Breaking work down and estimating it
This chapter assumes you have already chosen up to three outcomes for the week and worked out your plannable hours from your calendar. Both steps come earlier in the session. Here you turn each outcome into tasks small enough to estimate. Then you check whether the total fits your capacity before you schedule anything.
Why estimate before you block time
An outcome such as "Proposal approved" can't go on a calendar. You can't tell how long it takes, what to do first, or whether you have room for it. Estimating closes that gap. It answers one question: does the work I want to do fit in the hours I have?
You are not predicting the future precisely. You are catching plans that are clearly too big while they are still cheap to change. Finding out on Monday that 30 hours of work won't fit in 22 hours costs you one edit. Finding out on Thursday costs you a missed commitment.
The step sits between choosing outcomes and time blocking:
Breaking an outcome into tasks
A good task for weekly planning has three properties:
- It starts with a verb and names a visible result, such as "Draft section 2 of the proposal".
- One person can finish it without waiting on anyone else, or the wait is called out as a separate item.
- It fits in a single sitting, roughly 30 minutes to 3 hours.
If a task is longer than about half a day, split it. Large tasks hide uncertainty. "Write the proposal" might be 4 hours or 20, and you can't tell which until you list its parts.
Three common ways to split work:
| Method | Use it when | Example |
|---|---|---|
| By stage | The work has a natural order | Outline, draft, review, revise, send |
| By deliverable | The outcome has several parts | Slides, speaker notes, demo script |
| By unknown | You aren't sure how to start | Spike: read the API docs and write down what you learn |
The last row matters. When you don't know how to do something, don't estimate the whole job. Create a small, time-boxed task to find out, such as 90 minutes of investigation. Estimate the rest after that task is done, possibly during next week's session.
Stop splitting at the right point
You don't need a task for every five-minute action. Group small related items such as replying to a few emails or filing receipts into one task called "Admin sweep". Give it a single estimate. If you split too finely, planning takes longer than the work, and you will stop doing it.
Estimating each task
Give every task one number in hours. Use these habits to keep the numbers useful:
- Estimate effort, not elapsed time. "Two hours of focused work" is different from "done by Wednesday". Waiting for a reply does not count as effort. Track the wait separately.
- Use coarse sizes. Round to 0.5, 1, 2, 3, 4 or 6 hours. A figure like 2.75 hours claims more accuracy than you have.
- Compare to past work. Look at your review from last week. If a similar task took 3 hours, don't call this one 1 hour because you feel optimistic.
- Include the hidden parts. Setup, context switching, review, and fixing small mistakes belong in the estimate.
- Estimate the whole task before you start. Don't adjust numbers during the week to make the plan look better.
Most people underestimate. This is known as the planning fallacy: we picture the smooth path and forget interruptions. Counter it with a short, honest rule. Take your best guess and ask, "What happened the last time I did something like this?" If the answer is "it took longer", pad the estimate.
A quick three-point check for risky tasks
For a task you are unsure about, write an optimistic, a likely, and a pessimistic number. A common weighted formula is:
estimate = (optimistic + 4 * likely + pessimistic) / 6You don't need this for every task. Use it for the one or two tasks that worry you. The gap between optimistic and pessimistic also shows how uncertain the task is. A wide gap suggests splitting the task or adding a spike.
def three_point(optimistic, likely, pessimistic):
"""Weighted average of three estimates, in hours."""
return (optimistic + 4 * likely + pessimistic) / 6
print(round(three_point(3, 5, 12), 1)) # 5.8The result, 5.8 hours, sits above the likely value of 5 because the pessimistic case is far away. That is the point: the formula pulls the estimate toward the risk.
