Sub topic 11
Using a daily check-in to keep the plan honest
A weekly plan is a forecast. By Tuesday afternoon it is already slightly wrong, and by Thursday it can be fiction if nobody looks at it. The daily check-in is a short routine that compares the plan with what is actually happening and adjusts it while the adjustment is still cheap. This chapter covers what to look at, how long to spend, how to decide what to change, and the mistakes that turn the check-in into a second planning session.
This chapter assumes you already have a weekly plan with up to three outcomes, scheduled time blocks, and a buffer. It also assumes you have a task list or notes tool and a calendar you can edit. The earlier chapters on outcomes, capacity, and buffers cover those parts.
What the check-in is for
The check-in has one job: to answer "Is the plan for the rest of this week still achievable, and what is the next block?" It is not a place to plan new work, groom the inbox, or reflect on the week. Those belong to the weekly session and the retrospective.
The check-in does three things:
- It records what really happened yesterday, using real hours rather than hoped-for ones.
- It recalculates what is left against the time that is left.
- It makes one decision about today. You keep the plan, move something, or cut something.
Doing this daily matters because estimation errors compound. A task that overruns by two hours on Monday takes two hours from a later block. If you only notice on Friday, the choices are to work late or to miss the outcome. If you notice on Tuesday, you can drop a lower-priority task or move a meeting.
When and how long
Pick a fixed point in the day and attach it to something you already do. Two common choices:
| Timing | Strength | Weakness |
|---|---|---|
| Start of the day (first 10 minutes) | Sets the day's blocks while you are fresh | Yesterday's details are slightly stale |
| End of the day (last 10 minutes) | Yesterday's work is vivid, and tomorrow is ready when you sit down | Tired, so you may rationalize overruns |
Start-of-day is easier to keep. End-of-day gives better data. Either way, cap it at 5 to 10 minutes. If it regularly takes longer, you are replanning instead of checking in.
The check-in routine
Run the same four steps each time, so it needs little thought.
- Update actuals. For each block you worked, note whether the task is done, partly done, or untouched. Estimate the remaining hours for unfinished tasks. Do not keep the original estimate, because the remaining hours are the useful number.
- Update the calendar. Look at the rest of the week for new meetings, cancellations, and deadlines that moved. Recount the focus hours that are left.
- Compare. Sum the remaining task hours and compare them with the remaining plannable hours, which means focus hours minus the unspent buffer.
- Decide. Choose the smallest change that restores a realistic plan, and then name the first block of the day.
Step 3 in code
The comparison is simple arithmetic, but writing it down shows what to track. This script takes remaining hours per task and the days left, and reports the margin.
def check_in(remaining_by_task, days_left, focus_per_day):
"""Return remaining work, remaining capacity, and the margin in hours."""
remaining = sum(remaining_by_task.values())
capacity = days_left * focus_per_day
return remaining, capacity, round(capacity - remaining, 1)
# Tuesday evening: three days left, about 4.5 plannable hours per day.
tasks = {"Draft proposal": 4, "Review pull requests": 3, "Prepare demo": 5}
print(check_in(tasks, days_left=3, focus_per_day=4.5)) # (12, 13.5, 1.5)
# The demo turns out to need more work than estimated.
tasks["Prepare demo"] = 8
print(check_in(tasks, days_left=3, focus_per_day=4.5)) # (15, 13.5, -1.5)A positive margin means the plan holds. A negative margin means you are overcommitted by that many hours, and you need to make a decision before you start working. In the second case the shortfall is 1.5 hours. That is small enough to fix by trimming scope, not by working evenings.
Deciding what to change
When the margin is negative, you have a limited set of moves. Use them roughly in this order, because each later move costs more than the one before it.
- Use the buffer. This is what it is for. If the buffer covers the gap, absorb the overrun and note it.
- Shrink scope. Ask what the smallest version of the outcome is that still counts. A demo with two scenarios instead of four may still satisfy the outcome.
