequent entry errors. Which wastes are present?
Show answer
Copying the data is overprocessing, the approval delay is waiting, and correcting entry errors is defects-related rework. The repeated copying may also contribute to the defects.