Sub topic 7
Breaking work down and estimating it
This chapter assumes you already have a short list of weekly outcomes and a capacity figure in hours from your calendar. Here you turn each outcome into tasks small enough to estimate, then check the total against your capacity.
Why break work down
An outcome such as "Ship the proposal" is too large to estimate. You can't tell where it starts, what it contains, or how long it takes. A task such as "Write the pricing section" is concrete enough that you can guess its length.
Aim for tasks that take between 30 minutes and half a day. If a task looks longer than that, split it. If it takes under 15 minutes, group it with similar small tasks into one "admin" task.
A quick splitting method
- Write the outcome at the top.
- List the steps from start to finish, each beginning with a verb.
- Mark any step you can't picture doing. Split it again, or add a task that finds out what you need to know.
- Add the steps people forget: review, rework after feedback, and waiting time.
Estimating honestly
Estimates are usually too low, because you picture the work going smoothly. Three habits help.
- Use your own history. Look at last week's review and compare what you estimated with what the work took.
- Estimate in ranges when unsure. Write "3 to 5 hours" and plan with the higher number.
- Count work that depends on others at the time you need, not the time you hope for.
The following table shows a breakdown for one outcome.
| Task | Estimate (hours) |
|---|---|
| Outline the proposal | 1 |
| Write pricing section | 3 |
| Write scope section | 2 |
| Revise after feedback | 2 |
Checking the plan against capacity
Once each task has an estimate, add the hours and compare them with your plannable hours. The calendar chapter showed how to compute that figure. This function does the comparison.
def check_plan(tasks, capacity):
"""tasks is a list of (name, estimated_hours) pairs."""
total = sum(hours for _, hours in tasks)
return total, total <= capacity
tasks = [("Draft proposal", 6), ("Review pull requests", 4), ("Prepare demo", 5)]
total, fits = check_plan(tasks, capacity=22.4)
print(total, fits) # 15 TrueThe plan fits with 7.4 hours to spare. If fits were False, you would not squeeze the work in. You would remove a task or move it to next week, starting with the one that serves the outcome least.
Common errors
- Estimating the outcome, not the tasks. One big number hides what is in it. Split first.
- Planning to 100% of capacity. The buffer is already subtracted in the capacity figure. Do not fill it back in.
- Forgetting the small stuff. Messages, reviews, and handoffs take real time. Give them a task of their own.
- Never checking the guess. If you don't compare estimates with actuals, you can't improve them.
Exercise
Your capacity is 18 hours. Your tasks are: write report (7), prepare slides (5), review contract (4), and answer backlog of emails (3). Does the plan fit? What would you do about it?
Show answer
The total is 7 + 5 + 4 + 3 = 19 hours, which is more than 18, so the plan does not fit. Cut or defer at least one hour of work. The simplest choice is to move the email backlog (3 hours) to next week, or to shrink it to a 2-hour limited session, depending on which outcome it serves. Do not reduce your buffer to make the numbers fit.