Checking the plan against capacity
Once every task has an estimate, add them up and compare the total with your plannable hours. Plannable hours are what is left after meetings and the buffer, as worked out in the capacity step. The next function does this check.
def check_plan(tasks, capacity):
"""tasks is a list of (name, estimated_hours) pairs."""
total = sum(hours for _, hours in tasks)
return total, total <= capacity
tasks = [("Draft proposal", 6), ("Review pull requests", 4), ("Prepare demo", 5)]
total, fits = check_plan(tasks, capacity=22.4)
print(total, fits) # 15 TrueHere 15 hours of work fit within 22.4 plannable hours, with 7.4 hours to spare. This is a good sign, but it is not the end of the check. Ask whether your estimates are honest. If your history says you run about 50% over, test that case:
def check_plan(tasks, capacity):
"""tasks is a list of (name, estimated_hours) pairs."""
total = sum(hours for _, hours in tasks)
return total, total <= capacity
def padded_tasks(tasks, factor):
"""Scale every estimate by a factor based on your past overruns."""
return [(name, hours * factor) for name, hours in tasks]
tasks = [("Draft proposal", 6), ("Review pull requests", 4), ("Prepare demo", 5)]
total, fits = check_plan(padded_tasks(tasks, 1.5), capacity=22.4)
print(total, fits) # 22.5 FalseThe plan now misses by 0.1 hours. That is too close to call, and it tells you something useful: this plan has no real slack in the pessimistic case. You can drop a task, shrink one, or accept the risk with open eyes.
Your overrun factor is not a universal 1.5. Compute it from your own review: divide actual hours by estimated hours for the tasks you finished last week. Over a few weeks the number settles, and you can apply it directly.
What to do when the plan does not fit
If the total is above capacity, you have exactly four options. Pick one deliberately instead of hoping the week goes well.
- Cut scope. Remove a task, or reduce what "done" means for it.
- Drop an outcome. Go back to your three outcomes and demote the least important one.
- Add capacity. Move a meeting, decline an optional one, or find hours elsewhere. Be careful: this often means working longer, which defeats the purpose of the buffer.
- Delegate or defer. Hand a task to someone else or move it to next week.
Don't take the fifth option, which is to leave the plan as it is and plan to work faster. It is the most common choice and the least reliable.
Common errors
- Estimating at the outcome level. "Proposal: 15 hours" has no structure behind it. List the tasks first.
- Forgetting dependencies. A review that needs a colleague's feedback can't be finished on Monday if they reply on Wednesday. Put the wait on the calendar as a note, and schedule the dependent task after it.
- Estimating only the fun parts. Writing the code gets 4 hours, but testing, documentation, and the pull request get nothing. List the full path to "done".
- Treating estimates as promises. An estimate is a planning tool. When reality differs, record the difference in the retrospective and adjust the next estimate.
- Never comparing estimates with actuals. Without that comparison, your numbers never improve. A simple note beside each task, such as "est 3, took 5", is enough.
A short worked pass
Suppose your outcome is "Demo ready for Friday's review". You break it down and estimate:
| Task | Estimate (h) |
|---|---|
| Spike: check whether the export feature works with the sample data | 1.5 |
| Build the demo flow | 4 |
| Write the demo script | 1.5 |
| Rehearse twice | 1 |
| Fix problems found in rehearsal | 2 |
| **Total** | **10** |
If your plannable hours are 22.4 and another outcome needs 8, the total is 18. That fits with 4.4 hours of room. The spike carries the most uncertainty, so if it shows the export feature is broken, you will know on Monday and can renegotiate scope early.
Exercise
Your plannable hours for the week are 20. You have three tasks: 7 hours, 6 hours, and 5 hours. Your past reviews show you usually take about 40% longer than you estimate. Does the plan fit, and what is one sensible change if it doesn't?
Show answer
The raw total is 18 hours, which fits within 20. Applying the 1.4 factor gives 18 × 1.4 = 25.2 hours, which does not fit. A sensible change is to defer or shrink the least important task, for example dropping the 5-hour task, which leaves 13 × 1.4 = 18.2 hours. That fits within 20 with a small margin.
Exercise
You are asked to estimate "Migrate the reports to the new tool", and you have never used the new tool. How should you handle the estimate this week?
Show answer
Don't give one number for the whole job. Create a time-boxed spike task, for example 90 minutes to try the tool on one report and note what is hard. Put the spike in this week's plan. Estimate the migration itself once the spike has shown the likely effort, either later in the week or at the next planning session.