Sub topic 1
The baseline that everything is measured against
Earned value management (EVM) is a method for checking whether a project is on time and on budget. It compares three measurements taken on the same status date. This chapter covers the baseline and the first three measurements: planned value, earned value, and actual cost.
Prerequisites
You should be comfortable with project vocabulary such as scope, schedule, and budget, and with a work breakdown structure (WBS) that splits the project into work packages. You should also be able to read a schedule and a budget, and to work with simple ratios. The examples use Python 3.
The performance measurement baseline
The performance measurement baseline (PMB) is the approved plan. It assigns a budget to each work package and spreads that budget over time. The total budget for the whole project is the budget at completion (BAC). Every later measurement is compared against this baseline, so the baseline must be fixed once approved.
baseline = {"Design": 10_000, "Build": 60_000, "Test": 30_000}
bac = sum(baseline.values())
print(f"BAC: {bac:,}")Planned value (PV)
Planned value is the budgeted cost of the work scheduled to be done by the status date. It answers the question, "What should be done by now?" It does not depend on what the team has actually completed.
def planned_value(budget, start_week, end_week, week):
"""Planned value of one work package, spread evenly over its duration."""
if week <= start_week:
return 0.0
if week >= end_week:
return float(budget)
return budget * (week - start_week) / (end_week - start_week)
pv = planned_value(60_000, start_week=3, end_week=9, week=6)
print(f"PV for Build at week 6: {pv:,.0f}") # 30,000Earned value (EV)
Earned value is the budgeted cost of the work actually completed. It is measured with the baseline budget, not with what the work cost. If a 60,000 work package is 40 percent complete, its earned value is 24,000.
Actual cost (AC)
Actual cost is the money really spent to produce the work completed so far. AC can be higher or lower than EV. The gap between them is the basis for cost analysis in the next chapter.
Exercise
A work package has a budget of 20,000 and runs from week 2 to week 6. At week 4, the team has completed work the baseline values at 8,000, and the invoices total 9,500. What are PV, EV, and AC?
Show answer
PV is 10,000, because half the duration has passed (20,000 × 2/4). EV is 8,000, the budget of the completed work. AC is 9,500, the money spent.