Sub topic 8
Lead Time, Cycle Time, and Value-Added Time
This chapter assumes you can read a simple process map and understand that a process is a sequence of steps. It also assumes you can distinguish an external customer from an internal customer.
Why time measures matter
Classifying steps tells you where work creates value. Time measures tell you how much of the customer's wait is actually needed to create that value.
A customer usually experiences the full elapsed time from request to delivery. That time can include processing, queues, approvals, inspections, rework, and transport. Lean analysis separates these parts so a team can target the largest delays.
Lead time
Lead time is the total elapsed time from the beginning of a customer's request to the completion of the output.
For an order process, lead time might begin when the order arrives and end when the product is delivered. It includes both work time and waiting time.
For example:
- Entering an order takes 5 minutes.
- The order waits 120 minutes for credit approval.
- A credit check takes 10 minutes.
- Assembly takes 30 minutes.
- Rework takes 15 minutes.
- Inspection takes 10 minutes.
- Packing takes 10 minutes.
The lead time is:
5 + 120 + 10 + 30 + 15 + 10 + 10 = 200 minutes
A process map should record waiting time as well as hands-on work. Ignoring queues produces an unrealistically low lead time.
Cycle time
Cycle time is the time required to complete one unit or one case through a defined process or operation.
The exact meaning depends on the organization. Some teams use cycle time for the elapsed time from starting work on one case to finishing it. Others use it for the time between completed units, also called the production rate or pace of output.
Before collecting data, write down the local definition and the start and stop points.
| Measure | Meaning | Example |
|---|---|---|
| Lead time | Total elapsed time from request to delivery | 200 minutes |
| Cycle time | Time for one case through a defined process | From order entry to packing |
| Value-added time | Time spent changing the product or service in a way the customer values | 40 minutes |
Lead time and cycle time can be equal when the boundaries are the same. They can also differ. For example, lead time may include time waiting before work starts, while cycle time measures only active processing after an employee begins the case.
Value-added time
Value-added time is the total time spent on steps that meet the value-added test:
- The customer cares about the result and would recognize its value.
- The step changes the form, fit, function, or information of the output.
- The step is done correctly the first time.
In the example, assembly takes 30 minutes and packing takes 10 minutes. If both steps meet the test, value-added time is 40 minutes.
Rework is not value-added because it corrects an earlier defect. A regulatory inspection may be business-necessary non-value-added. It can be required, but it does not usually transform the product for which the customer pays.
steps = [
("Enter order", 5, "BNVA"),
("Wait for credit approval", 120, "NVA"),
("Credit check", 10, "BNVA"),
("Assemble product", 30, "VA"),
("Rework defects", 15, "NVA"),
("Regulatory inspection", 10, "BNVA"),
("Pack and label", 10, "VA"),
]
lead_time = sum(minutes for _, minutes, _ in steps)
value_added_time = sum(
minutes for _, minutes, classification in steps
if classification == "VA"
)
print(f"Lead time: {lead_time} minutes")
print(f"Value-added time: {value_added_time} minutes")The output is:
Lead time: 200 minutes
Value-added time: 40 minutesProcess cycle efficiency
Process cycle efficiency (PCE) is the percentage of lead time that is value-added:
PCE = value-added time ÷ lead time × 100
For this process:
PCE = 40 ÷ 200 × 100 = 20%
A low PCE does not prove that every non-value-added step can be removed immediately. Some steps protect safety, satisfy a law, or support a contractual requirement. It does show that most elapsed time deserves investigation.
Exercise
A process has 12 minutes of value-added work and 48 minutes of total lead time. What is its process cycle efficiency?
Show answer
PCE = 12 ÷ 48 × 100 = 25%.