Deciding What to Eliminate, Reduce, Simplify, or Keep
Assume you can read a basic process map, identify the customer of a process, and measure the time taken by its steps. This chapter uses those skills to turn step classifications into improvement decisions.
Classifying a step is a diagnosis, not the final decision. A value-added (VA) step usually needs to remain, but it may still contain defects or excess motion. A non-value-added (NVA) step is a candidate for removal. A business-necessary non-value-added (BNVA) step may be required today, but its method and frequency should still be challenged.
Start with evidence
For each process step, record:
- Its classification: VA, NVA, or BNVA
- The time spent doing the work
- The waiting time before or after it
- The defect, risk, or customer problem it addresses
- The rule, contract, or control that makes it necessary
- The number of times it occurs
Do not prioritize only by the number of steps. A single approval queue may consume more time than ten short administrative tasks.
| Classification | First question | Typical action |
|---|---|---|
| VA | Does the step reliably create what the customer needs? | Keep, improve quality, or make it faster |
| NVA | Does the customer need this step, or does it only compensate for another problem? | Eliminate or reduce |
| BNVA | What specific rule or risk requires it? | Simplify, automate, reduce frequency, or retain |
Eliminate pure waste
Eliminate an NVA step when it creates no customer value and has no valid legal, contractual, or risk-control purpose. Examples include duplicate data entry, unnecessary movement, avoidable approvals, and waiting caused by poor scheduling.
Before deleting a step, check its connections. A rework step may look like waste, but removing it without fixing the defect would only send incorrect work to the customer. The better sequence is to remove the cause of the defect, then remove the rework.
Reduce necessary delay and effort
Some waste cannot be removed immediately. Reduce it by lowering its duration, frequency, batch size, or number of handoffs.
For example, a credit review may be BNVA because a risk policy requires it. The review could still be reduced by:
- Routing low-risk orders through an automatic check
- Setting a response-time target
- Reviewing exceptions instead of every transaction
- Sending complete information at the first handoff
Reduction is useful when a constraint is real but the current amount of work exceeds what the constraint requires.
Simplify BNVA work
A BNVA step often exists because of a regulation, contract, or risk control. The requirement does not always dictate the current procedure. Trace the step to its source and ask:
- What exact evidence or decision is required?
- Who needs to receive it?
- How often must it occur?
- What is the smallest reliable method that meets the requirement?
An inspection may remain necessary, but a standardized checklist, sampling plan, or automated measurement may replace a slow manual routine. Keep the control objective while removing unnecessary effort.
Keep and improve value-added work
Keep a VA step when the customer cares about its result, the step changes the product or service, and it is done correctly the first time. “Keep” does not mean “leave unchanged.” Improve the step if it has variation, defects, excess motion, or an unstable cycle time.
A useful priority order is:
- Remove high-time NVA work.
- Fix defects that create rework.
- Simplify high-time BNVA work.
- Improve slow or unstable VA work.
- Retain controls that have a clear purpose.
This order prevents a team from optimizing an important production step while ignoring hours of avoidable waiting.
Common judgment errors
Teams often protect familiar work by calling it “necessary.” Ask for the source of the requirement. “We have always done it” is not evidence.
Teams also remove a control because it appears not to add customer value. First identify the failure it prevents and the consequence of failure. A control with no traceable purpose may be obsolete, but that conclusion should follow a risk review.
After changing a step, remeasure lead time, defects, and control performance. An improvement is successful only if it removes effort without creating new risk or customer problems.
Exercise
A report is checked by two people because the first check often finds missing data. Should the second check be kept as BNVA?
Show answer
Not automatically. Investigate why data is missing. Remove or reduce the second check after improving the input process, then verify that defect and risk levels remain acceptable.