Sub topic 2
Measuring earned value: 0/100, 50/50, weighted milestones and percent complete
This chapter assumes you know project vocabulary (scope, schedule, budget, work breakdown structure), can read a baseline schedule, and can work with ratios. Earned value (EV) is the budgeted value of work completed by the status date. To compute it, you need a rule for how much credit a work package earns while it is in progress. Pick the rule before the status date, because it changes every index that follows.
Choosing a measurement method
| Method | Credit before completion | Credit at completion | Best for |
|---|---|---|---|
| 0/100 | 0% | 100% | Short packages, roughly two weeks or less |
| 50/50 | 50% once started | 100% when finished | Packages with a clear start and finish |
| Weighted milestones | Each milestone's weight, once reached | Weights sum to 100% | Long packages with distinct deliverables |
| Percent complete | Estimated share of the budget | 100% | Work that is hard to split into milestones |
Weighted milestones assign each milestone a share of the package budget, such as design 20%, build 50% and test 30%. The weights must sum to 1.0.
def zero_hundred_ev(budget, finished):
return budget if finished else 0.0
def fifty_fifty_ev(budget, started, finished):
return budget * (0.5 * started + 0.5 * finished)
def weighted_ev(budget, milestones):
"""milestones: (weight, fraction_done) pairs whose weights sum to 1.0."""
total_weight = sum(weight for weight, _ in milestones)
if abs(total_weight - 1.0) > 1e-9:
raise ValueError("milestone weights must sum to 1.0")
return budget * sum(weight * done for weight, done in milestones)
if __name__ == "__main__":
budget = 10_000
print(f"0/100 EV: {zero_hundred_ev(budget, finished=False):,.0f}")
print(f"50/50 EV: {fifty_fifty_ev(budget, started=True, finished=False):,.0f}")
ev = weighted_ev(budget, [(0.2, 1.0), (0.5, 0.4), (0.3, 0.0)])
print(f"Weighted EV: {ev:,.0f}")Variances as absolute differences
Schedule variance (SV) is EV minus planned value (PV). Cost variance (CV) is EV minus actual cost (AC). Both are in currency. A negative value means behind schedule or over budget.
For example, with PV 4,500, EV 4,000 and AC 4,200, SV is -500 and CV is -200.
Schedule Performance Index: EV divided by PV
SPI = EV / PV. A value below 1.0 means less work is done than planned. Using the example above, SPI is 4,000 / 4,500 = 0.889.
Cost Performance Index: EV divided by AC
CPI = EV / AC. A value below 1.0 means the work costs more than its budgeted value. Using the same example, CPI is 4,000 / 4,200 = 0.952.
Exercise
A work package has a budget of 8,000. Design is 30% of the budget and is 100% done. Build is 50% of the budget and is 60% done. Test is 20% of the budget and is not started. What is EV? If PV is 6,000, what is SPI?
Show answer
EV is 8,000 × (0.3 × 1.0 + 0.5 × 0.6) = 4,800. SPI is 4,800 / 6,000 = 0.8.