- Move a low-value task. Push work that does not serve an outcome to next week. Do this explicitly, by writing it to next week's inbox, so that it is not silently lost.
- Renegotiate. If an outcome depends on someone else, or has a deadline someone else set, tell them early. A heads-up on Tuesday is a normal conversation. The same news on Friday is a problem.
- Drop an outcome. If the gap is large, choose which of the three outcomes to give up. Choose deliberately, by priority, rather than letting the last one fail by default.
Adding hours is not on the list. Working late is a way to borrow from next week, and it hides the estimate error that you want the retrospective to see.
Handling surprises and new requests
New requests are the other way plans go stale. When one arrives during the week, the check-in is the place to process it. Ask three questions:
- Is it urgent? It has a real deadline this week, or someone is blocked without it.
- Is it important? It serves one of your outcomes or a higher-priority one.
- What does it replace? A week has a fixed capacity, so anything new displaces something else.
If the request is neither urgent nor important, put it in the inbox for the next weekly session. If it is both, write down what you are removing before you add it. This turns "I'll just squeeze it in" into a visible trade, and visible trades are easier to defend later.
A recording format
Keep a short log, so each check-in is a few lines and the retrospective has data. Put it at the bottom of the weekly plan document.
## Daily check-ins
### Tuesday
- Done: Draft proposal (3 h of 6 h planned, 4 h remaining)
- Calendar: new 1 h sync on Thursday
- Margin: +1.5 h
- Change: none
- First block today: Draft proposal, 09:00 to 11:00
### Wednesday
- Done: Review pull requests (1 h; 3 h remaining)
- Calendar: no changes
- Margin: -1.5 h (demo estimate raised from 5 h to 8 h)
- Change: cut demo to two scenarios; moves 1.5 h to next week
- First block today: Prepare demo, 09:00 to 11:30The log records the margin, the change, and the reason. Those three fields are enough to spot patterns later, such as one kind of task that always runs over.
Common errors
- Turning it into a replan. If you rebuild the whole week each morning, you spend an hour a day on planning and you never trust any version. Change the smallest thing that restores the margin.
- Tracking the original estimate. Comparing "6 hours planned, 3 spent" tells you nothing about the future. "4 hours remaining" does.
- Skipping the check on bad days. The days you most want to skip are the days it is most useful. If the day was a mess, run a two-minute version: update the remaining hours and name tomorrow's first block.
- Forgetting to count the buffer as spent. If you absorb an overrun with buffer, reduce the buffer for the rest of the week. Otherwise you will spend the same hours twice.
- Never saying no. If every new request is accepted and nothing is removed, the check-in will report a negative margin every day. That is a signal about intake, not about estimation.
- Ignoring a repeated overrun. If the same type of task is late three weeks running, adjust your estimates for that type instead of absorbing the error each week.
Exercises
Exercise
It is Wednesday morning. Your plan has 3 days left (Wednesday to Friday) with 4 plannable hours per day. Remaining work is: Write report, 5 h; Review contract, 4 h; Prepare slides, 6 h. What is the margin, and what is your first move?
Show answer
Capacity is 3 x 4 = 12 hours. Remaining work is 5 + 4 + 6 = 15 hours. The margin is 12 - 15 = -3 hours. First check whether unspent buffer covers the gap. If it does not, shrink the scope of one task (for example, fewer slides) or move the lowest-priority task to next week. Do not add evening hours.
Exercise
A colleague asks you on Thursday to take on a 3-hour task "this week". Your margin is currently 0. List the questions you ask and the acceptable outcomes.
Show answer
Ask whether it is urgent and whether it serves a weekly outcome. Then ask what it replaces. With a margin of 0, accepting it creates a -3 hour margin, so you must remove 3 hours of work, shrink scope, or negotiate a deadline of next week. If it is neither urgent nor important, add it to the inbox for the next weekly session. If it is urgent, write down what you are dropping before you accept.