Sub topic 3
Reading SPI and CPI together
This chapter assumes you know planned value (PV), earned value (EV), actual cost (AC), and budget at completion (BAC), and that you can compute simple ratios. SPI is EV divided by PV. CPI is EV divided by AC. Read them together, not one at a time.
- SPI below 1.0 means the project is behind schedule.
- CPI below 1.0 means the project costs more than the work it has earned.
- Each index above 1.0 means the project is ahead of plan on that measure.
Forecasting final cost with EAC and ETC
Estimate at completion (EAC) is the forecast total cost. Estimate to complete (ETC) is the money still needed. If current cost efficiency continues, EAC = BAC / CPI and ETC = EAC - AC.
bac, pv, ev, ac = 100_000, 40_000, 35_000, 42_000
spi = ev / pv
cpi = ev / ac
eac = bac / cpi
etc = eac - ac
tcpi = (bac - ev) / (bac - ac)
print(f"SPI={spi:.3f} CPI={cpi:.3f} EAC={eac:,.0f} ETC={etc:,.0f} TCPI={tcpi:.3f}")TCPI: the efficiency the remaining work requires
The to-complete performance index (TCPI) is the cost efficiency needed on the remaining work to finish on BAC: TCPI = (BAC - EV) / (BAC - AC). In the example, TCPI is 1.121, so the team must earn 1.121 dollars of value per dollar spent from now on. That is harder than the current CPI of 0.833.
Why SPI drifts toward 1.0 as a project ends
Near the end, PV approaches BAC, so EV/PV tends toward 1.0 even when the project is late. A late project can look on schedule.
Earned schedule: a time-based alternative to SPI
Earned schedule (ES) converts EV into the time at which that value was planned. Time-based SPI(t) = ES / actual time. Suppose cumulative PV reaches 25,000 at the end of period 2 and 40,000 at the end of period 3. An EV of 35,000 gives ES = 2 + (35,000 - 25,000) / (40,000 - 25,000) = 2.667 periods. After 3 periods, SPI(t) = 2.667 / 3 = 0.889.
Trends, thresholds and honest reporting
Report the index for several status dates, not one. A falling CPI over three periods matters more than a single low value. Agree on thresholds in advance, such as 0.95 for amber and 0.90 for red, and state the forecast EAC with its assumptions.
Exercise
A project has BAC 80,000, EV 30,000 and AC 36,000. What are CPI, EAC and TCPI?
Show answer
CPI = 30,000 / 36,000 = 0.833. EAC = 80,000 / 0.833 = 96,000. TCPI = (80,000 - 30,000) / (80,000 - 36,000) = 50,000 / 44,000 = 1.136.