01Chapter 1: The baseline that everything is measured againstEarned value management (EVM) is a method for checking whether a project is on time and on budget. It compares three measurements taken on the same status date. This chapter covers the baseline and the first three measurements: planned value, earned value, and actual cost.2 min read
02Chapter 2: Measuring earned value: 0/100, 50/50, weighted milestones and percent completeThis chapter assumes you know project vocabulary (scope, schedule, budget, work breakdown structure), can read a baseline schedule, and can work with ratios. Earned value (EV) is the budgeted value of work completed by the status date. To compute it, you need a rule for how much credit a work packag1 min read
03Chapter 3: Reading SPI and CPI togetherThis chapter assumes you know planned value (PV), earned value (EV), actual cost (AC), and budget at completion (BAC), and that you can compute simple ratios. SPI is EV divided by PV. CPI is EV divided by AC. Read them together, not one at a time.2 min read