Sub topic 14
Running the session with a team
This chapter adapts the weekly planning session for a group. It assumes you already run your own session: you can pick weekly outcomes, calculate capacity, and block time. It builds on the earlier chapters on choosing outcomes and on committing to and sharing the plan.
What changes with a team
A personal session has one person deciding what matters and what fits. A team session has several people, each with their own calendar and skills, working toward shared results. Three things change:
- Outcomes need an owner. A shared outcome with no named owner usually has no one working on it.
- Capacity is the sum of individual capacities, and it is rarely even. Someone may be on leave, on call, or in meetings most of the week.
- Dependencies appear. One person's block may wait on another person's output.
Keep the personal session, add a short shared one
Do not replace individual planning. Each person first runs their own review and capacity check. Then the team meets for a short session, about 30 minutes for a team of five or fewer, to align on outcomes and dependencies.
A team agenda
Reuse the same structure as your personal agenda, with a shared focus:
- Review (5 min): What did the team finish, carry over, or drop last week?
- Outcomes (10 min): Propose at most three team outcomes. Assign one owner to each.
- Capacity (10 min): Each person states their plannable hours. Note absences.
- Dependencies and commitments (5 min): Who needs something from whom, and by which day?
Check team capacity
Compute each person's plannable hours with the same formula you use alone, then add them up and compare the total with the estimates.
def plannable_hours(working_hours, fixed_hours, buffer_ratio=0.2):
"""Hours left for planned work after meetings and a buffer."""
focus = max(working_hours - fixed_hours, 0)
return focus * (1 - buffer_ratio)
team = {
"Ana": plannable_hours(40, 12),
"Ben": plannable_hours(40, 20),
"Chen": plannable_hours(24, 6),
}
capacity = sum(team.values())
estimate = {"Ship search fix": 20, "Prepare demo": 10, "Migrate reports": 16}
total = sum(estimate.values())
for person, hours in team.items():
print(f"{person}: {hours:.1f} h")
print(f"Team capacity: {capacity:.1f} h, estimated work: {total} h")
print("Fits" if total <= capacity else "Over capacity: cut or defer")The team capacity is 22.4 + 16.0 + 14.4 = 52.8 hours, and the estimated work is 46 hours, so the plan fits. Notice that the total can fit while one person is still overloaded. Always check the load per person as well, not only the sum.
Share and commit
Put the plan in one place that everyone can see, such as a shared document or a board. Include each outcome, its owner, and any dependency with a date. Commit as a team: each owner confirms their outcome out loud before the session ends. During the week, a short daily check-in, such as a 10-minute stand-up or a written update, lets people flag blocked work early so the team can replan.
Common team mistakes
| Mistake | Fix |
|---|---|
| Too many outcomes because everyone adds their own | Cap team outcomes at three and move the rest to personal plans |
| Outcomes without owners | Assign one named owner per outcome |
| Ignoring absences and on-call duty | Collect them in the capacity step |
| Long session that repeats the individual plans | Do individual prep beforehand and keep the shared session short |
Exercise
Three people have plannable hours of 20, 10, and 15. The team plans 40 hours of work, but 25 of those hours are assigned to the person with 10 plannable hours. Does the plan work? What should the team do?
Show answer
The total capacity is 45 hours, so 40 hours fits in total. The plan still fails, because the person with 10 plannable hours is assigned 25. The team should reassign at least 15 hours of that work to the others, or cut or defer an outcome, until each person's load is within their own capacity.