Sub topic 2
Picking a time, length, and agenda
This chapter covers the second step of the weekly planning routine: deciding when the session happens, how long it runs, and what it contains. It assumes you already have a calendar application, a task list or notes tool, and a rough idea of your regular commitments. It also assumes you have read the chapter on why weekly planning matters. The goal here is a session you can repeat without having to decide anything new each time.
Why cadence matters
A planning session only helps if it happens. A session you skip every third week gives you a plan that is out of date most of the time. Cadence means the regular rhythm of the session: the same day, the same time, the same length. A fixed cadence removes the weekly decision of "should I plan now?" and turns the session into a habit tied to a calendar slot.
Three choices define the cadence:
- When in the week the session happens.
- How long it lasts.
- What it covers, and in what order.
You make these choices once, test them for a few weeks, and adjust. You do not need to get them right on the first try.
Choosing the time
There are two common slots, and each has trade-offs.
| Slot | Advantages | Drawbacks |
|---|---|---|
| Friday afternoon | The week is fresh in memory, so the review is accurate. You can leave work with a plan and rest without carrying open loops. | You are tired. Colleagues may have left, so you cannot ask questions. Next week's calendar may not be final. |
| Monday morning | You are rested. The calendar is closer to final, and you see new messages from the weekend. | The session competes with urgent requests. Monday meetings may start before you finish. Your review relies on memory of last week. |
A third option, Sunday evening, works for some people but moves work into personal time. Treat it as a last resort and not a default.
Whatever slot you pick, apply these rules:
- Put the session on your calendar as a recurring event. An unscheduled session loses to any meeting that is.
- Choose a time when you are alert enough to make trade-offs. Planning at the end of a long day produces optimistic plans.
- Choose a time when you can see the next seven to ten days of calendar. If your colleagues schedule most meetings on Monday morning, a Friday session may miss them.
- Protect it. Mark the event as busy so others cannot book over it.
A workable compromise is a split. Do the review on Friday (about ten minutes) and the planning on Monday morning. This only works if you keep both events. Start with one slot and split later if you need to.
Choosing the length
The overall session runs 30 to 60 minutes. A shorter session usually means you skip the capacity check, which is the part that stops over-commitment. A longer session usually means you are re-planning tasks that should have been settled earlier, or you are collecting inbox items during the session instead of during the week.
Use this guide:
- 30 minutes: your work is mostly predictable, your inbox is small, and you have run the routine for a while.
- 45 minutes: a typical week with a mix of meetings and project work.
- 60 minutes: you are new to the routine, your week is complex, or you are planning for a team.
If a session regularly runs over, do not just extend it. Find out which section overran. The usual causes are an inbox that has not been emptied during the week, too many candidate outcomes, and detailed task estimation that belongs to a separate planning step.
Choosing the agenda
An agenda gives each part of the session a time box, which is a fixed amount of time after which you move on. Time boxes stop one part, usually the review, from using all the time. The agenda also keeps the order stable. The order matters because each step depends on the one before it: you review before you choose outcomes, and you check capacity before you schedule.
The template below is the agenda used throughout this tutorial. Copy it into your notes tool and create a new copy each week.
# Weekly plan: week of YYYY-MM-DD
## Review (10 min)
- Finished last week:
- Carried over (and why):
- Dropped:
## Outcomes (max 3)
1.
2.
3.
## Capacity (10 min)
- Working hours:
- Meetings and fixed commitments:
- Focus hours available:
- Buffer (20%):
- Plannable hours:
## Time blocks (15 min)
| Day | Block | Outcome |
|-----|-------|---------|
| | | |
## Retrospective (5 min)
- What worked:
- What to change next week:The time boxes add up to 40 minutes, with the outcomes section taking the remaining time you allot. The sections map to later chapters:
- Review looks back. You list what you finished, what carries over, and what you drop. Each carried-over item needs a reason. If you cannot write one, the item is probably a candidate to drop.
