A five-minute retrospective
This chapter assumes you already run a weekly planning session with a review step, a short list of outcomes, and a plan built from your calendar capacity. If you have not set those up, read the earlier chapters first. Here you add the last piece: a short look back at how the session and the week worked, so the next session is better.
What a retrospective is for
A retrospective is a short, structured look at your own process. It is different from the review at the start of the session. The review asks what happened to each task: finished, carried over, or dropped. The retrospective asks why the week went the way it did, and what you will change.
Without it, you repeat the same mistakes. You overbook Tuesday every week, or you estimate every writing task too low, and you never notice because each week feels like its own story.
The two questions
Keep the retrospective to two prompts, which match the last section of the agenda template:
- What worked: one or two habits, blocks, or decisions you want to keep.
- What to change next week: one change, small enough to try immediately.
Limit yourself to one change. Several changes at once make it impossible to tell which one helped.
Use numbers, not impressions
Your memory of a week is unreliable. A bad Thursday can make the whole week feel like a failure. Compare the plan against what happened, using a few figures:
- Outcomes planned and outcomes finished.
- Estimated hours and actual hours for the main tasks.
- Plannable hours and the hours you really spent on planned work.
The estimate-versus-actual ratio is the most useful figure. If you planned 15 hours and the work took 21, your ratio is 1.4. You can feed that back into the next plan.
def estimate_ratio(tasks):
"""tasks is a list of (name, estimated_hours, actual_hours) tuples."""
estimated = sum(est for _, est, _ in tasks)
actual = sum(act for _, _, act in tasks)
return actual / estimated
week = [
("Draft proposal", 6, 9),
("Review pull requests", 4, 4),
("Prepare demo", 5, 8),
]
ratio = estimate_ratio(week)
print(round(ratio, 2)) # 1.4A ratio above 1 means you underestimate. Next week, multiply new estimates by that ratio, or raise your buffer above 20%. A ratio below 1 means you have slack you are not using.
Where it fits in the session
The retrospective is the last five minutes of the agenda. Some people prefer to do it at the end of the week, just before the next session, while the week is fresh. Either works if it happens at the same point each time.
Write the one change at the top of next week's plan. If you only write it in the retrospective notes, you will not see it again.
Common errors
- Skipping it when the week went well. Good weeks show you what to keep.
- Writing vague changes such as "be more focused". Write something testable, such as "no meetings before 11:00 on Tuesday and Thursday".
- Blaming interruptions without counting them. If interruptions caused the miss, record how many hours they took and raise the buffer to match.
- Running it as a long reflection. Stop at five minutes. If a problem needs more thought, add it to next week's outcomes as a task.
Exercise
Last week you planned three outcomes with 18 estimated hours. The work took 24 hours, and you finished two outcomes. What is your estimate ratio, and what one change would you write for next week?
Show answer
The ratio is 24 / 18 = 1.33. You underestimated by about a third. A good single change is to multiply next week's estimates by 1.33 (or raise the buffer from 20% to about 30%) and check the ratio again at the next retrospective.