Sub topic 10
Committing to the plan and sharing it
This chapter assumes you have already chosen your weekly outcomes, calculated your plannable hours, and placed time blocks and a buffer on your calendar. Here you turn that draft into a commitment and tell the right people about it.
Why a plan needs a commitment step
A draft plan is a guess. A committed plan is a promise you have checked against your capacity. The difference matters because the draft is easy to ignore on Tuesday, while a commitment you have written down and shared is harder to drop quietly.
Committing has two parts:
- A fit check: do the chosen tasks fit in the hours you can plan?
- A share: the people who depend on you can see what to expect.
Run the fit check
Compare the total estimated hours of your chosen work with your plannable hours. Do this before you commit, not after.
def plannable_hours(working_hours, fixed_hours, buffer_ratio=0.2):
"""Hours left for planned work after meetings and a buffer."""
focus = max(working_hours - fixed_hours, 0)
return focus * (1 - buffer_ratio)
def check_plan(tasks, capacity):
"""tasks is a list of (name, estimated_hours) pairs."""
total = sum(hours for _, hours in tasks)
return total, total <= capacity
capacity = plannable_hours(working_hours=40, fixed_hours=12)
tasks = [("Draft proposal", 6), ("Review pull requests", 4), ("Prepare demo", 5)]
total, fits = check_plan(tasks, capacity)
print(capacity, total, fits) # 22.4 15 TrueHere the plan uses 15 of 22.4 hours, so it fits with room to spare. If fits were False, you would not commit yet. You would cut or shrink an outcome first.
What to do when the plan does not fit
Remove work. Do not stretch the week.
- Move the lowest-priority outcome to next week.
- Reduce its scope, for example "draft the proposal" instead of "finish the proposal".
- Renegotiate a deadline with whoever set it.
Do not shrink the buffer to make the numbers work. The buffer exists because estimates are usually too low.
Share the plan
Sharing is a short message, not a document. Include only what other people need to act on:
- The outcomes, at most three.
- Days or times when you are focused and slow to respond.
- Anything that depends on someone else, with a date.
- What you are not doing this week, if someone might expect it.
Plan for the week of 2026-11-30
1. Send the proposal draft to Sam (Wed)
2. Clear the pull request backlog (Thu)
3. Demo ready for Friday 14:00
Focus time: Tue and Wed mornings, slower replies.
Need from Priya: API access by Tuesday.
Not this week: the onboarding doc.Post it where your team or manager already looks, such as a team channel or a shared note. A new place is one more thing people forget to check.
Common errors
- Committing before the fit check. The plan then starts the week already overloaded.
- Sharing a task list. A list of 15 items hides what matters. Share outcomes.
- Hiding dependencies. If you need something from someone, say so with a date, or you will find out on the day you are blocked.
- Treating the commitment as fixed. A commitment is firm for the week, but you can change it openly. Tell the same people when it changes. The daily check-in, covered in the next chapter, is where you decide that.
Exercise
You have 36 working hours and 10 hours of fixed commitments, with a 20% buffer. Your tasks are estimated at 9, 7, 6, and 5 hours. Does the plan fit? What do you do if it does not?
Show answer
Plannable hours are (36 - 10) x 0.8 = 20.8. The tasks total 27 hours, so the plan does not fit by 6.2 hours. Do not shrink the buffer. Move the lowest-priority task (the 7-hour or 5-hour one) to next week, reduce a task's scope, or renegotiate a deadline. Dropping the 7-hour task gives 20 hours, which fits. Then share the revised outcomes.