- Outcomes is a limit of three. An outcome is a result you want at the end of the week, such as "proposal sent to the client", not a task such as "work on proposal". Three is a cap, not a target. Fewer is fine.
- Capacity converts the calendar into hours you can really use.
- Time blocks places the outcomes on specific days and times.
- Retrospective closes the loop by asking what to change next time.
How the pieces fit together
The sequence has a direction. Review feeds outcomes, outcomes and capacity feed estimation and blocks, and the retrospective feeds the next review.
Capacity comes after outcomes in this template, but you often glance at the calendar while choosing outcomes. Do that, but write the numbers down in the capacity section so the check is explicit.
A worked example of the capacity section
The capacity section is the one most often skipped, so it helps to see the arithmetic. This function subtracts fixed commitments from working hours and then reserves a share as buffer.
def plannable_hours(working_hours, fixed_hours, buffer_ratio=0.2):
"""Hours left for planned work after meetings and a buffer."""
focus = max(working_hours - fixed_hours, 0)
return focus * (1 - buffer_ratio)
capacity = plannable_hours(working_hours=40, fixed_hours=12)
print(capacity) # 22.4With 40 working hours and 12 hours of meetings, you have 28 focus hours. Reserving 20% as buffer leaves 22.4 hours to plan against. The max(..., 0) guard handles a week where meetings exceed working hours, so the result never goes negative.
You then compare the estimated hours of your chosen work with that number.
def check_plan(tasks, capacity):
"""tasks is a list of (name, estimated_hours) pairs."""
total = sum(hours for _, hours in tasks)
return total, total <= capacity
tasks = [("Draft proposal", 6), ("Review pull requests", 4), ("Prepare demo", 5)]
total, fits = check_plan(tasks, capacity=22.4)
print(total, fits) # 15 TrueThe plan totals 15 hours against 22.4 available, so it fits with room to spare. If the check returned False, you would cut an outcome or move it to next week before committing. Later chapters cover estimation and buffers in detail. For now, note that the agenda reserves ten minutes for this check.
Common errors when setting up the cadence
- No recurring event. The session depends on remembering. Fix: create the calendar event first, before anything else.
- Time boxes ignored. The review takes 25 minutes and the rest is rushed. Fix: set a timer, and when it ends, write "unfinished" and move on.
- Planning before reviewing. You choose outcomes without knowing what carried over, so you double-book yourself. Fix: keep the agenda order.
- Too many outcomes. The limit of three is the part people drop first. Fix: if you list five, rank them and move the bottom two to a "later" list.
- Choosing a slot that conflicts with the calendar's busiest period. Fix: look at four weeks of past calendars and choose the quietest 60 minutes.
- Never adjusting. A cadence that fails for three weeks needs to change. Fix: use the retrospective to ask whether the time, length, or agenda is the problem.
Putting it together
Before the next chapter, complete these actions:
- Pick a day and time for your session and create the recurring calendar event, marked busy.
- Copy the agenda template into your notes tool.
- Set the length to 45 minutes if you are unsure.
- Plan to review the setup after three sessions.
Exercise
Your Friday afternoon session keeps running to 75 minutes and you feel rushed in the capacity section. Name two likely causes and one change for each.
Show answer
One likely cause is that the review section overruns because last week's items were not tidied during the week. The change is to set a ten-minute timer for the review and write "unfinished" when it ends. Another likely cause is that you are choosing too many outcomes or collecting new inbox items during the session. The change is to cap outcomes at three and capture items into the inbox during the week. A third acceptable cause is that you are tired late on Friday, so the change is to move the session to a time when you are more alert or to split the review and the planning.
Exercise
You have 36 working hours, 14 hours of fixed meetings, and a 25% buffer. How many hours can you plan, and does a plan of 6, 5, and 7 estimated hours fit?
Show answer
Focus hours are 36 - 14 = 22. The buffer leaves 22 * 0.75 = 16.5 plannable hours. The plan totals 6 + 5 + 7 = 18 hours, which is more than 16.5, so it does not fit. You should cut or defer one outcome, or reduce the scope of the largest one.